= Deliverables<br> = | = Deliverables<br> = | ||
{| class="wikitable" | {| class="wikitable" | ||
Line 9: | Line 9: | ||
! Code | ! Code | ||
! Title | ! Title | ||
! WP(s) | |||
! Lead Participant | |||
! Type | |||
! Dissemination level | |||
! Delivery PM | ! Delivery PM | ||
! Description<br> | ! Description<br> | ||
|- | |- | ||
! | !D 1.1 | ||
| Quality plan for Period 1 | |Quality plan for Period 1 | ||
| M03 | |WP 1 | ||
| | |EGI.eu | ||
|R | |||
|PU | |||
|M03 | |||
| | |||
|- | |||
!D 2.1 | |||
|Communications, Dissemination and Engagement Strategy | |||
|WP 2 | |||
|EGI.eu | |||
|R | |||
|PU | |||
|M03 | |||
| | |||
|- | |- | ||
! | !D 2.2 | ||
| | |Master Model for SME engagement | ||
| | |WP 2 | ||
| | |EGI.eu | ||
|R | |||
|PU | |||
|M06 | |||
| | |||
|- | |- | ||
! | !D 2.3 | ||
| | |Concept of EGI Marketplace | ||
| | |WP 2 | ||
| | |SWING | ||
|R | |||
|PU | |||
|M06 | |||
| | |||
|- | |- | ||
! | !D 2.4 | ||
| | |Data Management Plan | ||
| | |WP 2 | ||
| | |EGI.eu | ||
|R | |||
|PU | |||
|M06 | |||
| | |||
|- | |- | ||
! | !D 3.1 | ||
| | |Technical design of the new Accounting Portal and implementation plan | ||
| | |WP 3 | ||
| | |CSIC | ||
| | |R | ||
|PU | |||
|M06 | |||
| | |||
|- | |- | ||
! | !D 4.1 | ||
|CANFAR integration roadmap | |||
|WP 4 | |||
|INFN | |||
|R | |||
|PU | |||
|M06 | |||
| | |||
|- | |- | ||
! | !D 1.2 | ||
| | |Risk analysis and risk response for Period 1 | ||
|WP 1 | |WP 1 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M08 | |||
| | |||
|- | |||
!D 4.2 | |||
|VM snapshot support: OCCI extension, final specification | |||
|WP 4 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M09 | |||
| | |||
|- | |||
!D 4.3 | |||
|Resource template changes: OCCI extension, final specification | |||
|WP 4 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M09 | |||
| | |||
|- | |||
!D 6.1 | |||
|Assisted pattern recognition tools integrated with EGI for citizen science | |||
|WP 6 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M09 | |||
| | |||
|- | |||
!D 6.2 | |||
|Data repository for DARIAH | |||
|WP 6 | |||
|INFN | |||
|OTHER | |||
|PU | |||
|M11 | |||
| | |||
|- | |||
!D 2.5 | |||
|EGI Governance: Analysis and Recommendations | |||
|WP 2 | |||
|EGI.eu | |||
|R | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 2.6 | |||
|Report on data sharing policies and legal framework in fishery and marine sciences data sector | |||
|WP 2 | |||
|FAO | |||
|R | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 2.7 | |||
|Market Report on the fishery and marine sciences data sector | |||
|WP 2 | |||
|Engineering | |||
|R | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 3.2 | |||
|Design of the EGI Service Registry and Marketplace | |||
|WP 3 | |||
|SWING | |||
|R | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 3.3 | |||
|Accounting Repository release | |||
|WP 3 | |||
|STFC | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 3.4 | |||
|First release of the operational tools WP 3 | |||
|CNRS | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 4.4 | |||
|Relocating VM instances between providers, final specification | |||
|WP 4 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 4.5 | |||
|Deployment of a gCube release with Federated Cloud support | |||
|WP 4 | |||
|Engineering | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 6.3 | |||
|Production portal for EISCAT_3D | |||
|WP 6 | |||
|EISCAT | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 6.4 | |||
|Fully integrated MoBRAIN web portal | |||
|WP 6 | |||
|GNUBILA | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |- | ||
! | !D 6.5 | ||
| | |Final version of Multi-Source Distributed Real-Time Search and Information Retrieval application | ||
|WP 6 | |||
|GWDG | |||
|OTHER | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 6.6 | |||
|Data flow handler and basic R tools to integrate and process data from Ecological Observatories on EGI | |||
|WP 6 | |||
|CSIC | |||
|DEM | |||
|PU | |||
|M12 | |||
| | |||
|- | |||
!D 6.7 | |||
|Implementation and evaluation of AMBER and/or GROMACS | |||
|WP 6 | |||
|CIRMMP | |||
