===2.1. Progress Summary===
===2.1. Progress Summary===
===2.2. Main Achievements===
===2.2. Main Achievements===
|-
Over the last quarter, Glasgow has successfully upgraded its Cluster and all associated networking infrastructure to provide a robust and fully resilient service to the EGI. This includes new fibres, switches, and UPS within the cluster and across the university link to JANET. Additional supporting services such air conditioning, and power have been evaluated and, where required, will be replaced in the coming quarter. One major benefit of this work has been the release of older storage equipment for deployment into the Glasgow test Cluster which will allow for dual stack testing of IPv4 and IPv6 on DPM. The test-cluster will also be used to address other areas of interest to EGI. In the coming two quarters we plan to develop, test and deploy an automated Cluster restart system. Glasgow hope to present this work at the EGI technical Forum this autumn.  They have started more active work to support the fledgling NA62 VO.
Over the last quarter, Glasgow has successfully upgraded the Cluster and all associated networking infrastructure to provide a robust and fully resilient service to the EGI. This includes new fibres, switches, and UPS within the cluster and across the university link to JANET. Additional supporting services such air conditioning, and power have been evaluated and, where required, will be replaced in the coming quarter. One major benefit of this work has been the release of older storage equipment for deployment into the Glasgow test Cluster which will allow for dual stack testing of IPv4 and IPv6 on DPM. The test-cluster will also be used to address other areas of interest to EGI. In the coming two quarters we plan to develop, test and deploy an automated Cluster restart system. We hope to present this work at the EGI technical Forum this autumn.  We have started more active work to support the fledgling NA62 VO.




Line 87: Line 86:
!scope="col"| Mitigation Description
!scope="col"| Mitigation Description
|-
|-
| Glasgow's DPM deployment encountered issues recently. The software has been upgraded and is currently being monitored to asses any remaining instability issues. The Glasgow site will also experience some additional downtime in the next two quarters as further upgrades are made to the local network infrastructure for other local user groups
| Further monitoring to ensure stability
|}
|}


Line 92: Line 93:
  Please, fill the table below. You can add a line copyng the two lines
  Please, fill the table below. You can add a line copyng the two lines
|-
|-
| Issue Description || Issue mitigation
| Glasgow's DPM deployment encountered issues recently. The software has been upgraded and is currently being monitored to asses any remaining instability issues. The Glasgow site will also experience some additional downtime in the next two quarters as further upgrades are made to the local network infrastructure for other local user groups.
 
-->
-->

Revision as of 15:30, 2 May 2012

Quarterly Report Number NGI Name Partner Name Author


1. MEETINGS AND DISSEMINATION

1.1. CONFERENCES/WORKSHOPS ORGANISED

Date Location Title Participants Outcome (Short report & Indico URL)

1.2. OTHER CONFERENCES/WORKSHOPS ATTENDED

Date Location Title Participants Outcome (Short report & Indico URL)


1.3. PUBLICATIONS

Publication title Journal / Proceedings title Journal references
Volume number
Issue

Pages from - to
Authors
1.
2.
3.
Et al?

2. ACTIVITY REPORT

2.1. Progress Summary

2.2. Main Achievements

Over the last quarter, Glasgow has successfully upgraded its Cluster and all associated networking infrastructure to provide a robust and fully resilient service to the EGI. This includes new fibres, switches, and UPS within the cluster and across the university link to JANET. Additional supporting services such air conditioning, and power have been evaluated and, where required, will be replaced in the coming quarter. One major benefit of this work has been the release of older storage equipment for deployment into the Glasgow test Cluster which will allow for dual stack testing of IPv4 and IPv6 on DPM. The test-cluster will also be used to address other areas of interest to EGI. In the coming two quarters we plan to develop, test and deploy an automated Cluster restart system. Glasgow hope to present this work at the EGI technical Forum this autumn. They have started more active work to support the fledgling NA62 VO.


2.3. Issues and mitigation

Issue Description Mitigation Description
Glasgow's DPM deployment encountered issues recently. The software has been upgraded and is currently being monitored to asses any remaining instability issues. The Glasgow site will also experience some additional downtime in the next two quarters as further upgrades are made to the local network infrastructure for other local user groups Further monitoring to ensure stability