Alert.png The wiki is deprecated and due to be decommissioned by the end of September 2022.
The content is being migrated to other supports, new updates will be ignored and lost.
If needed you can get in touch with EGI SDIS team using operations @ egi.eu.

EGI-Engage:TASK JRA1.5 Resource Allocation – e-GRANT

From EGIWiki
Jump to navigation Jump to search
EGI-Engage project: Main page WP1(NA1) WP3(JRA1) WP5(SA1) PMB Deliverables and Milestones Quality Plan Risk Plan Data Plan
Roles and
responsibilities
WP2(NA2) WP4(JRA2) WP6(SA2) AMB Software and services Metrics Project Office Procedures


Task leader: Tomas Szepieniec/CYFRONET
Task leader deputy: Roksana Rozanska/CYFRONET

Mailing list: egrant-team@cyfronet.pl


Involved Partner

  • CYFRONET

Roadmap

Task number

(5.X)

Task name

Start date

(MM/YY)

Release Date

(MM/YY)

Status

(Planned/Done)

Dependencies from other tasks

(insert only task number)

Issues
5.1 Defining extenstions and interface with other tools and processes. 04/15 12/15 In progress
5.2 Continual implementation of improvement needed for resources allocation process 04/15 08/17 Planned 5.1
5.3 Aligment with EGI SLA framework for existing process 04/15 06/15 In progress 5.1
5.4 Implementing support for tracing site configuration for allocated SLA 07/15 06/16 Planned 5.1, 5.2
5.5 Integration with market-place 10/16 03/17 Planned 5.1
5.6 Integration with EGI monitoring framework  01/16 12/16 Planned 5.1
5.7 Integration with LTOS portal 04/15 12/15 In progress 5.1
5.8 Integration with EGI Accounting system 02/16 12/16 Planned 5.1, 5.2
5.9 Integration with EGI Accounting Portal 02/16 12/16 Planned 5.1, 5.2
5.10 Integration with EGI authorization platform - UNITY 04/15 09/15 In progress 5.1, 5.2
5.11 further integration with GOCDB 06/16 06/16 Planned 5.1, 5.2
5.12 Pilot execution of pay-for-use process in e-GRANT 08/15 11/15 Planned
5.13 First prototype of pay-for-use process in production 01/16 03/16 Planned 5.1
5.14 Extending support for pay-for-use process   03/16 12/16 Planned 5.1
5.15 Extenstion needed for including new types of EGI services  10/16 07/17 Planned 5.1
5.16 Final release of e-GRANT 08/17 08/17 Planned 5.2-5.7