Line 1: | Line 1: | ||
{{CMD_Menu}} {{TOC_right}} | {{Template:Tech menubar}} {{CMD_Menu}} {{TOC_right}} | ||
= Description of the process = | = Description of the process = | ||
Line 21: | Line 21: | ||
| 2 | | 2 | ||
| Injection | | Injection | ||
| UMD SR Manager | | UMD Team SR Manager | ||
| inject the product release in the EGI SW provisioning infrastructure: | | inject the product release in the EGI SW provisioning infrastructure: | ||
* One or more RT tickets are created to track the progress of the inclusion of the new product release; the status of the product release will then be tracked in RT, the status of the RT ticket just is initially '''Unverified''' | * One or more RT tickets are created to track the progress of the inclusion of the new product release; the status of the product release will then be tracked in RT, the status of the RT ticket just is initially '''Unverified''' | ||
Line 28: | Line 28: | ||
|- | |- | ||
| 3 | | 3 | ||
| Quality Verification | | Quality Verification starts | ||
| QC Verifier | | UMD Team QC Verifier | ||
| the QC verifier starts the verification process | | the QC verifier starts the verification process, switching the status of the RT ticket from "Unverified" to "Verification" | ||
| '''one month'''; after a month with the verification not yet started: | | the QC verification must start in '''one month''' after the creation of the RT ticket; after a month with the verification not yet started: | ||
* the RT ticket will be updated with an explanation for the delay | * the RT ticket will be updated with an explanation for the delay | ||
* the status will be changed to "Delayed" [*] | * the status will be changed to "Delayed" [*] | ||
Line 37: | Line 37: | ||
|- | |- | ||
| 4 | | 4 | ||
| | | Quality Verification execution | ||
| UMD Team QC Verifier | |||
| the UMD team is verifying the product in the testbed; after the verification process is completed, the RT ticket status is switched from "Verification" to "Staged Rollout" | |||
| an RT ticket cannot stay longer than '''one week''' in verification; after one week with the verification not yet completed: | |||
* the RT ticket will be updated with an explanation for the delay | |||
* the status will be changed to "Delayed" [*] | |||
* the Technology Provider will be informed (using the contacts in the [https://wiki.egi.eu/wiki/EGI_Cloud_Middleware_Distribution_products product ID card]) | |||
|- | |||
| 5 | |||
| Staged Rollout | |||
| UMD Team Staged Rollout manager | |||
| The product is announced to the early adopters testing the product in staged rollout. | |||
| RT tickets cannot stay longer than '''one month''' in the "Staged Rollout" status; after a month with the staged rollout not yet completed: | |||
* the RT ticket will be updated with an explanation for the delay | |||
* the status will be changed to "Delayed" [*] | |||
* the Technology Provider will be informed (using the contacts in the [https://wiki.egi.eu/wiki/EGI_Cloud_Middleware_Distribution_products product ID card]) | |||
|- | |||
| 6 | |||
| Inclusion in the next release | |||
| Release manager | |||
| include the product in the next release | |||
| see the [https://wiki.egi.eu/wiki/EGI_Cloud_Middleware_Distribution_schedule CMD release schedule] | |||
|- | |||
|} | |} | ||
[*] Being in the "Delayed" status RT tickets can be identified as problematic by the UMD team and followed up more closely. | [*] Being in the "Delayed" status RT tickets can be identified as problematic by the UMD team and followed up more closely. | ||
== Verification == | |||
For further details on the Verification Process, please visit https://wiki.egi.eu/wiki/EGI_Quality_Assurance | |||
== Staged-Rollout == | == Staged-Rollout == | ||
For further details about the Staged-Rollout process, please visit https://wiki.egi.eu/wiki/Staged_Rollout | |||
== Release process == | |||
TBD |
Latest revision as of 16:25, 24 January 2017
Technology | Software Component Delivery | Software Provisioning | UMD Middleware | Cloud Middleware Distribution | Containers Distribution | Technology Glossary |
CMD menu: | Overview | Products | Process | Release schedule |
Description of the process
Step | Action | Action on | Description | Timeline |
---|---|---|---|---|
1 | Submission | Technology Provider | submit a GGUS ticket, assigned to Support Unit "EGI Software provisioning support", providing them with the following information:
|
at TP convenience |
2 | Injection | UMD Team SR Manager | inject the product release in the EGI SW provisioning infrastructure:
|
5 working days |
3 | Quality Verification starts | UMD Team QC Verifier | the QC verifier starts the verification process, switching the status of the RT ticket from "Unverified" to "Verification" | the QC verification must start in one month after the creation of the RT ticket; after a month with the verification not yet started:
|
4 | Quality Verification execution | UMD Team QC Verifier | the UMD team is verifying the product in the testbed; after the verification process is completed, the RT ticket status is switched from "Verification" to "Staged Rollout" | an RT ticket cannot stay longer than one week in verification; after one week with the verification not yet completed:
|
5 | Staged Rollout | UMD Team Staged Rollout manager | The product is announced to the early adopters testing the product in staged rollout. | RT tickets cannot stay longer than one month in the "Staged Rollout" status; after a month with the staged rollout not yet completed:
|
6 | Inclusion in the next release | Release manager | include the product in the next release | see the CMD release schedule |
[*] Being in the "Delayed" status RT tickets can be identified as problematic by the UMD team and followed up more closely.
Verification
For further details on the Verification Process, please visit https://wiki.egi.eu/wiki/EGI_Quality_Assurance
Staged-Rollout
For further details about the Staged-Rollout process, please visit https://wiki.egi.eu/wiki/Staged_Rollout
Release process
TBD