This page describes steps which should be taken by COD shifter to follow availability/reliability issues.

When GGUS ticket about availability/reliability metrics is assigned to COD:

  1. add ticket url to Availability and reliability internal procedure for COD tickets page
  2. review Ava/Rel report and prepare following lists:
    • CASE 1: sites for suspension (Look at two previous months in AR report and the current one. If all are below 50% then sites qualifies for suspension.)
    • CASE 2: sites to be asked for explanation (below 75% for reliability and 70% for availability)
  1. Generate child tickets for both lists
    • for CASE1: when explanation was provided and is found satisfactory, set child ticket to 'verified' status
  1. When the deadline (7 working days) expired:
    • suspend in GOC DB sites qualified for suspension
    • prepare summary report of explanations (it should be placed in parent ticket):
      • sites which are not responsive
      • sites which provided not satisfactory explanation
      • ROCs/NGIs which are not responsive