EGI.eu distributes separately the funding related to the global efforts declared. A cumulative overview table is available.

Project Advance payments

A pre-financing payment equating to 40% of the total budget for the project was released from EC to EGI. From this, EGI is required to place 5% (of the total budget) in a Participant Guarantee Fund account managed by the European Investment Bank. When the project completes, this 5% will be returned to the participants with the final payment.

Quarterly payment are set-up to cover costs incurred in a quarter. It is based on the PPT effort returns.


Final payment

The details of the Payment related to the closure of the project are available here. It includes:

- PY5 complete overview
- Final payment
- Payment Summary

and the supporting documentation from the Commission:


Advance 13

The details of the Payment related to PY4 financial reporting are available here. It contains the following:

- Payment Summary
- PY4 complete overview

and the supporting documentation from the Commission:


Advance 12

The details of the Payments of PY3 closure are available here. It contains the following spreadsheets:

EGI-InSPIRE payment details:

- Payment Summary
- PY3 complete overview
- Q12 Global Tasks Payment

and the supporting documentation from the Commission:


Advance 11

EC deliverable EGI-MS (PQ11)

The details of the Payments of PQ11 Nov2012-Jan2013 available here; it contains the following 3 spreadsheets:

In addition is also available the overview of the distribution of the grant versus the work declared in PPT from the start of the project: DISTRIBUTION OF THE GRANT ANNUAL

Advance 10

EC deliverable EGI MS-PQ10

The details of the Payments of PQ10 Aug2012-Oct2012 available here; it contains the following 3 spreadsheets:

In addition is also available the overview of the distribution of the grant versus the work declared in PPT from the start of the project: DISTRIBUTION OF THE GRANT ANNUAL-wiki

Advance 9

EC deliverable EGI-MS(PQ9)

The details of the Payments of PQ9 May2012-Jul2012 available here; it contains the following spreadsheets:

In addition is also available the overview of the distribution of the grant versus the work declared in PPT from the start of the project: DISTRIBUTION OF THE GRANT ANNUAL-wiki

Advance 8

The details of the Payments of PY2 closure are available here. It contains the following spreadsheets:

and the supporting documentation from the Commission:


Advance 7

EC deliverable EGI-MS114-CO-(PQ7)

The details of the Payments of PQ7 Nov2011-Jan 2012 available here; it contains the following 3 spreadsheets:

In addition is also available the overview of the ditribution of the grant versus the work declared in PPT from the start of the project: DISTRIBUTION OF THE GRANT ANNUAL-wiki

Advance 6

EC deliverable EGI-MS113-CO-(PQ6)

The details of the Payments of PQ6 Aug-Oct 2011 available here; it contains the following 3 spreadsheets:

In addition here is also available the overview of the ditribution of the grant versus the work declare din PPT from the start of the project: DISTRIBUTION OF THE GRANT ANNUAL-wiki

Advance 5

EC deliverable MS112-CO

The details of the Payments of PQ5 May-July 2011 available here:

Advance 4

Costs accepted on 14/12/2011: EC deliverable MS111-CO

YEAR 1 EC summaries, download the following files here:

The details of the payment and summary is available here:

Note that Year1 balance of costs accepted versus quarterly payments excludes the 6 months prefinancing released along with Advance Nr1, which is considered as cash flow.

Advance 3

EC deliverable MS107-CO [MS-107-CO]

Payments of Q3 Nov-Dec 2010-Jan 2011: download the files [here]


Advance 2

EC deliverable MS106-CO

Detailed Summary Payment per partners and JRUs This spreadsheet summarises the payments related to PQ2 and EGI.eu contribution to the Global efforts.

Advance 1

It is the responsibility of the Lead Beneficiary to redistribute the money to its JRUs. The following table shows the share of funding for each participant, Leads and JRUs, for the total funding.

Pre-Financing and payment of Q1 May-June-July 2010:

40% of the total pre-financing received from the EC is decreased with the 5% corresponding to the PFG (Participant Guarantee Fund). The remaining 35% are distributed as follows:

Then EGI.eu distributes separately the funding related to the global efforts declared in Q1 see Table 3.