Line 57: Line 57:


== Reports ==  
== Reports ==  
=== Report due 02.08.2013 ===
==== Work achieved last two weeks ====
* Continuation of implementation of initial workflow for RA process
* Design of federated resources presentation
* Implementation of editing pools
==== Work planned for next two weeks ====
* Implementation of right-to-revoke and free-hand allocation scenarios
* Preparation of materials for RA TF
* Implementation of presentation of state of federated resources
==== Progress against the goals in the project plan ====
* Implementation phase in progress
==== Issues that the virtual team leader needs help with ====
NONE





Revision as of 15:45, 6 August 2013

General Project Information

  • Leader: Tomasz Szepieniec
  • Mailing List: -
  • Meetings:
  • Status: In progress
  • Start Date: 1.04.2013
  • Duration: 30.03.2014
  • Customer: EGI Operation (Tiziana Ferrari)

Motivation

TODO

Objectives

TODO

Tasks

List and describe the specific tasks with target dates for completion.

Outcomes/Deliverables

  • Deliverable 1 description and target date
  • Deliverable 2 description

Members

  • Tomasz Szepieniec, ACC Cyfronet AGH, coordinator
  • Michał Dobrzański, ACC Cyfronet AGH, developer
  • Tomasz Zatorski, ACC Cyfronet AGH, developer
  • Cyril L'Orphelin, CNRS (IN2P3), developer


  • Tiziana Ferrari, Technical Shepard


Emerging Information

N/A

Resources

TODO

Progress Reporting

Progress report will be delivered bi-weekly, by updating this page.

The report will be due by 17:00 on Fridays and is to contain details of:

  • Work achieved that week
  • Work planned for next week
  • Progress against the goals in the project plan
  • Issues that the virtual team leader needs help with (e.g. non-responsive partners, more resources, support from EGI.eu teams, etc.)

The Team project manager will also provide a more comprehensive input for the EGI InSPIRE quarterly reporting.

Reports

Report due 02.08.2013

Work achieved last two weeks

  • Continuation of implementation of initial workflow for RA process
  • Design of federated resources presentation
  • Implementation of editing pools

Work planned for next two weeks

  • Implementation of right-to-revoke and free-hand allocation scenarios
  • Preparation of materials for RA TF
  • Implementation of presentation of state of federated resources

Progress against the goals in the project plan

  • Implementation phase in progress

Issues that the virtual team leader needs help with

NONE



Report due 19.07.2013

Work achieved last two weeks

  • Continuation of implementation of initial workflow for RA process
  • Works on integration with EGI SSO
  • Draft implementation of editing pools

Work planned for next two weeks

  • Continuation of implementation of initial workflow for RA process
  • Design of federated resources presentation

Progress against the goals in the project plan

  • Implementation phase in progress

Issues that the virtual team leader needs help with

NONE


Report due 05.07.2013

Work achieved last two weeks

  • Works on integration with GOCDB and EGI SSO
  • Implementing initial workflow for RA process
  • working meeting with EGI.eu operation staff (2.07 10:00- 11:00)

Work planned for next two weeks

  • Continuation of implementation of initial workflow for RA process

Progress against the goals in the project plan

  • Implementation phase in progress

Issues that the virtual team leader needs help with

NONE


Report due 21.06.2013

Work achieved last two weeks

Work planned for next two weeks

  • Works on integration with GOCDB and EGI SSO
  • Implementing initial workflow for RA process

Progress against the goals in the project plan

  • Implementation phase in progress

Issues that the virtual team leader needs help with

NONE


Report due 21.06.2013

Work achieved last two weeks

Work planned for next two weeks

  • Works on integration with GOCDB and EGI SSO
  • Implementing initial workflow for RA process

Progress against the goals in the project plan

  • Implementation phase in progress

Issues that the virtual team leader needs help with

NONE


Report due 07.06.2013

Work achieved last two weeks

  • Set-up of implementation environment
  • Initial structure of SLA implementation

Work planned for next two weeks

  • Planning initial (testing) workflow of SLA negotiations
  • Study of rules for 1st prototype

Progress against the goals in the project plan

  • Implementation phase started acccording to schedule

Issues that the virtual team leader needs help with

NONE


Report due 24.05.2013

Work achieved last two weeks

  • Completed work on design and functional specification
  • Decision on technical platform was made (Agreemount framework)
  • New developed employed (Tomasz Zatorski)

Work planned for next two weeks

  • Organizing implementation works

Progress against the goals in the project plan

  • Design of the the tools were completed, except detailed operation procedure the is not prepared yet by operation.

Issues that the virtual team leader needs help with

NONE

Report due 10.05.2013

Work achieved next two weeks

  • Miniproject Kick-off meeting was held in Amsterdam
  • Details of functionality for the first protype agreed with client

Work planned for last two weeks

  • Completion of technical design
  • Decision on the platform

Progress against the goals in the project plan

N/A

Issues that the virtual team leader needs help with

NONE