Difference between revisions of "Service for AAI: EGI Catchall Availability and continuity Plan"

From EGIWiki
Jump to navigation Jump to search
Line 141: Line 141:
| 2018-11-07
| 2018-11-07
| plan finalised
| plan finalised
|-
| <br>
| Alessandro Paolini
| 2019-11-26
| starting the yearly review....
|-
|-
|
|

Revision as of 10:13, 26 November 2019

Main EGI.eu operations services Support Documentation Tools Activities Performance Technology Catch-all Services Resource Allocation Security


Documentation menu: Home Manuals Procedures Training Other Contact For: VO managers Administrators


Back to main page: Services Availability Continuity Plans

Introduction

This page reports on the Availability and Continuity Plan for the EGI Catchall and it is the result of the risks assessment conducted for this service: a series of risks and treats has been identified and analysed, along with the correspondent countermeasures currently in place. Whenever a countermeasure is not considered satisfactory for either avoiding or reducing the likelihood of the occurrence of a risk, or its impact, it is agreed with the service provider a new treatment for improving the availability and continuity of the service. The process is concluded with an availability and continuity test.

Last Next
Risks assessment 2018-10-24 Q4 2019
Av/Co plan 2018-11-07 Q4 2019

Performances

The performances reports in terms of Availability and Reliability are produced by ARGO on an almost real time basis and they are also periodically collected into the Documentation Database.

In the OLA it was agreed the following performances targets, on a monthly basis:

  • Availability: 95%
  • Reliability 99%

Over the past years, EGI Catchall hadn't particular Av/Co issues highlighted by the performances that need to be further investigated.

Risks assessment and management

For more details, please look at the google spreadsheet. We will report here a summary of the assessment.

Risks analysis (to update)

Risk id Risk description Affected components Established measures Risk level Treatment Expected duration of downtime / time for recovery
1 Service unavailable / loss of data due to hardware failure VOMS database, MyProxy proxy files The VOMS database and the MyProxy proxy directory are regularly backuped. Additionally, they are running on a redundant VM environment, on a redundant storage Low Service restored from backups 1 working day
2 Service unavailable / loss of data due to software failure VOMS database, MyProxy proxy files The VOMS database and the MyProxy proxy directory are regularly backuped. Additionally, they are running on a redundant VM environment, on a redundant storage Low Service restored from backups 1 working day
3 service unavailable / loss of data due to human error VOMS database, MyProxy proxy files The VOMS database and the MyProxy proxy directory are regularly backuped. Additionally, they are running on a redundant VM environment, on a redundant storage Low Service restored from backups 1 working day
4 service unavailable for network failure (Network outage with causes external of the site) VOMS, MyProxy There are redundant uplinks connecting the data center to the public network. Medium Service restored from backups 1 working day
5 Unavailability of key technical and support staff (holidays period, sickness, ...) VOMS, MyProxy There is always one member of the team available. Low - -
6 Major disruption in the data centre. Fire, flood or electric failure for example VOMS database, MyProxy proxy files The data center is well maintained, with UPS, diesel generator and fire suppression system. Medium Service restored from backups 1 or more working days
7 Major security incident. The system is compromised by external attackers and needs to be reinstalled and restored. VOMS database, MyProxy proxy files The VOMS database and the MyProxy proxy directory are regularly backuped. Low Service restored from backups 1 working day
8 (D)DOS attack. The service is unavailable because of a coordinated DDOS. VOMS, MyProxy The network is monitored for DDOS attacks by GRNET NOC. Medium Service restored from backups 1 working day

Outcome

The level of all the identified risks is acceptable and the countermeasures already adopted are considered satisfactory

Availability and Continuity test

The critical level of this service is low.

Taking into account the availability and continuity measures adopted by the provider, and considering that the VOMS and MyProxy services are quite easy to install, we don't require a continuity/recovery test for this service: the team has extensive experience with VOMS and is able to to install a new instance rapidly if its needed.

Revision History

Version Authors Date Comments

Alessandro Paolini 2018-11-02 first draft, discussing with the provider

Alessandro Paolini 2018-11-07 plan finalised

Alessandro Paolini 2019-11-26 starting the yearly review....