|R | |||
|PU | |||
|M13 | |||
| | |||
|- | |||
!D 1.3 | |||
|Report of quality status and quality plan for Period 2 | |||
|WP 1 | |WP 1 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M14 | |||
|- | |||
!D 3.5 | |||
|First release of the new Accounting Portal deployed in production | |||
|WP 3 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M14 | |||
| | |||
|- | |- | ||
! | !D 6.8 | ||
| | |Analysis of requirements on biobank and study workflows | ||
|WP | |WP 6 | ||
| | |BBMRI ERIC | ||
| | |R | ||
|PU | |||
|M14 | |||
| | |||
|- | |||
!D 6.9 | |||
|web portals for tsunami wave propagation simulations and for WRF-based weather simulation | |||
|WP 6 | |||
|AS | |||
|OTHER | |||
|PU | |||
|M14 | |||
| | |||
|- | |- | ||
! | !D 2.8 | ||
| | |Communications, Dissemination and Engagement Report and Updated Strategy | ||
|WP 2 | |WP 2 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M15 | |||
| | |||
|- | |- | ||
! | !D 2.9 | ||
| | |EGI Sustainability and Business Development Plan | ||
|WP 2 | |WP 2 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 3.6 | |||
|Analysis on techniques to manage big data on the EGI accounting system | |||
|WP 3 | |||
|STFC | |||
|R | |||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 4.6 | |||
|e-Infrastructures integration report | |||
|WP 4 | |||
|INFN | |||
|R | |||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 5.1 | |||
|Report on the evolution of the EGI Operations | |||
|WP 5 | |||
|EGI.eu | |||
|R | |||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 5.2 | |||
|Platforms for the long-tail of science | |||
|WP 5 | |||
|CNR | |||
|R | |||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 6.10 | |||
|Infrastructure tests and best usage practices for life science service providers | |||
|WP 6 | |||
|CSC | |||
|R | |||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 6.11 | |||
|Security toolset release for BBMRI-ERIC | |||
|WP 6 | |||
|SNIC/KTH | |||
|OTHER | |||
|PU | |||
|M15 | |||
| | |||
|- | |||
!D 6.12 | |||
|GPGPU-enabled web portal(s) for MoBrain | |||
|WP 6 | |||
|CIRMMP | |||
|OTHER | |||
|PU | |||
|M16 | |||
| | |||
|- | |- | ||
! | !D 2.10 | ||
| | |Market Analysis Report of selected sectors | ||
|WP 2 | |WP 2 | ||
| | |GRNET | ||
| | |R | ||
|PU | |||
|M18 | |||
| | |||
|- | |- | ||
! | !D 3.7 | ||
| | |First release of the EGI Service Registry and Marketplace prototype | ||
|WP 3 | |||
|SWING | |||
|DEM | |||
|PU | |||
|M18 | |||
| | |||
|- | |||
!D 6.13 | |||
|EPOS EGI pilot incorporating data retrieval, transfer and linkage | |||
|WP 6 | |||
|SURFsara/KNMI | |||
|DEM | |||
|PU | |||
|M18 | |||
| | |||
|- | |||
!D 1.4 | |||
|Risk analysis and risk response for Period 2 | |||
|WP 1 | |||
|EGI.eu | |||
|R | |||
|PU | |||
|M20 | |||
| | |||
|- | |||
!D 3.8 | |||
|First data accounting prototype | |||
|WP 3 | |||
|STFC | |||
|DEM | |||
|PU | |||
|M20 | |||
| | |||
|- | |||
!D 4.7 | |||
|Open Data Platform First Prototype | |||
|WP 4 | |||
|CYFRONET | |||
|DEM | |||
|PU | |||
|M20 | |||
| | |||
|- | |||
!D 6.14 | |||
|Scipion cloud deployment for MoBrain | |||
|WP 6 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M21 | |||
| | |||
|- | |||
!D 2.11 | |||
|Cross-border procurement of e-Infrastructure services: Opportunities, Barriers, Use cases, Best Practices | |||
|WP 2 | |WP 2 | ||
| | |CERN | ||
|EGI | |R | ||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 3.9 | |||
|Identity Management for Distributed User Communities | |||
|WP 3 | |||
|GRNET | |||
|R | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 3.10 | |||
|Second release of the new Accounting Portal deployed in production | |||
|WP 3 | |||
|CSIC | |||
|OTHER | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 3.11 | |||
|Second release of the operational tools | |||
|WP 3 | |||
|CNRS | |||
|OTHER | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 3.12 | |||
|Second release of the Accounting Repository | |||
|WP 3 | |||
|STFC | |||
|OTHER | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 6.15 | |||
|Demonstrator for ELIXIR workflows implemented in the EGI Federated cloud | |||
