! scope="row"| Risks assessment
! scope="row"| Risks assessment
|  
| 2020 Jul
|  
| Q3 2021
|-
|-
! scope="row"| Av/Co plan and test
! scope="row"| Av/Co plan and test
|  
| 2020 Nov
|  
| Q3 2021
|-
|-
|}
|}


= Availability requirements and performances =
= Availability requirements and performances =
<pre style="color: blue">
 
List the Service Level Targets as agreed in the OLA/UA
Service level targets:
* Availability: 90%
* Reliability 95%


Other ava requirements:
Other ava requirements:
 
* The service is accessible via webUI
the service is accessible through X509 certificate and/or other authentication system
* The service availability is regularly tested by nagios probe org.nagiosexchange.Portal-WebCheck (currently on the uncert ARGO instance): https://argo-mon-uncert.cro-ngi.hr/nagios/cgi-bin/status.cgi?host=eosc-portal.eu&style=detail
The service is accessible via CLI and/or webUI (link to the probes that checks the authentication and the service in general)
(depending on the service, specific requirements can be identified. In case, for each requirement report what is the action/measure in case of failure)
Look at monitoring history, in case of particular issues
</pre>


= Risks assessment and management =
= Risks assessment and management =
Line 57: Line 55:
| EOSC Portal user GUI, EOSC Portal database
| EOSC Portal user GUI, EOSC Portal database
| All services are running on virtual machines. In case of hardware failure of the host machine the virtual machine can be re-instantiated.
| All services are running on virtual machines. In case of hardware failure of the host machine the virtual machine can be re-instantiated.
|  
| style="background: red"| High
|  
| up to 8 hours
|  
| style="background: red"| It is necessary to verify the implementation status of the hardware HA configuration.
|-
|-
| 2
| 2
Line 65: Line 63:
| EOSC Portal user GUI, EOSC Portal database
| EOSC Portal user GUI, EOSC Portal database
| All services databases are backed up on a tape storage. Service VM will be restored with the database back up from the tape storage.
| All services databases are backed up on a tape storage. Service VM will be restored with the database back up from the tape storage.
|  
| style="background: yellow"| Medium
|  
| 1 or more working days
|
|
|-
|-
Line 73: Line 71:
| EOSC Portal user GUI, EOSC Portal database
| EOSC Portal user GUI, EOSC Portal database
| Monitoring of system health, backups
| Monitoring of system health, backups
|  
| style="background: yellow"| Medium
|  
| up to 4 hours
|
|
|-
|-
Line 81: Line 79:
| EOSC POrtal user GUI
| EOSC POrtal user GUI
| Monitoring of system health, backups
| Monitoring of system health, backups
|
| style="background: yellow"| Medium
|  
| less than 1 hour
|
|
|-
|-
Line 89: Line 87:
|
|
| Monitoring of service availability, ACC Cyfronet AGH has redundant network connectivity.
| Monitoring of service availability, ACC Cyfronet AGH has redundant network connectivity.
|  
| style="background: green"| Low
|  
| up to 4 hours
|
|
|-
|-
Line 97: Line 95:
| EOSC Portal user GUI, EOSC Portal database
| EOSC Portal user GUI, EOSC Portal database
| More personnel may be involved in the operation of the EOSC Portal
| More personnel may be involved in the operation of the EOSC Portal
|  
| style="background: green"| Low
|  
| 1 or more working days
|
|
|-
|-
Line 105: Line 103:
| EOSC Portal user GUI, EOSC Portal database
| EOSC Portal user GUI, EOSC Portal database
| The computing centre has electric backup system and fire control devices.
| The computing centre has electric backup system and fire control devices.
|  
| style="background: yellow"| Medium
|  
| 1 or more working days
|
|
|-
|-
Line 113: Line 111:
| EOSC POrtal user GUI
| EOSC POrtal user GUI
| Monitoring of system health, security audits, backups, following best practices for security configuration and timely implementation of patches
| Monitoring of system health, security audits, backups, following best practices for security configuration and timely implementation of patches
|  
| style="background: green"| Low
|  
| up to 8 hours
|
|
|-
|-
Line 121: Line 119:
|  
|  
| Local network team provides monitoring and protection for DOS attacks, firewall can limit impact of the DDoS
| Local network team provides monitoring and protection for DOS attacks, firewall can limit impact of the DDoS
|  
| style="background: yellow"| Medium
|  
| up to 8 hours
|
|
|}
|}


== Outcome ==
== Outcome ==
Currently there is no hardware HA configuration. It is important agreeing with the provider a plan for implementing it in order to decrease the rating of risk number 1.


== Additional information ==
== Additional information ==


<pre style="color: blue">
The provider has got internal procedures to invoke in case of risk occurrence
procedures for the several countermeasures to invoke in case of risk occurrence (put a link if public)


Specify if the Availability targets are different in case the plan is invoked.
The Availability targets don't change in case the plan is invoked.


Specify the recovery requirements (in general they are the outcomes of the BIA).
Recovery requirements:
*Maximum tolerable period of disruption (MTPoD) (the maximum amount of time that a service can be unavailable or undelivered after an event that causes disruption to operations, before its stakeholders perceive unacceptable consequences): 1 day
*Recovery time objective (RTO) (the acceptable amount of time to restore the service in order to avoid unacceptable consequences associated with a break in continuity (this has to be less than MTPoD)): 4 hours
*Recovery point objective (RPO) (the acceptable latency of data that will not be recovered): n.a.


