== 1. Progress on Milestones Deliverables == | == 1. Progress on Milestones Deliverables == | ||
* Periodic Report | |||
PTs input collected. JRA1 contribution completed by this week. | |||
* MS710 - Operational Tools Roadmap | |||
Final version available at: https://documents.egi.eu/document/1501 | |||
* D7.3 - Annual Report on Operational Tool maintenance and development activity | |||
Final version available at: https://documents.egi.eu/secure/ShowDocument?docid=1562 | |||
== 2. Critical Issues == | == 2. Critical Issues == | ||
* GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was expected for May/early June). | |||
== 3. Major work done during the past week by task == | == 3. Major work done during the past week by task == | ||
=== 3.1 TJRA1.1 === | === 3.1 TJRA1.1 === | ||
* Periodic Report | |||
* Metrics computation | |||
* JRA1 monthly meeting preparation | |||
* JRA1 action review | |||
=== 3.2 TJRA1.2 TJRA1.3 TJRA1.5 === | === 3.2 TJRA1.2 TJRA1.3 TJRA1.5 === | ||
==== 3.2.1 SAM ==== | ==== 3.2.1 SAM ==== | ||
* Final version of EGI QR12 | |||
* Next SAM Update ongoing | |||
==== 3.2.2 GOCDB ==== | ==== 3.2.2 GOCDB ==== | ||
* Hardware installation for new gocdb-failover at Daresbury labs. | |||
* Initial review of JC's v5 code. | |||
* | * Mentoring our new GOCDB mini-project developer. | ||
* | |||
* | |||
==== 3.2.3 GGUS ==== | ==== 3.2.3 GGUS ==== | ||
* Ticket monitoring | |||
* Preparation of the next GGUS release | |||
* Cleaning up support units after end of EMI project | |||
* Defining new structure of PTs | |||
* | |||
* | |||
* | |||
* | |||
==== 3.2.4 Ops Portal ==== | ==== 3.2.4 Ops Portal ==== | ||
* Refactoring of the VO ID cards (bootstrap + Jquery) | |||
==== 3.2.5 Accounting Portal ==== | ==== 3.2.5 Accounting Portal ==== | ||
* Continuing refactor of the code | |||
* Changes for new accounting. | |||
* | |||
* | |||
==== 3.2.6 Metrics Portal ==== | ==== 3.2.6 Metrics Portal ==== | ||
* Work for QR12 | |||
* | |||
=== 3.3 TJRA1.4 (Accounting for new resource types) === | === 3.3 TJRA1.4 (Accounting for new resource types) === | ||
==== Accounting Repo ==== | |||
* EMI 3 APEL client | * EMI 3 APEL client update released, first site now publishing in production | ||
* Cloud | * Regional APEL Server documentation/links to code sent to additional site (Taiwan) for testing. | ||
==== Accounting Portal ==== | |||
* Cloud accounting fixes | |||
== 4. Next Meetings == | == 4. Next Meetings == | ||
* Next JRA1 meeting: 13 May 2013 | |||
Latest revision as of 11:18, 6 January 2015
EGI Inspire Main page |
<< JRA1 weekly reports main page
1. Progress on Milestones Deliverables
- Periodic Report
PTs input collected. JRA1 contribution completed by this week.
- MS710 - Operational Tools Roadmap
Final version available at: https://documents.egi.eu/document/1501
- D7.3 - Annual Report on Operational Tool maintenance and development activity
Final version available at: https://documents.egi.eu/secure/ShowDocument?docid=1562
2. Critical Issues
- GOCDB issue: John Casson left the GOCDB team. This will delay the release of GOCDB v5. The delay should be in order of 2 months (v5 was expected for May/early June).
3. Major work done during the past week by task
3.1 TJRA1.1
- Periodic Report
- Metrics computation
- JRA1 monthly meeting preparation
- JRA1 action review
3.2 TJRA1.2 TJRA1.3 TJRA1.5
3.2.1 SAM
- Final version of EGI QR12
- Next SAM Update ongoing
3.2.2 GOCDB
- Hardware installation for new gocdb-failover at Daresbury labs.
- Initial review of JC's v5 code.
- Mentoring our new GOCDB mini-project developer.
3.2.3 GGUS
- Ticket monitoring
- Preparation of the next GGUS release
- Cleaning up support units after end of EMI project
- Defining new structure of PTs
3.2.4 Ops Portal
- Refactoring of the VO ID cards (bootstrap + Jquery)
3.2.5 Accounting Portal
- Continuing refactor of the code
- Changes for new accounting.
3.2.6 Metrics Portal
- Work for QR12
3.3 TJRA1.4 (Accounting for new resource types)
Accounting Repo
- EMI 3 APEL client update released, first site now publishing in production
- Regional APEL Server documentation/links to code sent to additional site (Taiwan) for testing.
Accounting Portal
- Cloud accounting fixes
4. Next Meetings