|WP 6 | |||
|CESNET | |||
|DEM | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 6.16 | |||
|Evaluated cloud environment and demonstrator of analysis workflow for biobank studies | |||
|WP 6 | |||
|BBMRI ERIC | |||
|DEM | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 6.17 | |||
|Production level gateway for Arts and Humanities | |||
|WP 6 | |||
|MTA SZTAKI | |||
|OTHER | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 6.18 | |||
|Report on the installed LifeWatch applications and their usage record | |||
|WP 6 | |||
|CSIC | |||
|R | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 6.19 | |||
|EPOS EGI pilot integrating computational resources and services | |||
|WP 6 | |||
|CYFRONET | |||
|DEM | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 6.20 | |||
|Application of the simulation portals for scientific scenario in disaster mitigation | |||
|WP 6 | |||
|AS | |||
|DEM | |||
|PU | |||
|M24 | |||
| | |||
|- | |||
!D 5.3 | |||
|Evolution of security policies, procedures and best practices | |||
|WP 5 | |||
|STFC | |||
|R | |||
|PU | |||
|M25 | |||
| | |||
|- | |||
!D 3.13 | |||
|Second release of the EGI Service Registry and Marketplace prototype | |||
|WP 3 | |||
|SWING | |||
|DEM | |||
|PU | |||
|M26 | |||
| | |||
|- | |||
!D 3.14 | |||
|Report on Data Accounting | |||
|WP 3 | |||
|STFC | |||
|R | |||
|PU | |||
|M27 | |||
| | |||
|- | |||
!D 4.8 | |||
|Cross-infrastructure case studies report | |||
|WP 4 | |||
|INFN | |||
|R | |||
|PU | |||
|M27 | |||
| | |||
|- | |- | ||
! | !D 2.12 | ||
| | |EGI Governance: Report on Adoption | ||
|WP 2 | |WP 2 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M28 | |||
| | |||
|- | |||
!D 3.15 | |||
|Second data accounting prototype | |||
|WP 3 | |||
|STFC | |||
|DEM | |||
|PU | |||
|M28 | |||
| | |||
|- | |- | ||
! | !D 3.16 | ||
| | |Final report on EGI Service Registry and Marketplace | ||
|WP 3 | |||
|SWING | |||
|R | |||
|PU | |||
|M28 | |||
| | |||
|- | |||
!D 6.21 | |||
|Second version of enhanced portal for EISCAT_3D | |||
|WP 6 | |||
|EISCAT | |||
|OTHER | |||
|PU | |||
|M28 | |||
| | |||
|- | |||
!D 1.5 | |||
|Report of quality status for Period 2 | |||
|WP 1 | |||
|EGI.eu | |||
|R | |||
|PU | |||
|M29 | |||
| | |||
|- | |||
!D 4.9 | |||
|Open Data Platform: Demonstrator, Experience Report and Use Cases | |||
|WP 4 | |||
|CYFRONET | |||
|R | |||
|PU | |||
|M29 | |||
| | |||
|- | |||
!D 6.22 | |||
|Design larger scale multi-hazards simulation attempting to reduce the uncertainty of climate change assessment | |||
|WP 6 | |||
|AS | |||
|DEM | |||
|PU | |||
|M29 | |||
| | |||
|- | |||
!D 2.13 | |||
|EGI Sustainability and Business Development Plan | |||
|WP 2 | |WP 2 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M30 | |||
| | |||
|- | |- | ||
! | !D 2.14 | ||
| | |Final Report on Communications, Dissemination and Engagement | ||
|WP 2 | |WP 2 | ||
| | |EGI.eu | ||
| | |R | ||
|PU | |||
|M30 | |||
| | |||
|- | |- | ||
! | !D 3.17 | ||
| | |Final release of the accounting repository | ||
|WP 3 | |WP 3 | ||
| | |STFC | ||
| | |OTHER | ||
|PU | |||
|M30 | |||
| | |||
|- | |- | ||
! | !D 3.18 | ||
| | |Final release of the Operational tools | ||
|WP 3 | |WP 3 | ||
| | |CNRS | ||
| | |OTHER | ||
|PU | |||
|M30 | |||
| | |||
|- | |- | ||
! | !D 3.19 | ||
| | |Final release of the new Accounting Portal deployed in production | ||
|WP 3 | |WP 3 | ||
| | |CSIC | ||
| | |OTHER | ||
|PU | |||
|M30 | |||
| | |||
|- | |- | ||
!M 3.4 | !D 4.10 | ||
|Pilot services and best practices to enable federated AAI solutions released | |Final CANFAR integration release | ||
|WP 3 | |WP 4 | ||
|M16 | |NFN | ||
|Pilot services and best practices to enable federated AAI solutions for EGI services are available for the VREs and CCs | |DEM | ||
|PU | |||
|M30 | |||
| | |||
|- | |||
!D 5.4 | |||
|Status report and evolution of operations after the project | |||
|WP 5 | |||
|EGI.eu | |||
|R | |||
|PU | |||
|M30 | |||
| | |||
|- | |||
!D 6.23 | |||
|Report on evaluation of EPOS EGI pilot studies | |||
|WP 6 | |||
|INFN/INGV | |||
|R | |||
|PU | |||
|M30 | |||
| | |||
|} | |||
<br> | |||
<br> | |||
