EGI-InSPIRE:Jra1 2014-04-01

From EGIWiki
Jump to: navigation, search
EGI Inspire Main page


<< JRA1 weekly reports main page


1. Progress on Milestones Deliverables

  • Current Status: Done
  • D7.4
  • QR15
    • JRA1 contribution sent to AMB

2. Critical Issues

  • Nothing new to report

3. Major work done during the past week by task

3.1 TJRA1.1

  • Tools roadmap review
  • D7.4: external review
  • Monthly JRA1 meeting (26 March)
  • 7th SAM Migration meeting (27 March)
  • Pay-for-Use meeting (28 March)
  • Meeting scheduled to discuss EGI requirements on SAM for PY5 (9 April)

3.2 TJRA1.2 TJRA1.3 TJRA1.5

3.2.1 SAM

  • Reconfigured ops-­monitor to track Update-­22 deployment
  • Migration of SAM central services
    • Established production instance at IN2P3
    • comparison of A/R, report generation, few operational issues
    • Established opsmon.egi.eu at SRCE
    • Campaign on mon.egi.eu, opsmon.egi.eu aliases started
      • Reconfigured grid-­monitoring to track adoption of mon.egi.eu
    • Decommissioning CERN central pre-­production instance (ongoing)
    • Migration of CERN central instance to dedicated messaging for non-­OPS monitoring (ongoing)

3.2.2 GOCDB

  • New IPv6 network range fields added to GOCDB for Sites and Services
  • New role type requested – ‘SiteMonitor’
  • New service type requested 'hu.guse.ws-pgrade'

3.2.3 GGUS

  • Implementation and testing of CMS integration into GGUS
  • GGUS release
  • Fixing problems after GGUS release
  • GGUS AB
  • Ticket monitoring

3.2.4 Ops Portal

  • Working on user feedback from the candidate release (improvements and bug fixing)
  • Preparation for the deployment in production of the new release

3.2.5 Accounting Repository

  • No report received

3.2.6 Accounting Portal

  • Security work.
  • Continuing refactor of the code.
  • Changes on custom VO handling.
  • Updated RT tickets on dashboard.

3.2.7 Metrics Portal

  • Maintenance
  • Bug fixing
  • RT ticket updating
  • Certificate and server updating

3.3 TJRA1.4 (Accounting for new resource types)

3.3.1 Accounting Repository

  • No report received

3.3.2 Accounting Portal

  • Work on pay-per-use, user views implemented.
  • Work on pay-per-use, per-user cost calculation
  • Work on pay-per-use, VAT cost calculation

4. Next Meetings

  • SAM roadmap in PY5: 9 April 2014
  • Migration of SAM Central Services - 8th meeting: week before Easter (doodle)
  • Next JRA1 Meeting: 23 April 2014