EGI-Engage:Risk Plan

From EGIWiki
Revision as of 10:04, 15 September 2015 by Krakow (talk | contribs)
Jump to navigation Jump to search
EGI-Engage project: Main page WP1(NA1) WP3(JRA1) WP5(SA1) PMB Deliverables and Milestones Quality Plan Risk Plan Data Plan
Roles and
responsibilities
WP2(NA2) WP4(JRA2) WP6(SA2) AMB Software and services Metrics Project Office Procedures


Baustelle.png This page is under construction.



Help and support: quality@egi.eu

This page is proving rules regarding risk management within EGI-Engage project.


Risk process.png


  1. Risk identification
    • goal: determining which risk can affect the project and documenting it in Risk registry
    • a process that is used to find, recognize, and describe the risks that could affect the achievement of objectives.
  2. Risk analysis
    • goal: assessing likelihood and consequences
    • a process that is used to understand the nature, sources, and causes of the risks that you have identified and to estimate the level of risk. It is also used to study impacts and consequences and to examine the controls that currently exist.
  3. Risk evaluation
      • a process that is used to compare risk analysis results with risk criteria in order to determine whether or not a specified level of risk is acceptable or tolerable.
  4. Risk monitor
    • a process which goal is to review of existing Risk database conducted periodically

Roles and responsibilities

Quality and Risk Manager:

Risk Manager


Technical Coordinator:


Work Package leaders:

Risk management team members 




Timing

Risk management process is daily responsibility of EGI-Engage Work Package leaders. Risks should be treated and identified on daily basis.

Periodically as part of the review process Project Management Board is involved to review status of risk management performed by Work Package leaders.

Definitions

Risk

  • iso 31000: a risk is defined as the effect of uncertainty on objectives
  • PMBok: a risk is an uncertain event or condition that if it occurs, has a positive or negative effect on a Project's Objectives

Risk Registry (Access restricted)

  • database of identified risks with recorded their analysis and response planning


Each risk in Risk Registry is described as follow:

  • Risk no - unique risk identifier
  • Risk - one sentence description of the risk
  • Risk level - (Low/Medium/High/Extreme) The level of risk is its magnitude. It is estimated by considering and combining consequences and likelihoods. A consequence is the outcome of an event and has an effect on objectives. Likelihood is the chance that something might happen.
  • Likelihood - (Unlikely, Possible, Likely, Almost Certain) Likelihood (probability) is the chance that something might happen.
  • Consequences - (Minor/Moderate/Major/Catastrophic) A consequence (impact) is the outcome of an event and has an effect on objectives.
  • Treatment - (Protective, mitigation measures, recovery activities, controls) description of possible treatment of the risk
  • Impact - description of impact risk will have in case of occurrence
  • Deliverables - Deliverables which might me impacted in case of occurrence
  • KPIs - Impacted KPIs
  • Objective - Impacted Objective
  • WP1-WP6 - Impacted WPs
  • Owner - A risk owner is WP that has been given the authority to manage a particular risk and is accountable for doing so.
  • Trend - (Stable, Improving, Degrading, New, Deprecated) Indication of risk trend comparing to previous risk review period
  • Comment for PMB - additional comments for PMB after AMB review


Risk identification

Input: Work Package leaders expertise 

Output: Initial Risk entry in Risk registry

Risk identification is a process that involves finding, recognizing, and describing the risks that could affect the achievement of an organization’s objectives. It is used to identify possible sources of risk in addition to the events and circumstances that could affect the achievement of objectives. It also includes the identification of potential consequences.

Risk are identified:

  1. Periodicaly: 
    • During Risk registry review through interviews and brainstorming with Work Package leaders
  2. On daily basis:
    • For all newly identified risks EGI Engage risk entry template should be filled in (Part Risk Description)
    • Sent the document to Quality Manager (quality@egi.eu)


Risk analysis

Input: risk entry in Risk registry

Output: risk likelihood and consequences assessment, risk level calculation

The level of likelihood and consequences for each risk is evaluated during the interviews with Work Package leaders performed by Quality manager. 

Risk rating (level) is calculated according to Likelihood and consequences matrix:

Risk likelihood and consequences matrix (risk level)

The matrix is a grid for mapping the consequences and likelihood of each risk occurrence and its impact to the project objectives if that risk occurs. Risks are prioritized according to their potential implications on project objectives.

Likelihood Consequences
Minor Moderate Major Catastrophic
Unlikely Low Low Medium High
Possible Low Medium High High
Likely Medium High High Extreme
Almost Certain High High Extreme Extreme

Risk evaluation

Input:

Output:


Risk level
Treatment
PMB involvement
Low
  • accept
  • define recovery activities
Informed
Medium
  • define mitigation activities
Informed
High
  • add controls
  • define recovery activities
Consulted
Extreme
  • add controls
  • define contingency plan
  • define recovery activities
Responsible



Protective measures: (activities designed to reduce the chances of a disruptive event occurring - likelihood)

Mitigation measures: (activities designed to minimize the severity of the event once it has occurred.)

Recovery activities: (activities serve to bring back disrupted systems and infrastructure.)

Contingency plans: (process-level documents describe what an organization can do in the aftermath of a disruptive event; they are usually triggered based on input from the emergency management team.)

Controls: (additional controls applied to it in order to reduce it to an acceptable level. What the appropriate additional controls might be, whether they can be afforded.)

Risk monitor

Input:

Output:

Risk review process

A review is an activity. Review activities are carried out in order to determine whether something is a suitable, adequate, and effective way of achieving established objectives.

In general, ISO 31000 expects you to review your risk management framework and your risk management process. It specifically expects you to review your risk management policy and plans as well as your risks, risk criteria, risk treatments, controls, residual risks, and risk assessment process.