Alert.png The wiki is deprecated and due to be decommissioned by the end of September 2022.
The content is being migrated to other supports, new updates will be ignored and lost.
If needed you can get in touch with EGI SDIS team using operations @ egi.eu.

Difference between revisions of "EGI-Engage:WP6-PY1-Roadmap"

From EGIWiki
Jump to navigation Jump to search
Line 225: Line 225:
! Comments
! Comments
|-
|-
! 1
! 12
| Task 6.9  
| Task 6.9  
| EPOS requirements analysis and outline of pilot use cases are agreed<br>  
| EPOS requirements analysis and outline of pilot use cases are agreed<br>  
|  
|  
* AAI requirements analysed
* AAI requirements analysed and the EPOS AAI architecture envisaged.
* Basic multidisciplinary AAI use case, dealing with the discovery of heterogeneous data from the ICS-C portal, defined
* Basic multidisciplinary AAI use case, dealing with the discovery of heterogeneous data from the ICS-C portal, defined
* An extended, single discipline, computational oriented use case defined<br>  
* An extended, single discipline, computational oriented use case defined<br>  
Line 235: Line 235:
| <br>
| <br>
|-
|-
! 1
!
| Task 6.2
|
|  
|  
|  
|  

Revision as of 13:05, 11 June 2015

EGI-Engage project: Main page WP1(NA1) WP3(JRA1) WP5(SA1) PMB Deliverables and Milestones Quality Plan Risk Plan Data Plan
Roles and
responsibilities
WP2(NA2) WP4(JRA2) WP6(SA2) AMB Software and services Metrics Project Office Procedures




This page is providing yearly activity plan for WP6 in PY1



YIN

Project month

Project Tasks

Work to be done

Goal 

(measurable)

Owner

(reponsible person)

Comments
1 Task 6.8

1) Portal Design Specification

2) Portal prototype

1) Agreement on task responsibilities of participating parties by May 2015

2) First version of the portal specification to be drafted by the end of Summer 2015

3) First prototype of the portal aims to be delivered by Dec 2015

  • Portal Design Specification: EISCAT (Ingemar Haggstrom)
  • Portal prototype SNIC (Ake Sandgren)
  • EGI contribution (Yin Chen)

1
2




3



4



5



6



7



8



9



10



11



12




ENOL

Project month

Project Tasks

Work to be done

Goal 

(measurable)

Owner

(reponsible person)

Comments
1 Task 6.2 Definition of the technical use cases support process Establishment of a procedure for handling use case support, RT queue for tracking use cases Gergely Sypos / Enol Fernandez
X Task 6.2 Pilot usage of EGI infrastructure by HBP XX XXX
XX Task 6.2 Pilot usage of EGI infrastructure by LOFAR/SKA XX XX
9 Task 6.7 Assisted pattern recognition tools integrated with EGI for citizen science XXX Jesús Marco/Fernando Aguilar
12 Task 6.7 Data flow handler and basic R tools to integrate and process data from Ecological Observatories on EGI XXX Jesús Marco/Fernando Aguilar)


DIEGO

Project month

Project Tasks

Work to be done

Goal 

(measurable)

Owner

(reponsible person)

Comments
12 Task 6.9 EPOS requirements analysis and outline of pilot use cases are agreed
  • AAI requirements analysed and the EPOS AAI architecture envisaged.
  • Basic multidisciplinary AAI use case, dealing with the discovery of heterogeneous data from the ICS-C portal, defined
  • An extended, single discipline, computational oriented use case defined
Daniele Balio (EPOS/INGV), Diego Scardaci (EGI.eu/INFN)

2



3



4



5



6



7



8



9



10



11



12




GERGELY

Project month

Project Tasks

Work to be done

Goal 

(measurable)

Owner

(reponsible person)

Comments

3

Task 6.1

Define EGI's training plan for the 1st year of EGI-Engage

M6.1 Joint training programme for the first project year (With EUDAT, PRACE, CCs, NGIs, UCB)

Gergely Sipos

Document was delivered at the end of May: http://go.egi.eu/trainingplan

5

Task 6.1

Setup training VO on the Federated Cloud

Register training robot certificate, generate proxies for students and trainers

Prepare training materials for 3.5 course (slides + hands-on exercises incl. VM images and datasets) 

Test training material and setup by July 15, deliver courses in second part of July

Deliver two courses on EGI Federated Cloud at 'Software Carpentry workshop' (SAP, UK) and HPCS (Amsterdam)

Gergely Sipos

10

Task 6.1

Work with Resource providers of the training VO to identify suitable business model for continued provisioning of thevirtualised training e-infrastructure that can operate 24/7 to serve EGI-related courses and self-paced training needs.

