EGI-InSPIRE:Amb 2014-02-05

From EGIWiki
(Redirected from Inspire amb 2014-02-05)
Jump to navigation Jump to search
EGI Inspire Main page



Back to the AMB wiki home page

Activity Reports

NA1

NA2

NA2.2

NA2.3 Strategic Planning and Policy Support

NA2.4 Events

NA2.5

BioVeL

  • Planning for Strategy meeting (To be held next week in Finland)
  • ST-weekly meeting
  • Handle certificate problem for BGBM.org users

ER-flow

  • Planning for the hackathon at the EGI CF
  • Nagios instance for shiwa-workflow.eu VO (discussing with Sara people)
  • Enabling VAPOR for testing shiwa-workflow.eu VO (configuring and testing stage in progress by Franck)
  • Hands on using SSP latest portal within shiwa-workflow.eu VO (defining strategy, creating material for website for presenting to the users about the available services)
  • Reporting bugs/issues to the SHIWA User Forum

Major Events Planned

SA1

https://wiki.egi.eu/wiki/Inspire_sa1_2014-02-04

SA2

SA4

TSA4.1 - Management

  • weekly report compilation
  • Assembling QR15 contributions

TSA4.2 - MOOC

Progress
  • We've started contacting those students who have passed the course.
  • We've created an example solution for the final assignment
Plans for next week
  • Creating course certificates
  • Creating a video explaining the example solution
  • Preparing a presentation about the project

TSA4.3 - Liferay

bi-weekly reporting

TSA4.4 - OCCI for CMF

rOCCI-core
  • bugfix releases 4.2.6 and 4.2.7
rOCCI-api
  • testing RC1
rOCCI-cli
  • testing RC1
rOCCI-server
  • upgrading local infrastructure
  • working on installation & configuration docs
ToDo for next week
  • interoperability testing
  • in parallel, continue working on the rOCCI framework
Problems
  • None (yet :-))
Delays
  • Still approx. one month (== Florian's contribution), no further delay

TSA4.5 - CDMI in CMF

bi-weekly reporting

TSA4.6 - OCCI CompClouds

nothing to report

TSA4.7 - AppDeployment

Progress
  • Preparation of sessions abstracts for EGI CF 2014
  • VM launching now available at the frontend
  • Testing with local users
Plans for next week
  • Continue the front-end implementation
  • Submit abstracts for EGI CF 2014
Issues

- Still delayed on the front-end implementation, but we are putting most of our effort there.

TSA4.8 - CloudCapabilities

Progress
  • We made good progress with the BNCweb use case, upgrading and shrinking the original image. All relevant components, i.e. DB data image, db server image, and web server image, are available now.
  • cloud-init including support for ONE is now available for Debian Wheezy.
Plans for next weeks
  • The BNCweb work needs to be finalized by allowing to contextualize the DB connection as well and providing generic instruction about how to deploy the application components.
  • cloud-init for Debian Wheezy needs to be tested also in OS to check that it can retrieve a configuration from the metadata service. Also, the basic configuration should be aligned and documented.
  • We will need to start thinking about a structure for the tutorial at CF14.
Problems we encountered, but can solve in the mini-project
  • It is not quite clear how the copying of the DB data image for BNCweb is to be handled through OCCI, as implementations lack support for image copy (e.g. by restoring snapshots). We'll follow up on this issue.
Problems and issues we need external help with

None

TSA4.9 - VAPOR

bi-weekly reporting

TSA4.10 - CompReports

bi-weekly reporting

TSA4.12 - AllocateFedRes

VT_Resource_Allocation_Tools#Report_due_31.01.2014

JRA1

Report: Inspire jra1 2014-02-04

Participants

Discussion