EGI Core activities:PHASE I
Main | EGI.eu operations services | Support | Documentation | Tools | Activities | Performance | Technology | Catch-all Services | Resource Allocation | Security |
Service/Activities
Message Broker Network
- Consortium: GRNET, SRCE
- Contact:
- Funded resources: 5 PMs
- Total cost: 26550 Euro
- Duration: 12 months, as of May 01 2014
Operations Portal
- Consortium: CNRS, GRNET
- Contact:
- Funded resources: 24 PMs
- Total cost: 157100 Euro
- Duration: 12 months, as of May 01 2014
Accounting Repository
- Consortium: STFC
- Contact:
- Funded resources: 12 PM, 4800 Euro of extra cost
- Total cost: 95469 Euro
- Duration: 12 months, as of May 01 2014
Accounting Portal
- Consortium: CESGA
- Contact:
- Funded resources: 6 PM
- Total cost: 25380 Euro
- Duration: 12 months, as of May 01 2014
SAM central services
- Consortium: GRNET, SRCE
- Contact:
- Funded resources: 28 PM and 2500 Euro of extra costs
- Total cost: 159900 Euro
- Duration: 12 months, as of May 01 2014
Central monitoring services
- Consortium: GRNET, SRCE
- Contact:
- Funded resources: 12 PM and 2500 Euro of extra costs
- Total cost: 64710 Euro
- Duration: 12 months, as of May 01 2014
Security monitoring and security operations support tools
- Consortium: CESNET
- Contact:
- Funded resources: 4 PMs
- Total cost (40% EGI.eu co-funding): 25600
- Duration: 12 months, as of May 01 2014
Service registry (GOCDB)
- Consortium: STFC
- Contact:
- Funded resources: 6 PM and 5581 Euro of extra costs
- Total cost: 80963 Euro
- Duration: 12 months, as of May 01 2014
Operations support services
- Consortium: CYFRONET, GRNET
- Contact:
- Funded resources: 8 PMs
- Total cost: 65400 Euro
- Duration: 12 months, as of May 01 2014
Security coordination
- Consortium: STFC, FOM, SNIC
- Contact:
- Funded resources: 20 PMs and 17000 Euro of extra costs
- Total cost: 223371 Euro
- Duration: 12 months, as of May 01 2014
Acceptance criteria
- Consortium: IberGrid
- Contact:
- Funded resources: 10 PMs
- Total cost: 56400 Euro
- Duration: 12 months, as of May 01 2014
Collaboration tools/IT support
- Consortium: CESNET
- Contact:
- Funded resources: 12 PMs
- Total cost: 76800 Euro
- Duration: 12 months, as of May 01 2014
Staged Rollout
- Consortium: GRNET, SRCE
- Contact:
- Funded resources:
- Total cost (40% EGI.eu co-funding):
- Duration: 12 months, as of May 01 2014
Software provisioning infrastructure
- Consortium: GRNET, CESGA
- Contact:
- Funded resources: 18 PMs
- Total cost: 119160 Euro
- Duration: 12 months, as of May 01 2014
Incident management helpdesk
- Consortium: KIT
- Contact:
- Funded resources: 12 PMs and 18000 Euro of extra costs
- Total cost: 124740 Euro (offered in-kind in 2014)
- Duration: 12 months, as of May 01 2014
1st level support
(merged with second level support)
- Consortium: IberGrid, CESNET
- Contact:
- Funded resources: 28 PMs
- Total cost: 157280 Euro
- Duration: 12 months, as of May 01 2014
2nd level support (core platform)
- provided as part of other tasks and partially merged with 1st level support (aboe)
2nd level support (community platform)
- Consortium: GRNET, SRCE
- Contact:
- Funded resources:
- Total cost (40% EGI.eu co-funding):
- Duration: 12 months, as of May 01 2014
Document EGI-InSPIRE Operational Tools Sustainability provides more information about the current technical specifications, support and maintenance activities of the following services: Operations Portal, GGUS, GOCDB, SAM, Messaging, Accounting Repository, and Accounting Portal.