= Milestones<br> = | |||
{| class="wikitable" | |||
|- | |||
! Milestone | |||
! Title | |||
! Related WP | |||
! Delivery PM | |||
! Means of verification | |||
|- | |||
! M 1.1 | |||
| Execution plan | |||
| WP 1 | |||
| M02 | |||
| Staff for each partner per each task is identified and communicated to the project office, the reporting lines, the project management and governance structures are defined and approved | |||
|- | |||
! M 1.2 | |||
| First intermediate report | |||
| WP 1 | |||
| M08 | |||
| A quarterly report describing the status of each activity within the project (M01 – M07) is approved | |||
|- | |||
! M 1.3 | |||
| Second intermediate report | |||
| WP 1 | |||
| M23 | |||
| A quarterly report describing the status of each activity within the project (M16 – M22) is approved | |||
|- | |||
! M 2.1 | |||
| Website and templates | |||
| WP 2 | |||
| M01 | |||
| Project information is available on the Web and document/presentation templates are defined | |||
|- | |||
! M 2.2 | |||
| Technical Forum 2015 is organised | |||
| WP 2 | |||
| M12 | |||
| The event took place and a report is published with the main indicators including user satisfaction | |||
|- | |||
! M 2.3 | |||
| The EGI website is reviewed | |||
| WP 2 | |||
| M13 | |||
| The website is reviewed and a number of recommended changes have been applied | |||
|- | |||
! M 2.4 | |||
| EGI Service management practices are audited | |||
| WP 2 | |||
| M15 | |||
| EGI service management practices are audited by an external FitSM consultant | |||
|- | |||
! M 2.5 | |||
| Technical Forum 2016 is organised | |||
| WP 2 | |||
| M24 | |||
| The event took place and a report is published with the main indicators including user satisfaction | |||
|- | |||
! M 2.6 | |||
| The EGI website is reviewed | |||
| WP 2 | |||
| M25 | |||
| The website is reviewed and a number of recommended changes have been applied | |||
|- | |||
! M 2.7 | |||
| EGI Service management practices are audited | |||
| WP 2 | |||
| M29 | |||
| EGI service management practices are audited by an external FitSM consultants | |||
|- | |||
! M 3.1 | |||
| Operational tools development roadmap agreed | |||
| WP 3 | |||
| M04 | |||
| The operational tools development roadmap is agreed | |||
|- | |||
! M 3.2 | |||
| User requirements on data accounting collected | |||
| WP 3 | |||
| M12 | |||
| The user requirements on Data Accounting are agreed and documented | |||
|- | |||
! M 3.3 | |||
| Operational tools development roadmap revised | |||
| WP 3 | |||
| M16 | |||
| The operational tools development roadmap is revised and documented | |||
|- | |||
! M 3.4 | |||
| Pilot services and best practices to enable federated AAI solutions released | |||
| WP 3 | |||
| M16 | |||
| Pilot services and best practices to enable federated AAI solutions for EGI services are available for the VREs and CCs | |||
|- | |- | ||
!M 3.5 | ! M 3.5 | ||
|The first version of the EGI Marketplace is demonstrated | | The first version of the EGI Marketplace is demonstrated | ||
|WP 3, WP 2 | | WP 3, WP 2 | ||
|M18 | | M18 | ||
|Demo showcased at EGI Technical Forum and made available online | | Demo showcased at EGI Technical Forum and made available online | ||
|- | |- | ||
!M 3.6 | ! M 3.6 | ||
|The second version of the EGI Marketplace is demonstrated | | The second version of the EGI Marketplace is demonstrated | ||
|WP 3, WP 2 | | WP 3, WP 2 | ||
|M26 | | M26 | ||
|Demo showcased at EGI Technical Forum and made available online | | Demo showcased at EGI Technical Forum and made available online | ||
|- | |- | ||
!M 4.1 | ! M 4.1 | ||
|Open Data Platform: requirements and implementation plans | | Open Data Platform: requirements and implementation plans | ||
|WP 4 | | WP 4 | ||
|M06 | | M06 | ||
|Final selection of the technologies used to create Open Data Access Platform agreed. The report includes requirements and use cases from selected communities interested in open data | | Final selection of the technologies used to create Open Data Access Platform agreed. The report includes requirements and use cases from selected communities interested in open data | ||
