EGI-DRIHM:Roadmap
|
EGI DRIHAM collaboration menu: | Home • | Members • | Infrastructure • | Roadmap |
Note well. The detailed description of the computational and storage activity requirements to support DRIHM applications, both the highly parallel and less demanding ones, will be added to the wiki EGI-DRIHM collaboration wiki pages (June 15 - June 30 2013).
DRIHM VO Support
- June 15 - July 31 2013. Enable the DRIHM VO in a couple of EGI scheduler service (i.e. gLite-WMS/LB), in order to test the facilities offered by these services (jobs bookeeping, rescheduling, resources matchmaking, Input/Output SandBox handling, etc.).
Services for DRIHM
June 15 - June 30 2013. Other services needed are: a VOMS server (already available for DRIHM), a file catalogue (i.e. gLite-LFC) and a MyProxy server.
Porting
15 June - 01 July 2013. Porting of the demanding model (i.e. WRF) to the Grid Environment in collaboration with the EGI/NGIs user support teams for some selected "Critical Cases" and preliminary tests of the Grid submission/data management. (using NGI general purpose VO if DRIHM is not deployed yet)
Define sites to support the demanding jobs
01 July - 15 August 2013. Identification of the testbed members willing to run demanding jobs, as the meteo models, with the indication of the maximum allowable parallelism degree.
Job submission testing
- 01 July - 31 Aug 2013. Test the job submission (direct to CE and via WMS/LB) and data management from a command line user interface for the most demanding models on the DRIHM testbed - Performance evaluation of the infrastructure resources and services.
- 01 July - 31 Aug 2013. Porting and preliminary tests for the submission of jobs and data management from a command line user interface of the less demanding applications (hydrologic and hydraulic models) - Performance evaluation of the infrastructure and investigation of the capabilities offered by the virtualization systems available within EGI that can be suitable to run these applications.
- 01-30 September 2013. Preliminary test for the submission of jobs from the DRIHM sci-bus-based portal to the EGI testbed resources.
- 1 October 2013 - June 2014. Incremental setup and tests of the complete suite of DRIHM models on the testbed resources ?
Production phase
November 2013 ? - end of the DRIHM project
Table of actions 2013
Nr. | From | To | Involved | Action | Done | Notes and progress |
1. | June 15 | June 30 | NGIs | Enable DRIHM VO at sites listed in the testbed (computing and storage resources) | No | Below is the list of sites already supporting DRIHM VO: Serbia: |
2. | June 15 | June 30 | NGIs | Enable DRIHM VO in EGI schedulers | No | in order to test the facilities offered by these services (jobs bookeeping, rescheduling, resources matchmaking, Input/Output SandBox handling, etc.). |
gLite-WMS/LB | ||||||
3. | June 15 | June 30 | NGIs & DRIHM | DRIHM VO services | No | |
WMS | WMS: $ lcg-infosites --is lcg-bdii.cern.ch --vo drihm.eu wms https://graszode.nikhef.nl:7443/glite_wms_wmproxy_server https://gridrb.fe.infn.it:7443/glite_wms_wmproxy_server https://prod-wms-01.ct.infn.it:7443/glite_wms_wmproxy_server https://prod-wms-02.ct.infn.it:7443/glite_wms_wmproxy_server https://wms-aegis.ipb.ac.rs:7443/glite_wms_wmproxy_server https://wms-demo.ipb.ac.rs:7443/glite_wms_wmproxy_server https://wms.ipb.ac.rs:7443/glite_wms_wmproxy_server https://wms004.cnaf.infn.it:7443/glite_wms_wmproxy_server https://wms005.cnaf.infn.it:7443/glite_wms_wmproxy_server https://wms014.cnaf.infn.it:7443/glite_wms_wmproxy_server https://wms024.cnaf.infn.it:7443/glite_wms_wmproxy_server https://wms1.grid.cesnet.cz:7443/glite_wms_wmproxy_server | |||||
MyProxy | VOMS: vomsmania.cnaf.infn.it | |||||
LFC | LFC: $ lcg-infosites --is lcg-bdii.cern.ch --vo drihm.eu lfcLocal lfc.ipb.ac.rs | |||||
VOMS | MyProxy: myproxy.hellasgrid.gr [[|Catch All Services]] | |||||
3. | June 15 | June 30 | NGIs & DRIHM | WRF with MPICH2, GFORTRAN, NetCDF, GRIB2 deployment at NGIs. | By Daniele Cesini: One of the use cases provided by CIMA with WRF on the Naples site (SL6 WNs), using 16 core on 8 differnet nodes with infiniband and OpenMPI, but the performance (*) were not so exiting, Jerome from France provided the WRF configruation file with needed dependencis by DRIHM. | |
4. | July 01 | August 15 | NGIs | List of sites for demanding jobs (indicate maximum number of cores for paralell computing) | ||
5. | July 01 | August 31 | DRIHM | Testing DRIHM models at NGIs computing and storage resources (job submission of WRF models, data management using command line interface) | ||
6. | September 01 | September 30 | DRIHM | Testing DRIHM models at NGIs computing and storage resources (job submission of WRF models, data management using dedicated SCI-BUS portal) |