(Created page with "{{Template:Op menubar}} {{TOC_right}} Category:SA1 weekly report << SA1 weekly reports =Progress of SA1 issues= <!-- T. Ferrari --> Nothing n...")
 
Line 10: Line 10:
=Milestones/Deliverables=
=Milestones/Deliverables=
<!-- T. Ferrari -->
<!-- T. Ferrari -->
* D4.7 Operations Sustainability. Still in draft status, will be ready for review next Monday.
* D4.7 Operations Sustainability.  


=SA1.1 Activity Management=  
=SA1.1 Activity Management=  
Line 16: Line 16:


MEETINGS
MEETINGS
* JRA1 meeting
*
* organization and contribution to the EGI/EUDAT/PRACE workshop
* security meeting


ACTIVITIES
ACTIVITIES
* contribution to the defininition of a new VO A/R calculation algorithm
*  
* discussion of problem of NGI A/R statistics, which are currently affected by sites that are in production just for a fraction of the calendar month
* Follow up of a GOCDB outage
* Follow up of message broker network outage affecting all NGIs (November A/R statistics will be recomputed)
* OPS VO management
* Submission of two abstracts for ISGC 2013
* coordination of plan for retirement of unsupported software, and discussion of a new plan and of the related development actions needed, for decommissioning of gLite 3.2 WN, DPM, LFC and EMI 1. 1/3 of the affected services retired/upgraded in the last 2 weeks. Discussion of an action plan to check the progress of upgrade plans by end of November
* contribution of ideas for the preparation of the EGI Champion programme


=SA1.2 Security=  
=SA1.2 Security=  
<!-- D. Kelsey -->
<!-- D. Kelsey -->
* monthly CSIRT team meeting held on 22 November
*  
* activities for tracking upgrading status from gLite 3.2 components
* Including handling potential suspension of unresponsive sites - not needed in the end - all went into downtime
* SVG - handling of several new issues
* planning for security workshop and submission of 2 talks to ISGC 2013
* development work on new custom security probes for NGI SAM instance
* '''no''' sites were eventually suspended because of the lack of feedback about upgrade plans


= SA1.3 Staged rollout =
= SA1.3 Staged rollout =
*EMI1 update 21 and EMI2 update 6 have entered into the SW provisioning process
<!-- Mario David -->
**Some components already under verification (LB 3.2.9 from EMI1, and gridsite).
*  
**UMD urgent release foreseen for some components, at least WN and DPM
*SAM19 completed SW provisioning and released into production.
*CA 1.51 completed SW provisioning expected to be released this week
*New changes into the SW provisioning process under discussion


=SA1.3 Integration=
=SA1.3 Integration=
<!-- E. Imamagic, M. Krakowian from Nov 2012 -->
<!-- M. Krakowian from Nov 2012 -->
* Participation to the envri use case meeting
*  
* discussion of MAPPER helpdesk strategy and new actions
* Organization of the EGI/EUDAT/PRACE meeting, with the contribution of 6 user communities


=SA1.4 Central tools=  
=SA1.4 Central tools=  
<!--E. Imamagic -->
<!--E. Imamagic -->


* Upgrade of AUTH and SRCE brokers finished successfully, CERN brokers will be upgraded tomorrow (https://operations-portal.egi.eu/broadcast/archive/id/817).
*  
* SAM Update-19 released on November 23rd
* prolonged downtime of GOCDB because of power issues, the failover configuration did not prove to be ready to replace the primary instance affected by the problem. Action on EGI operations to discuss a better failover strategy for GOCDB.
* APEL downtime caused by issues of the power supply system of the hosting organization


=SA1.5 Accounting=  
=SA1.5 Accounting=  
'''<!--A. Packer--> Repository '''
'''<!--A. Packer--> Repository '''
- outage last Tuesday, 20th November due to problem caused by electrical work carried out on the UPS at RAL, all APEL systems restored on Wednesday, 21st November.  Sites continue to raise tickets in order to republish user DNs.
*
*
 
'''<!--A. Packer--> Portal'''


=SA1.6 Helpdesk=  
=SA1.6 Helpdesk=  
<!-- T. Antoni -->
<!-- T. Antoni -->
* Shopping list meeting to prioritise requests for GGUS
*  
* Preparing the GGUS-AB phone conference next Thursday (2012-11-29), see agenda: https://indico.egi.eu/indico/conferenceDisplay.py?confId=1259
* Preparing the next GGUS release on 2012-11-28


=SA1.7 Support=
=SA1.7 Support=
<!--  trompert -->
<!--  trompert -->
* usual ticket handling and dashboard work
*  
* handling unsupported middleware tickets
* review of GOCdb business logic
* wrote plan for future COD activities


== Software Support ==
== Software Support ==
<!-- A Krenek -->
<!-- A Krenek -->
No report received


== Network Support  ==
== Network Support  ==
 
<!-- Mario Reale -->
Started assessment of IPv6 compliance of FTS 3.


=SA1.8 Availability and core services=
=SA1.8 Availability and core services=
<!--C. Kanellopoulos-->
<!--C. Kanellopoulos-->
* Revision of A/R algorithm for the computation of NGI availability/reliability statistics
*  
* assessment of migration plan from VOMRS to VOMS and impact on DTEAM VO management duties. Upgrade date was postponed.


== Documentation ==
== Documentation ==
<!-- M. Krakowian -->
<!-- M. Krakowian -->
* [[EGI_Operations_Start_Guide | EGI Operations Start Guide]] for newcomers was created.
*  
* [[PROC04| PROC04]] was reviewed and split into two pages [[PROC04|PROC04]] and [[Availability_and_reliability_monthly_statistics| Availability and reliability monthly statistics]]
* [[Administrator_Documentation|Documentation page for administrators]] was created


= Meetings=
= Meetings=
<!--all-->
<!--all-->
* TERENA Network Operations Task Force meeting, Poznan, 12-13 Dec 2012
*

Revision as of 09:21, 28 November 2012

Main EGI.eu operations services Support Documentation Tools Activities Performance Technology Catch-all Services Resource Allocation Security


<< SA1 weekly reports

Progress of SA1 issues

Nothing new to report.

Milestones/Deliverables

  • D4.7 Operations Sustainability.

SA1.1 Activity Management

MEETINGS

ACTIVITIES

SA1.2 Security

SA1.3 Staged rollout

SA1.3 Integration

SA1.4 Central tools

SA1.5 Accounting

Repository

Portal

SA1.6 Helpdesk

SA1.7 Support

Software Support

Network Support

SA1.8 Availability and core services

Documentation

Meetings