Service/Activities

Message Broker Network

  • Consortium: GRNET, SRCE
  • Contact:
  • Funded resources: 5 PMs
  • Total cost: 26550 Euro
  • Duration: 12 months, as of May 01 2014

Operations Portal

  • Consortium: CNRS, GRNET
  • Contact:
  • Funded resources: 24 PMs
  • Total cost: 157100 Euro
  • Duration: 12 months, as of May 01 2014

Accounting Repository

  • Consortium: STFC
  • Contact:
  • Funded resources: 12 PM, 4800 Euro of extra cost
  • Total cost: 95469 Euro
  • Duration: 12 months, as of May 01 2014

Accounting Portal

  • Consortium: CESGA
  • Contact:
  • Funded resources: 6 PM
  • Total cost: 25380 Euro
  • Duration: 12 months, as of May 01 2014

SAM central services

  • Consortium: GRNET, SRCE
  • Contact:
  • Funded resources: 28 PM and 2500 Euro of extra costs
  • Total cost: 159900 Euro
  • Duration: 12 months, as of May 01 2014

Central monitoring services

  • Consortium: GRNET, SRCE
  • Contact:
  • Funded resources: 12 PM and 2500 Euro of extra costs
  • Total cost: 64710 Euro
  • Duration: 12 months, as of May 01 2014

Security monitoring and security operations support tools

  • Consortium: CESNET
  • Contact:
  • Funded resources: 4 PMs
  • Total cost (40% EGI.eu co-funding): 25600
  • Duration: 12 months, as of May 01 2014

Service registry (GOCDB)

  • Consortium: STFC
  • Contact:
  • Funded resources: 6 PM and 5581 Euro of extra costs
  • Total cost: 80963 Euro
  • Duration: 12 months, as of May 01 2014

Operations support services

  • Consortium: CYFRONET, GRNET
  • Contact:
  • Funded resources: 8 PMs
  • Total cost: 65400 Euro
  • Duration: 12 months, as of May 01 2014

Security coordination

  • Consortium: STFC, FOM, SNIC
  • Contact:
  • Funded resources: 20 PMs and 17000 Euro of extra costs
  • Total cost: 223371 Euro
  • Duration: 12 months, as of May 01 2014

Acceptance criteria

  • Consortium: IberGrid
  • Contact:
  • Funded resources: 10 PMs
  • Total cost: 56400 Euro
  • Duration: 12 months, as of May 01 2014

Collaboration tools/IT support

  • Consortium: CESNET
  • Contact:
  • Funded resources: 12 PMs
  • Total cost: 76800 Euro
  • Duration: 12 months, as of May 01 2014

Staged Rollout

  • Consortium: GRNET, SRCE
  • Contact:
  • Funded resources:
  • Total cost (40% EGI.eu co-funding):
  • Duration: 12 months, as of May 01 2014

Software provisioning infrastructure

  • Consortium: GRNET, CESGA
  • Contact:
  • Funded resources: 18 PMs
  • Total cost: 119160 Euro
  • Duration: 12 months, as of May 01 2014

Incident management helpdesk

  • Consortium: KIT
  • Contact:
  • Funded resources: 12 PMs and 18000 Euro of extra costs
  • Total cost: 124740 Euro (offered in-kind in 2014)
  • Duration: 12 months, as of May 01 2014

1st level support

(merged with second level support)

  • Consortium: IberGrid, CESNET
  • Contact:
  • Funded resources: 28 PMs
  • Total cost: 157280 Euro
  • Duration: 12 months, as of May 01 2014

2nd level support (core platform)

  • provided as part of other tasks and partially merged with 1st level support (aboe)

2nd level support (community platform)

  • Consortium: GRNET, SRCE
  • Contact:
  • Funded resources:
  • Total cost (40% EGI.eu co-funding):
  • Duration: 12 months, as of May 01 2014

Document EGI-InSPIRE Operational Tools Sustainability provides more information about the current technical specifications, support and maintenance activities of the following services: Operations Portal, GGUS, GOCDB, SAM, Messaging, Accounting Repository, and Accounting Portal.