EGI-Engage project: Main page WP1(NA1) WP3(JRA1) WP5(SA1) PMB Deliverables and Milestones Quality Plan Risk Plan Data Plan
Roles and
responsibilities
WP2(NA2) WP4(JRA2) WP6(SA2) AMB Software and services Metrics Project Office Procedures




This page is providing yearly activity plan for WP2 in PY2


Project month Calendar month Project Tasks Work to be done Goal  (measurable) Owner (responsible person) Comments
14 April 2016 Task 2.1 Newsletter - issue 23 n.a. SC
14 April 2016 Task 2.1 EGI Conference 2016 n.a SC
17 July 2016 Task 2.1 Newsletter - issue 24 n.a. SC
Task 2.1 New website published n.a. SC
19 Sept 2016 Task 2.1 DI4R 2016 n.a SC
Task 2.2 Community service portfolio published
19 Sept 2016 Task 2.2 Revised service catalogue completed The service catalogue is complete in the IMS and approved by the SSB SC
20 Oct 2016 Task 2.1 Newsletter - issue 25 n.a. SC
20 Oct 2016 Task 2.1 Assessment of DI4R n.a. SC
20 Oct 2016 Task 2.1 Opening bid for Autumn event n.a. SC
20 Oct 2016 Task 2.2 Pay-for-use prototype moved into production SH
21 Nov 2016 Task 2.1 Updated Communications Plan 1 report SC
22 Dec 2016 Tasj 2.2 EGI Impact report
24 Feb 2017 Task 2.2 Procurement study completed D2.11 published BJ
24 Feb 2017 Task 2.2 ISO9k+20k certification achieved
24 Feb 2017 Task 2.2 Legal and business analysis of EGI Foundation as full broker (now that VAT issues seem to be cleared)
30 Aug 2017 Task 2.1/2.3 Business use cases 3 SC
30 Aug 2017 Task 2.1 Case studies 10 SC


To be added in the table above for WP2.3:

  • 08.2016: Market Analysis Report of selected sectors (D2.10 published)
  • 08.2016: General business brochure updated
  • 08.2016: 1st business case study written (e.g. Terra due) + potential video
  • 09.2016: Business pilot run: Sentinel data with 2 SMEs
  • 12.2016: Business pilot run: CloudEO follow-up result from TEISS
  • 12.2016: Service offering developed for fishery and marine (based on D2.6/2.7 analysis)
  • 02.2017: Business pilot run: CloudSME based on MoU
  • 02.2017: Service offering developed for agri-food (based on D2.10)
  • 02.2017: Publication of national/regional SME engagement success stories