Suitable business model for continued operation of the training VO in EGI

Gergely Sipos


10

Task 6.1

Prepare module based on the joint use case that has been identified and documented during the EGI-EUDAT meeting at the EGI Conference in Lisbon. (FedCloud, B2Find, B2Drop, B2Safe)

Joint training module with EUDAT 

Diego Scardaci

F2F delivery at the EGI Community Forum? 

8

Task 6.1

After the platform components are integrated and tested develop training for the NGI user support teams and EGI.eu staff on how to support long-tail users with the platform. 

Training module on the 'EGI long tail of science' platform

Diego Scardaci, Peter Solagna

F2F delivery at the EGI Community Forum?

8

Task 6.1

A module about security policy, procedures and interoperability solutions in the various e-infrastructures, with possible involvement of EUDAT. The content will be developed for a joint event that will be held in the autumn, then will be shared as a training module in the marketplace.


Joint event and training module with PRACE

Dave Kelsey

Event approx in October (date, venue TBD)

5

Task 6.1

The module will target those who prepare and those who endorse VM images for scientific/training purposes. The module will define the characteristics of ‘secure’ VM images, will teach how to prepare such images, and will demonstrate how to assess the security characteristics of such images. 


Training module on Virtual Machine preparation and certification in the EGI Federated Cloud.


Vincenzo Spinoso

To be developed by security experts funded in T6.1: CERN, CESNET, LIP, NIKHEF

10

Task 6.1

Training module on Incident handling in the EGI Federated Cloud. 

Dave Kelsey

To be developed by security experts funded in T6.1: CERN, CESNET, LIP, NIKHEF

F2F delivery at EGI Community Forum?

12

Task 6.1

Exploring possibility of training module developments with other tasks on the following topics:

1. Open Data Processing solution from EGI (by members of task JRA2.1).

2. GPGPU-computing in EGI (by members of task JRA2.4 and NGI-BG).

3. Deploying clouds and federated clouds for scientific and educational purposes (by members of the Federated Cloud collaboration).

4. iRODS training (in collaboration with NGI-FR and the DIRAC team).

Additional training modules

Gergely Sipos

F2F delivery at EGI Community Forum?

4 Task 6.1

Ensure that the Training Marketplace is used accross EGI, and that it can collect and provide the relevant details about events, content, etc and the impact.

Provide templates and surveys for EGI trainers to be able to collect relevant metrics. 

Mechanisms and tools to assess impact of training activities. Gergely Sipos
12 Task 6.3 (ELIXIR)

Collect use cases from ELIXIR-EXCELERATE, CC members, EGI members (e.g. GAPF VT), then select the most relevant ones for the CC to work with. Analyse use cases from the technical perspective to capture requirements for e-infra and ELXIR RI services. 

Life science requirements analysis and driver use case(s) with implementation roadmap are agreed

M6.3: Life science requirements analysis and driver use case(s) with implementation roadmap are agreed Tommi Nyronen
12 Task 6.4 (BBMRI)

Collect use cases from the BBMRI community and from CC members then select the most relevant ones for the CC to work with. Analyse use cases from the technical perspective to capture requirements for e-infra and BBMRI RI services. Design suitable technical architecture to address the requirements. 

M6.2: Security and privacy requirements and secure storage architectural design are agreed Petr Holub
7 Task 6.5 (MoBrain) Discuss options for the implementation of a fully integrated MoBrain portal (built on N4U and WeNMR technologies, considering work in WestLife VRE project). Reach agreement on the concept of the integrated portal and on CC partners' responsibilty for developing it. Agreement on the concept of the integrated portal and on CC partners' responsibilty for developing it. Alexander Bonvin
12 Task 6.5 (MoBrain) D6.4: Fully integrated MoBrain web portal (OTHER) Alexander Bonvin