EGI-Engage:WP2-PY2-Roadmap
Jump to navigation
Jump to search
This page is providing yearly activity plan for WP2 in PY2
Project month | Calendar month | Project Tasks | Work to be done | Goal (measurable) | Owner (responsible person) | Comments |
---|---|---|---|---|---|---|
14 | April 2016 | Task 2.1 | Newsletter - issue 23 | n.a. | SC | |
14 | April 2016 | Task 2.1 | EGI Conference 2016 | n.a | SC | |
17 | July 2016 | Task 2.1 | Newsletter - issue 24 | n.a. | SC | |
Task 2.1 | New website published | n.a. | SC | |||
19 | Sept 2016 | Task 2.1 | DI4R 2016 | n.a | SC | |
19 | Sept 2016 | Task 2.2 | Impact assessment brochure published | |||
Task 2.2 | Community service portfolio published | |||||
19 | Sept 2016 | Task 2.2 | Revised service catalogue completed | The service catalogue is complete in the IMS and approved by the SSB | SC | |
20 | Oct 2016 | Task 2.1 | Newsletter - issue 25 | n.a. | SC | |
20 | Oct 2016 | Task 2.1 | Assessment of DI4R | n.a. | SC | |
20 | Oct 2016 | Task 2.1 | Opening bid for Autumn event | n.a. | SC | |
20 | Oct 2016 | Task 2.2 | Pay-for-use prototype moved into production | SH | ||
21 | Nov 2016 | Task 2.1 | Updated Communications Plan | 1 report | SC | |
24 | Feb 2017 | Task 2.2 | Procurement study completed | D2.11 published | BJ | |
24 | Feb 2017 | Task 2.2 | ISO9k+20k certification achieved | |||
24 | Feb 2017 | Task 2.2 | Legal and business analysis of EGI Foundation as full broker (now that VAT issues seem to be cleared) | |||
30 | Aug 2017 | Task 2.1/2.3 | Business use cases | 3 | SC | |
30 | Aug 2017 | Task 2.1 | Case studies | 10 | SC | |