Difference between revisions of "EGI-InSPIRE:Jra1 2013-04-30"
Jump to navigation
Jump to search
(13 intermediate revisions by 5 users not shown) | |||
Line 1: | Line 1: | ||
{{Template:EGI-Inspire menubar}} | |||
[[Category:EGI-InSPIRE]] | |||
[[Inspire_JRA1_weekly_reports| << JRA1 weekly reports main page]] | [[Inspire_JRA1_weekly_reports| << JRA1 weekly reports main page]] | ||
Line 4: | Line 6: | ||
== 1. Progress on Milestones Deliverables == | == 1. Progress on Milestones Deliverables == | ||
* Periodic Report | |||
Collecting PTs input | |||
* MS710 - Operational Tools Roadmap | |||
Final version available at: https://documents.egi.eu/document/1501 | |||
* D7.3 - Annual Report on Operational Tool maintenance and development activity | |||
AMB review: https://documents.egi.eu/secure/ShowDocument?docid=1562 | |||
== 2. Critical Issues == | == 2. Critical Issues == | ||
* GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was expected for May/early June). | |||
== 3. Major work done during the past week by task == | == 3. Major work done during the past week by task == | ||
=== 3.1 TJRA1.1 === | === 3.1 TJRA1.1 === | ||
* Periodic Report | |||
* JRA1 monthly meeting preparation | |||
* JRA1 action review | |||
* Meeting to discuss billing and Pay-for-Use matters | |||
=== 3.2 TJRA1.2 TJRA1.3 TJRA1.5 === | === 3.2 TJRA1.2 TJRA1.3 TJRA1.5 === | ||
Line 20: | Line 38: | ||
==== 3.2.2 GOCDB ==== | ==== 3.2.2 GOCDB ==== | ||
* Two day handover over of JC's v5 developments to DM. | |||
==== 3.2.3 GGUS ==== | ==== 3.2.3 GGUS ==== | ||
Line 27: | Line 46: | ||
==== 3.2.4 Ops Portal ==== | ==== 3.2.4 Ops Portal ==== | ||
* Refactoring of the VO ID cards (bootstrap + Jquery) | |||
* QR12 | |||
==== 3.2.5 Accounting Portal ==== | ==== 3.2.5 Accounting Portal ==== | ||
* Continuing refactor of the code | |||
* Changes for new accounting. | |||
* Fix for Unknown Discipline counting on VO Discipline CVS report. | |||
==== 3.2.6 Metrics Portal ==== | ==== 3.2.6 Metrics Portal ==== | ||
* Work for QR12 | |||
=== 3.3 TJRA1.4 (Accounting for new resource types) === | === 3.3 TJRA1.4 (Accounting for new resource types) === | ||
==== Accounting Portal ==== | |||
* Cloud accounting fixes | |||
== 4. Next Meetings == | == 4. Next Meetings == | ||
* Next JRA1 meeting: 13 May 2013 | |||
Latest revision as of 11:17, 6 January 2015
EGI Inspire Main page |
<< JRA1 weekly reports main page
1. Progress on Milestones Deliverables
- Periodic Report
Collecting PTs input
- MS710 - Operational Tools Roadmap
Final version available at: https://documents.egi.eu/document/1501
- D7.3 - Annual Report on Operational Tool maintenance and development activity
AMB review: https://documents.egi.eu/secure/ShowDocument?docid=1562
2. Critical Issues
- GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was expected for May/early June).
3. Major work done during the past week by task
3.1 TJRA1.1
- Periodic Report
- JRA1 monthly meeting preparation
- JRA1 action review
- Meeting to discuss billing and Pay-for-Use matters
3.2 TJRA1.2 TJRA1.3 TJRA1.5
3.2.1 SAM
- EGI SAM/Nagios probes WG: ARC probes meeting
- First draft of EGI QR12
- Next SAM Update ongoing
3.2.2 GOCDB
- Two day handover over of JC's v5 developments to DM.
3.2.3 GGUS
- Ticket monitoring
- GGUS release on 2013-04-24
- Preparation of the following GGUS release
3.2.4 Ops Portal
- Refactoring of the VO ID cards (bootstrap + Jquery)
- QR12
3.2.5 Accounting Portal
- Continuing refactor of the code
- Changes for new accounting.
- Fix for Unknown Discipline counting on VO Discipline CVS report.
3.2.6 Metrics Portal
- Work for QR12
3.3 TJRA1.4 (Accounting for new resource types)
Accounting Portal
- Cloud accounting fixes
4. Next Meetings
- Next JRA1 meeting: 13 May 2013