|- | |- | ||
!M 4.2 | ! M 4.2 | ||
|Launch of call for cross e-Infrastructure case studies | | Launch of call for cross e-Infrastructure case studies | ||
|WP 4 | | WP 4 | ||
|M15 | | M15 | ||
|A call for participation for cross e-Infrastructure case studies is published | | A call for participation for cross e-Infrastructure case studies is published | ||
|- | |- | ||
!M 4.3 | ! M 4.3 | ||
|Open Data Platform in the Production | | Open Data Platform in the Production | ||
|WP 4 | | WP 4 | ||
|M30 | | M30 | ||
|The Open Data Platform is released in the production environment | | The Open Data Platform is released in the production environment | ||
|- | |- | ||
!M 5.1 | ! M 5.1 | ||
|Platform for the long-tail of science is available | | Platform for the long-tail of science is available | ||
|WP 5 | | WP 5 | ||
|M10 | | M10 | ||
|The services to enable easy access to EGI resources are production-ready. | | The services to enable easy access to EGI resources are production-ready. | ||
|- | |- | ||
!M 5.2 | ! M 5.2 | ||
|e-CEO challenges run on EGI resources | | e-CEO challenges run on EGI resources | ||
|WP 5 | | WP 5 | ||
|M15 | | M15 | ||
|The e-CEO tool for the ESA data challenge is using also EGI resources to run the data analysis tasks | | The e-CEO tool for the ESA data challenge is using also EGI resources to run the data analysis tasks | ||
|- | |- | ||
!M 5.3 | ! M 5.3 | ||
|VREs for the fishery and marine sciences community are deployed in production | | VREs for the fishery and marine sciences community are deployed in production | ||
|WP 5 | | WP 5 | ||
|M18 | | M18 | ||
|Services for the fishery and marine sciences are available and production-ready on EGI resources | | Services for the fishery and marine sciences are available and production-ready on EGI resources | ||
|- | |- | ||
!M 6.1 | ! M 6.1 | ||
|Joint training program for the first period is agreed | | Joint training program for the first period is agreed | ||
|WP 6 | | WP 6 | ||
|M03 | | M03 | ||
|The plan is defined by the competence centres, the partner e-Infrastructures and partner projects of EGI-Engage | | The plan is defined by the competence centres, the partner e-Infrastructures and partner projects of EGI-Engage | ||
|- | |- | ||
!M 6.2 | ! M 6.2 | ||
|Security and privacy requirements and secure storage architectural design are agreed | | Security and privacy requirements and secure storage architectural design are agreed | ||
|WP 6 | | WP 6 | ||
|M06 | | M06 | ||
|Requirements are approved by the BBMRI Research Infrastructure community and the developers of the secure storage solution verified and accepted the design | | Requirements are approved by the BBMRI Research Infrastructure community and the developers of the secure storage solution verified and accepted the design | ||
|- | |- | ||
!M 6.3 | ! M 6.3 | ||
|Life science requirements analysis and driver use case(s) with implementation roadmap are agreed | | Life science requirements analysis and driver use case(s) with implementation roadmap are agreed | ||
|WP 6 | | WP 6 | ||
|M12 | | M12 | ||
|Requirements are approved by the ELIXIR Research Infrastructure community | | Requirements are approved by the ELIXIR Research Infrastructure community | ||
|- | |- | ||
!M 6.4 | ! M 6.4 | ||
|EPOS requirements analysis and outline of pilot use cases are agreed | | EPOS requirements analysis and outline of pilot use cases are agreed | ||
|WP 6 | | WP 6 | ||
|M12 | | M12 | ||
|Requirements and pilot use cases are approved by the EPOS Research Infrastructure community | | Requirements and pilot use cases are approved by the EPOS Research Infrastructure community | ||
|- | |- | ||
!M 6.5 | ! M 6.5 | ||
|Joint training program for the second period is agreed | | Joint training program for the second period is agreed | ||
|WP 6 | | WP 6 | ||
|M15 | | M15 | ||
|The plan is endorsed by the competence centres, the partner e-Infrastructures and partner projects of EGI-Engage | | The plan is endorsed by the competence centres, the partner e-Infrastructures and partner projects of EGI-Engage | ||
|} | |} | ||
