Progress of SA1 issues

Nothing new to report

Milestones/Deliverables

  • MS421: External review completed, Erika contacted the reviewers/moderator on 02/10 for a final check
  • D4.6 Operations Architecture: external review started, contacted various partners to get an additional reviewer (no reply yet)

SA1.1 Activity Management

  • participation to globus on line internal EGI.eu meeting
  • contacted integrated RP partners for the negotiation of a RP MoU
  • completed editing of D4.6
  • assessment of deployment of obsolete services, and participation to the discussion of the nagios probes needed to track upgrade of unsupported software
  • review of DANTE MoU
  • discussion of migration of VOMS services for OPS from CERN to GRNET

SA1.2 Security

  • configuration of Security Nagios to run new probes needed to monitor sites hosting gLite 3.1 services and unsupported gLite 3.2 services
  • assessment of status of WMS installations
  • Addendum week 38: Security-Track at TF in Prague, Introduction to Forensics, Part-1: Handle attacks targeted at OS vulnerabilities, Part:2 Handle an attack exploring grid technologies.

SA1.3 Staged rollout

SA1.3 Integration

  • Discussion with PRACE on a EUDAT, EGI, PRACE, VERCE and MAPPER workshop on pilot activities for coupled data management. The workshop originally foreseen for October/November has to be postponed to end of Nov/beginning of Dec because of the upcoming PRACE review
  • Definition/discussion of MAPPER ticket workflows
  • Completed integration of GLOBUS and UNICORE tests into the operations dashboard (October 1st)
  • Provided updated MS 421 to external reviewers (September 26th)

SA1.4 Central tools

  • By the end of Tuesday 21 NGIs have deployed SAM Update-17.

SA1.5 Accounting

Assessment of sites still not publishing User DNs in September: 103. 1/3 of the sites not publishing in May have been fixed.

SA1.6 Helpdesk

New release of GGUS on 26/09/2012: https://operations-portal.egi.eu/broadcast/archive/id/744

SA1.7 Support

Various nagios probes were validated and turned into OPERATIONS: Globus GRAM5 service (hr.srce.GRAM-Auth, hr.srce.GRAM-CertLifetime, hr.srce.GRAM-Command) and Globus-GRIDFTP service (hr.srce.GridFTP-Transfer, org.nagios.GridFTP-Check), Globus-GSISSHD service (org.nagios.gsissh-Check ), unicore6.Gateway service (emi.unicore.Gateway ), unicore6.Registry service (emi.unicore.Registry ), unicore6.ServiceOrchestrator service (emi.unicore.ServiceOrchestrator ), unicore6.UVOSAssertionQueryService (emi.unicore.UVOS), unicore6.TargetSystemFactory (emi.unicore.TargetSystemFactory ), unicore6.StorageManagement (emi.unicore.GlobalStorage, emi.unicore.GlobalStorage-FreeSpace), unicore6.WorkflowFactory (emi.unicore.WorkflowService)


Software Support

The task runs smoothly its day-to-day work, no particular issues to report.

DMSU tickets flow Sep 23 -- 30
assigned 15
back to tpm 0
reassigned to 3rd level 14
solved 12
open DMSU tickets status
assigned 0
in progress 3
waiting for reply 7
on hold 3

Network Support

SA1.8 Availability and core services

Analysis of solutions for VO A/R computation

Documentation

Meetings

  • fedSM meeting, Oct 04-05
  • ENVRI use cases meetings (two meetings in November)
  • PRACE/EGI/community meeting on data management (date to be defined through doodle that PRACE will organize)