PROC25
Jump to navigation
Jump to search
Steps
Responsible | Action | Notes | |
---|---|---|---|
1 | Product team | submits a ggus ticket for the "EGI Software provisioning support" support unit with the following information
|
|
2 | Stage rollout manager | product release is injected in the EGI SW provisioning infrastructure
|
This action must be completed within 5 working days after step 1. |
3 | UMD team, quality assurance | Begin of verification
|
This action must start within one month after step 2 is completed.
This action must be completed in one week.
|
4 | Staged Rollout manager | Begin staged rollout
|
This action must be completed in one month
|
5 | Staged rollout manager | Complete staged rollout
|
Notes
- The whole process should not last longer than 2 months without providing any information to the product team about delays through the RT ticket.