<br> | <br> | ||
<br> | <br> | ||
<br> | <br> | ||
[[Category:EGI-Engage]] | [[Category:EGI-Engage]] |
Revision as of 12:49, 29 January 2015
Deliverables
Code | Title | WP(s) | Lead Participant | Type | Dissemination level | Delivery PM | Description |
---|---|---|---|---|---|---|---|
D 1.1 | Quality plan for Period 1 | WP 1 | EGI.eu | R | PU | M03 | |
D 2.1 | Communications, Dissemination and Engagement Strategy | WP 2 | EGI.eu | R | PU | M03 | |
D 2.2 | Master Model for SME engagement | WP 2 | EGI.eu | R | PU | M06 | |
D 2.3 | Concept of EGI Marketplace | WP 2 | SWING | R | PU | M06 | |
D 2.4 | Data Management Plan | WP 2 | EGI.eu | R | PU | M06 | |
D 3.1 | Technical design of the new Accounting Portal and implementation plan | WP 3 | CSIC | R | PU | M06 | |
D 4.1 | CANFAR integration roadmap | WP 4 | INFN | R | PU | M06 | |
D 1.2 | Risk analysis and risk response for Period 1 | WP 1 | EGI.eu | R | PU | M08 | |
D 4.2 | VM snapshot support: OCCI extension, final specification | WP 4 | CSIC | OTHER | PU | M09 | |
D 4.3 | Resource template changes: OCCI extension, final specification | WP 4 | CSIC | OTHER | PU | M09 | |
D 6.1 | Assisted pattern recognition tools integrated with EGI for citizen science | WP 6 | CSIC | OTHER | PU | M09 | |
D 6.2 | Data repository for DARIAH | WP 6 | INFN | OTHER | PU | M11 | |
D 2.5 | EGI Governance: Analysis and Recommendations | WP 2 | EGI.eu | R | PU | M12 | |
D 2.6 | Report on data sharing policies and legal framework in fishery and marine sciences data sector | WP 2 | FAO | R | PU | M12 | |
D 2.7 | Market Report on the fishery and marine sciences data sector | WP 2 | Engineering | R | PU | M12 | |
D 3.2 | Design of the EGI Service Registry and Marketplace | WP 3 | SWING | R | PU | M12 | |
D 3.3 | Accounting Repository release | WP 3 | STFC | OTHER | PU | M12 | |
D 3.4 | First release of the operational tools WP 3 | CNRS | OTHER | PU | M12 | ||
D 4.4 | Relocating VM instances between providers, final specification | WP 4 | CSIC | OTHER | PU | M12 | |
D 4.5 | Deployment of a gCube release with Federated Cloud support | WP 4 | Engineering | OTHER | PU | M12 | |
D 6.3 | Production portal for EISCAT_3D | WP 6 | EISCAT | OTHER | PU | M12 | |
D 6.4 | Fully integrated MoBRAIN web portal | WP 6 | GNUBILA | OTHER | PU | M12 | |
D 6.5 | Final version of Multi-Source Distributed Real-Time Search and Information Retrieval application | WP 6 | GWDG | OTHER | PU | M12 | |
D 6.6 | Data flow handler and basic R tools to integrate and process data from Ecological Observatories on EGI | WP 6 | CSIC | DEM | PU | M12 | |
D 6.7 | Implementation and evaluation of AMBER and/or GROMACS | WP 6 | CIRMMP | R | PU | M13 | |
D 1.3 | Report of quality status and quality plan for Period 2 | WP 1 | EGI.eu | R | PU | M14 | |
D 3.5 | First release of the new Accounting Portal deployed in production | WP 3 | CSIC | OTHER | PU | M14 | |
D 6.8 | Analysis of requirements on biobank and study workflows | WP 6 | BBMRI ERIC | R | PU | M14 | |
D 6.9 | web portals for tsunami wave propagation simulations and for WRF-based weather simulation | WP 6 | AS | OTHER | PU | M14 | |
D 2.8 | Communications, Dissemination and Engagement Report and Updated Strategy | WP 2 | EGI.eu | R | PU | M15 | |
D 2.9 | EGI Sustainability and Business Development Plan | WP 2 | EGI.eu | R | PU | M15 | |
D 3.6 | Analysis on techniques to manage big data on the EGI accounting system | WP 3 | STFC | R | PU | M15 | |
D 4.6 | e-Infrastructures integration report | WP 4 | INFN | R | PU | M15 | |
D 5.1 | Report on the evolution of the EGI Operations | WP 5 | EGI.eu | R | PU | M15 | |
D 5.2 | Platforms for the long-tail of science | WP 5 | CNR | R | PU | M15 | |
D 6.10 | Infrastructure tests and best usage practices for life science service providers | WP 6 | CSC | R | PU | M15 | |
D 6.11 | Security toolset release for BBMRI-ERIC | WP 6 | SNIC/KTH | OTHER | PU | M15 | |
D 6.12 | GPGPU-enabled web portal(s) for MoBrain | WP 6 | CIRMMP | OTHER | PU | M16 | |
D 2.10 | Market Analysis Report of selected sectors | WP 2 | GRNET | R | PU | M18 | |
