The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
In the table below, you should provide your self-assessment for the EGI-InSPIRE "NGI International Tasks" for milestone MS124 "NGI International Tasks Review"
For more information on how to complete the tables, read the dedicated Instructions Page
Notes:
- This milestone is an assessment of services from a managerial perspective and should be reported as an evaluation of the services (e.g. objectives being met; resources to effort; issues; suggested strategic changes).
- 'DO NOT' report what your NGI did for those tasks/services as this is covered by the Quarterly Reports.
- In order to edit this page, you need to log in with your EGI SSO account and click 'edit' on the tab (top of this page).
EGI-InSPIRE Task
|
Task Name
|
Assessment
|
Score
|
How to Improve
|
After EGI-InSPIRE**
|
*NA2U.2E
|
Marketing
|
-
|
-
|
-
|
|
NA2.1N
|
NGI International Liaison
|
Objectives of this task are being met.
|
4
|
-
|
Best effort basis
|
NA2.6N
|
Distributed Competency Centre
|
Virtual Team projects are good way of solving emerging issues in inter-NGI collaborative way.
|
4
|
-
|
|
*Please provide your external assessment on the quality of the service, which is delivered as a Global Task (scores and feedback will be included as part of MS123 - Global Task Review).
**Please comment on the continuation or service impact at the end of EC funding regarding the EGI-InSPIRE task/service.
Operations
EGI-InSPIRE Task
|
Task Name
|
Assessment
|
Score
|
How to Improve
|
After EGI-InSPIRE**
|
SA1.1N
|
NGI Activity Management
|
Internal operational activities are operating efficiently.
|
4
|
-
|
Could be covered by effort from related national research projects
|
SA1.2N
|
A Secure Infrastructure
|
Objectives of this task are fulfilled in satisfying manner.
|
3
|
-
|
Could be covered by effort from related national research projects
|
SA1.3N
|
Service Deployment
|
Objectives of this task are met.
|
3
|
More resource centers should take part in the staged roll-out process.
|
-
|
SA1.4N
|
Infrastructure for Grid Management
|
Objectives of this task are met.
|
4
|
-
|
Could be covered by effort from related national research projects
|
SA1.5N
|
Accounting
|
Objectives of this task are mostly met.
|
3
|
Implementation of the APEL publisher with the feature of stripping out the Common Name from the user DN.
|
Best effort basis
|
SA1.6N
|
Helpdesk Infrastructure
|
Objectives of this task are being met (one excellent example is integration of National Helpdesks and GGUS, operating without any problems).
|
4
|
Response times of certain support units could be shorter.
|
Could be covered by effort from related national research projects
|
SA1.7N
|
Support Teams
|
Objectives of this task are met.
|
4
|
-
|
Best effort basis
|
SA1.8N
|
Providing a Reliable Grid Infrastructure
|
Objectives of this task are met.
|
4
|
-
|
Best effort basis
|
**Please comment on the continuation or service impact at the end of EC funding regarding the EGI-InSPIRE task/service. If you have no information you can leave this column blank.