Collecting PTs input | Collecting PTs input | ||
* MS710 - Operational Tools Roadmap | * MS710 - Operational Tools Roadmap | ||
Final version available at: https://documents.egi.eu/document/1501 | Final version available at: https://documents.egi.eu/document/1501 | ||
* D7.3 - Annual Report on Operational Tool maintenance and development activity | * D7.3 - Annual Report on Operational Tool maintenance and development activity | ||
AMB review | AMB review: https://documents.egi.eu/secure/ShowDocument?docid=1562 | ||
https://documents.egi.eu/secure/ShowDocument?docid=1562 | |||
== 2. Critical Issues == | == 2. Critical Issues == | ||
* GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was | * GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was expected for May/early June). | ||
== 3. Major work done during the past week by task == | == 3. Major work done during the past week by task == | ||
Line 48: | Line 46: | ||
==== 3.2.4 Ops Portal ==== | ==== 3.2.4 Ops Portal ==== | ||
* Refactoring of the VO ID cards (bootstrap + Jquery) | |||
* QR12 | |||
==== 3.2.5 Accounting Portal ==== | ==== 3.2.5 Accounting Portal ==== | ||
Line 64: | Line 65: | ||
== 4. Next Meetings == | == 4. Next Meetings == | ||
* Next JRA1 meeting: 13 May 2013 | * Next JRA1 meeting: 13 May 2013 | ||
Latest revision as of 11:17, 6 January 2015
EGI Inspire Main page |
<< JRA1 weekly reports main page
1. Progress on Milestones Deliverables
- Periodic Report
Collecting PTs input
- MS710 - Operational Tools Roadmap
Final version available at: https://documents.egi.eu/document/1501
- D7.3 - Annual Report on Operational Tool maintenance and development activity
AMB review: https://documents.egi.eu/secure/ShowDocument?docid=1562
2. Critical Issues
- GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was expected for May/early June).
3. Major work done during the past week by task
3.1 TJRA1.1
- Periodic Report
- JRA1 monthly meeting preparation
- JRA1 action review
- Meeting to discuss billing and Pay-for-Use matters
3.2 TJRA1.2 TJRA1.3 TJRA1.5
3.2.1 SAM
- EGI SAM/Nagios probes WG: ARC probes meeting
- First draft of EGI QR12
- Next SAM Update ongoing
3.2.2 GOCDB
- Two day handover over of JC's v5 developments to DM.
3.2.3 GGUS
- Ticket monitoring
- GGUS release on 2013-04-24
- Preparation of the following GGUS release
3.2.4 Ops Portal
- Refactoring of the VO ID cards (bootstrap + Jquery)
- QR12
3.2.5 Accounting Portal
- Continuing refactor of the code
- Changes for new accounting.
- Fix for Unknown Discipline counting on VO Discipline CVS report.
3.2.6 Metrics Portal
- Work for QR12
3.3 TJRA1.4 (Accounting for new resource types)
Accounting Portal
- Cloud accounting fixes
4. Next Meetings
- Next JRA1 meeting: 13 May 2013