D 3.7 | First release of the EGI Service Registry and Marketplace prototype | WP 3 | SWING | DEM | PU | M18 | |
D 6.13 | EPOS EGI pilot incorporating data retrieval, transfer and linkage | WP 6 | SURFsara/KNMI | DEM | PU | M18 | |
D 1.4 | Risk analysis and risk response for Period 2 | WP 1 | EGI.eu | R | PU | M20 | |
D 3.8 | First data accounting prototype | WP 3 | STFC | DEM | PU | M20 | |
D 4.7 | Open Data Platform First Prototype | WP 4 | CYFRONET | DEM | PU | M20 | |
D 6.14 | Scipion cloud deployment for MoBrain | WP 6 | CSIC | OTHER | PU | M21 | |
D 2.11 | Cross-border procurement of e-Infrastructure services: Opportunities, Barriers, Use cases, Best Practices | WP 2 | CERN | R | PU | M24 | |
D 3.9 | Identity Management for Distributed User Communities | WP 3 | GRNET | R | PU | M24 | |
D 3.10 | Second release of the new Accounting Portal deployed in production | WP 3 | CSIC | OTHER | PU | M24 | |
D 3.11 | Second release of the operational tools | WP 3 | CNRS | OTHER | PU | M24 | |
D 3.12 | Second release of the Accounting Repository | WP 3 | STFC | OTHER | PU | M24 | |
D 6.15 | Demonstrator for ELIXIR workflows implemented in the EGI Federated cloud | WP 6 | CESNET | DEM | PU | M24 | |
D 6.16 | Evaluated cloud environment and demonstrator of analysis workflow for biobank studies | WP 6 | BBMRI ERIC | DEM | PU | M24 | |
D 6.17 | Production level gateway for Arts and Humanities | WP 6 | MTA SZTAKI | OTHER | PU | M24 | |
D 6.18 | Report on the installed LifeWatch applications and their usage record | WP 6 | CSIC | R | PU | M24 | |
D 6.19 | EPOS EGI pilot integrating computational resources and services | WP 6 | CYFRONET | DEM | PU | M24 | |
D 6.20 | Application of the simulation portals for scientific scenario in disaster mitigation | WP 6 | AS | DEM | PU | M24 | |
D 5.3 | Evolution of security policies, procedures and best practices | WP 5 | STFC | R | PU | M25 | |
D 3.13 | Second release of the EGI Service Registry and Marketplace prototype | WP 3 | SWING | DEM | PU | M26 | |
D 3.14 | Report on Data Accounting | WP 3 | STFC | R | PU | M27 | |
D 4.8 | Cross-infrastructure case studies report | WP 4 | INFN | R | PU | M27 | |
D 2.12 | EGI Governance: Report on Adoption | WP 2 | EGI.eu | R | PU | M28 | |
D 3.15 | Second data accounting prototype | WP 3 | STFC | DEM | PU | M28 | |
D 3.16 | Final report on EGI Service Registry and Marketplace | WP 3 | SWING | R | PU | M28 | |
D 6.21 | Second version of enhanced portal for EISCAT_3D | WP 6 | EISCAT | OTHER | PU | M28 | |
D 1.5 | Report of quality status for Period 2 | WP 1 | EGI.eu | R | PU | M29 | |
D 4.9 | Open Data Platform: Demonstrator, Experience Report and Use Cases | WP 4 | CYFRONET | R | PU | M29 | |
D 6.22 | Design larger scale multi-hazards simulation attempting to reduce the uncertainty of climate change assessment | WP 6 | AS | DEM | PU | M29 | |
D 2.13 | EGI Sustainability and Business Development Plan | WP 2 | EGI.eu | R | PU | M30 | |
D 2.14 | Final Report on Communications, Dissemination and Engagement | WP 2 | EGI.eu | R | PU | M30 | |
D 3.17 | Final release of the accounting repository | WP 3 | STFC | OTHER | PU | M30 | |
D 3.18 | Final release of the Operational tools | WP 3 | CNRS | OTHER | PU | M30 | |
D 3.19 | Final release of the new Accounting Portal deployed in production | WP 3 | CSIC | OTHER | PU | M30 | |
D 4.10 | Final CANFAR integration release | WP 4 | NFN | DEM | PU | M30 | |
D 5.4 | Status report and evolution of operations after the project | WP 5 | EGI.eu | R | PU | M30 | |
D 6.23 | Report on evaluation of EPOS EGI pilot studies | WP 6 | INFN/INGV | R | PU | M30 |
Milestones
Milestone | Title | Related WP | Delivery PM | Means of verification |
---|---|---|---|---|
M 1.1 | Execution plan | WP 1 | M02 | Staff for each partner per each task is identified and communicated to the project office, the reporting lines, the project management and governance structures are defined and approved |
M 1.2 | First intermediate report | WP 1 | M08 | A quarterly report describing the status of each activity within the project (M01 – M07) is approved |
