Alert.png The wiki is deprecated and due to be decommissioned by the end of September 2022.
The content is being migrated to other supports, new updates will be ignored and lost.
If needed you can get in touch with EGI SDIS team using operations @ egi.eu.

Difference between revisions of "EU deliverable review procedure"

From EGIWiki
Jump to navigation Jump to search
(Created page with '{| border="1" |- | '''Time before submission''' || '''State in AMB RT Queue''' || '''Material'''|| |- | 6 weeks || ToC || Document skeleton created and first version of the docum…')
 
 
(9 intermediate revisions by one other user not shown)
Line 1: Line 1:
{| border="1"
#REDIRECT [[EGI-InSPIRE:Review process for deliverables and milestones]]
|-
| '''Time before submission''' || '''State in AMB RT Queue''' || '''Material'''||
|-
| 6 weeks || ToC || Document skeleton created and first version of the document with the table of contents entered into the document.
|-
| 4 weeks || Draft || A full draft is available in the repository that has been reviewed within the activity.
|-
| 2 weeks || Review || A review led by a moderator and three reviewers using the document comments form has been completed and responded to by the document authors. This may take multiple cycles.
|-
| 2 weeks || AMB Review || Document starts being reviewed by the AMB.
|-
| 1 week || PMB Review|| Document starts being reviewed by the PMB.
|-
|Deadline || With EC|| A clean version of the document is in the document repository. ||

Latest revision as of 12:42, 5 June 2015