This page contains the assessment of the NGI International Task at year 1 of the EGI-InSPIRE project (one page per NGI). The NGI representatives are required to fill the tables according to the required information. The content will be integral part of the EGI-InSPIRE milestone MS109 "NGI International Task Review"
- Main page with instructions
- In order to edit this page, you need to log in with your EGI SSO account and click 'edit' on the tab (top of this page)
User Services
Human Services (Table 1)
Table 1: NGI Assessment: User Services >> Human Services
EGI-InSPIRE
|
EGI_DS
|
Name
|
Assessment
|
Score
|
How to Improve
|
NA3.3N
|
U-N-3 U-N-13
|
Requirements Gathering
|
write here
|
0-5
|
write here
|
NA3.3N
|
U-N-14 U-N-15
|
Application Database
|
write here
|
0-5
|
write here
|
NA3.3N
|
U-N-16 U-N-17
|
Training
|
write here
|
0-5
|
write here
|
NA3.3N
|
U-N-12 U-N-18 U-N-19
|
Consultancy
|
write here
|
0-5
|
write here
|
Operations Services
Human Services (Table 2)
Table 2: NGI Assessment: Operations Services >> Human Services
EGI-InSPIRE
|
EGI_DS
|
Name
|
Assessment
|
Score
|
How to Improve
|
SA1.4N
|
O-N-9
|
Requirements Gathering
|
Small community makes direct contact prefered solution
|
3
|
Education efforts should (and have already been) increased
|
SA1.1N
|
O-N-9
|
Operations Coordination
|
Small number of sites closely cooperating
|
4
|
Help migration of sites to EGI infrastructure where applicable
|
SA1.2N
|
O-N-9
|
Security
|
Security related problems were properly followed
|
4
|
Improve NGI security related infrastructure and resources
|
Infrastructure Services (Table 3)
Table 3: NGI Assessment: Operations Services >> Infrastructure Services
EGI-InSPIRE
|
EGI_DS
|
Name
|
Assessment
|
Score
|
How to Improve
|
SA1.3N
|
O-N-9
|
Software Rollout
|
Small number of sites simplifies rollout, but must plan for larger infrastructure
|
3
|
This issue will need to be tackled more directly when the NGI infrastructure increases
|
SA1.4N
|
O-N-3
|
Monitoring
|
National Nagios monitoring as well as SEE-GRID based monitoring are operational, we are providing monitoring for sites that are not a part of any production infrastructure in the region via BBmSAM system at BA-01-ETFBL site. We are also developing a grid monitoring SNMP bridge/adapter in order to enable easier monitoring of all the layers of the infrastructure in exiting network management/monitoring systems (to ease debugging and enable closer cooperation with REN).
|
5
|
Continue working and adapt to new requirements
|
SA1.5N
|
O-N-2
|
Accounting
|
Just one site certified and using ActiveMQ
|
2
|
This issue will need to be tackled more directly when the NGI infrastructure increases
|
SA1.4N
|
O-N-1 O-N-4
|
Configuration Repository and Operations Portal
|
Usage as expected (some minor inaccessibility issues with Dashboard)
|
3
|
Introduce proper mobile optimized page
|
SA1.6N SA1.7N
|
O-N-6 O-N-7
|
Helpdesk
|
Small NGI using central GGUS. Some issues with GGUS access via X.509 certificates are being dealt with
|
3
|
When time comes create national helpdesk
|
SA1.8N
|
O-N-5 O-N-8
|
Core Services
|
Core services working properly. CA does not exist, activities on setting up NGI CA in progress
|
3
|
Set up CA and redundant services
|
Other (Table 4)
Table 4: NGI Assessment: Other
EGI-InSPIRE
|
EGI_DS
|
Name
|
Assessment
|
Score
|
How to Improve
|
NA2.3N
|
|
Policy Development
|
Policies implemented on best effort basis
|
2
|
Implement all applicable policies (serious work needed in some areas)
|
NA2.2N
|
E-N-2
|
Dissemination
|
Dissemination 9and training) efforts significantly stepped up - close cooperation with HPC related dissemination and HP-SEE project.
|
3
|
Focus on a larger number of smaller scale first party events.
|