M 1.3 | Second intermediate report | WP 1 | M23 | A quarterly report describing the status of each activity within the project (M16 – M22) is approved |
M 2.1 | Website and templates | WP 2 | M01 | Project information is available on the Web and document/presentation templates are defined |
M 2.2 | Technical Forum 2015 is organised | WP 2 | M12 | The event took place and a report is published with the main indicators including user satisfaction |
M 2.3 | The EGI website is reviewed | WP 2 | M13 | The website is reviewed and a number of recommended changes have been applied |
M 2.4 | EGI Service management practices are audited | WP 2 | M15 | EGI service management practices are audited by an external FitSM consultant |
M 2.5 | Technical Forum 2016 is organised | WP 2 | M24 | The event took place and a report is published with the main indicators including user satisfaction |
M 2.6 | The EGI website is reviewed | WP 2 | M25 | The website is reviewed and a number of recommended changes have been applied |
M 2.7 | EGI Service management practices are audited | WP 2 | M29 | EGI service management practices are audited by an external FitSM consultants |
M 3.1 | Operational tools development roadmap agreed | WP 3 | M04 | The operational tools development roadmap is agreed |
M 3.2 | User requirements on data accounting collected | WP 3 | M12 | The user requirements on Data Accounting are agreed and documented |
M 3.3 | Operational tools development roadmap revised | WP 3 | M16 | The operational tools development roadmap is revised and documented |
M 3.4 | Pilot services and best practices to enable federated AAI solutions released | WP 3 | M16 | Pilot services and best practices to enable federated AAI solutions for EGI services are available for the VREs and CCs |
M 3.5 | The first version of the EGI Marketplace is demonstrated | WP 3, WP 2 | M18 | Demo showcased at EGI Technical Forum and made available online |
M 3.6 | The second version of the EGI Marketplace is demonstrated | WP 3, WP 2 | M26 | Demo showcased at EGI Technical Forum and made available online |
M 4.1 | Open Data Platform: requirements and implementation plans | WP 4 | M06 | Final selection of the technologies used to create Open Data Access Platform agreed. The report includes requirements and use cases from selected communities interested in open data |
M 4.2 | Launch of call for cross e-Infrastructure case studies | WP 4 | M15 | A call for participation for cross e-Infrastructure case studies is published |
M 4.3 | Open Data Platform in the Production | WP 4 | M30 | The Open Data Platform is released in the production environment |
M 5.1 | Platform for the long-tail of science is available | WP 5 | M10 | The services to enable easy access to EGI resources are production-ready. |
M 5.2 | e-CEO challenges run on EGI resources | WP 5 | M15 | The e-CEO tool for the ESA data challenge is using also EGI resources to run the data analysis tasks |
M 5.3 | VREs for the fishery and marine sciences community are deployed in production | WP 5 | M18 | Services for the fishery and marine sciences are available and production-ready on EGI resources |
M 6.1 | Joint training program for the first period is agreed | WP 6 | M03 | The plan is defined by the competence centres, the partner e-Infrastructures and partner projects of EGI-Engage |
M 6.2 | Security and privacy requirements and secure storage architectural design are agreed | WP 6 | M06 | Requirements are approved by the BBMRI Research Infrastructure community and the developers of the secure storage solution verified and accepted the design |
M 6.3 | Life science requirements analysis and driver use case(s) with implementation roadmap are agreed | WP 6 | M12 | Requirements are approved by the ELIXIR Research Infrastructure community |
M 6.4 | EPOS requirements analysis and outline of pilot use cases are agreed | WP 6 | M12 | Requirements and pilot use cases are approved by the EPOS Research Infrastructure community |
M 6.5 | Joint training program for the second period is agreed | WP 6 | M15 | The plan is endorsed by the competence centres, the partner e-Infrastructures and partner projects of EGI-Engage |