Specify if there is a particular approach for the return to normal working conditions if different from what already reported in the risk assessment.
Approach for the return to normal working conditions as reported in the risk assessment.
 
The support unit ... shall be used to report any incident or service request
 
The providers can contact EGI Operations via ticket or email in case the continuity plan is invoked, or to discuss any change to it.
</pre>


= Availability and Continuity test =
= Availability and Continuity test =
<pre style="color: blue">
The proposed A/C test will focus on a recovery scenario: the service is supposed to have been disrupted and needs to be reinstalled from scratch. Typically this covers the risks 1,3, and 8. The last backup of the data will be used for restoring the service, verifying how much information will be lost, and the time spent will be measured.
The proposed A/C test will focus on a recovery scenario: the service is supposed to have been disrupted and needs to be reinstalled from scratch. Typically this covers the risks #,#, and #. The last backup of the data will be used for restoring the service, verifying how much information will be lost, and the time spent will be measured.


Performing this test will be useful to spot any issue in the recovery procedures of the service.
Performing this test will be useful to spot any issue in the recovery procedures of the service.
</pre>


== Test details and outcome ==
== Test details and outcome ==
The overall time needed to recover the service: 4h
The [https://docs.google.com/document/d/1XFtsShYbvZd4CpFYNuJe-KSXXMdlUMx15GCYhiOZ654/edit?pli=1 proposed test] focused on a recovery scenario:
# Restore virtual machines from backups (tapes) (haproxy,apache httpd, mysql)
# Restore databases data using the latest dump.
# Setup haproxy to proxy services from new machines.
# Associate floating IP addresses in OpenStack to haproxy service and open firewall.
# Test instance https:/eosc-portal.eu


= Revision History  =
= Revision History  =
Line 162: Line 164:
! Comments
! Comments
|-
|-
| <br>
|
|  
| Alessandro Paolini
|  
| 2020-07-02
|
| risk assessment completed
|-
| Alessandro Paolini
| 2020-11-10
| plan completed
|-
|-
| <br>
| <br>

Latest revision as of 10:39, 10 November 2020

Main EGI.eu operations services Support Documentation Tools Activities Performance Technology Catch-all Services Resource Allocation Security


Documentation menu: Home Manuals Procedures Training Other Contact For: VO managers Administrators


Back to main page: Services Availability Continuity Plans

work in progress

Introduction

This page reports on the Availability and Continuity Plan for the EOSC Portal and it is the result of the risks assessment conducted for this service: a series of risks and treats has been identified and analysed, along with the correspondent countermeasures currently in place. Whenever a countermeasure is not considered satisfactory for either avoiding or reducing the likelihood of the occurrence of a risk, or its impact, it is agreed with the service provider a new treatment for improving the availability and continuity of the service. The process is concluded with an availability and continuity test.

Last Next
Risks assessment 2020 Jul Q3 2021
Av/Co plan and test 2020 Nov Q3 2021

Availability requirements and performances

Service level targets:

  • Availability: 90%
  • Reliability 95%

Other ava requirements:

Risks assessment and management

For more details, please look at the google spreadsheet. We will report here a summary of the assessment.

Risks analysis

Risk id Risk description Affected components Established measures Risk level Expected duration of downtime / time for recovery Comment
1 Service unavailable / loss of data due to hardware failure EOSC Portal user GUI, EOSC Portal database All services are running on virtual machines. In case of hardware failure of the host machine the virtual machine can be re-instantiated. High up to 8 hours It is necessary to verify the implementation status of the hardware HA configuration.
2 Service unavailable / loss of data due to CEPH file system in the cloud infrastructure EOSC Portal user GUI, EOSC Portal database All services databases are backed up on a tape storage. Service VM will be restored with the database back up from the tape storage. Medium 1 or more working days
3 Service unavailable / loss of data due to software failure EOSC Portal user GUI, EOSC Portal database Monitoring of system health, backups Medium up to 4 hours
4 service unavailable / loss of data due to human error EOSC POrtal user GUI Monitoring of system health, backups Medium less than 1 hour
5 service unavailable for network failure (Network outage with causes external of the site) Monitoring of service availability, ACC Cyfronet AGH has redundant network connectivity. Low up to 4 hours
6 Unavailability of key technical and support staff (holidays period, sickness, ...) EOSC Portal user GUI, EOSC Portal database More personnel may be involved in the operation of the EOSC Portal Low 1 or more working days
7 Major disruption in the data centre. Fire, flood or electric failure for example EOSC Portal user GUI, EOSC Portal database The computing centre has electric backup system and fire control devices. Medium 1 or more working days
8 Major security incident. The system is compromised by external attackers and needs to be reinstalled and restored. EOSC POrtal user GUI Monitoring of system health, security audits, backups, following best practices for security configuration and timely implementation of patches Low up to 8 hours
9 (D)DOS attack. The service is unavailable because of a coordinated DDOS. Local network team provides monitoring and protection for DOS attacks, firewall can limit impact of the DDoS Medium up to 8 hours

Outcome

Currently there is no hardware HA configuration. It is important agreeing with the provider a plan for implementing it in order to decrease the rating of risk number 1.

Additional information

The provider has got internal procedures to invoke in case of risk occurrence

The Availability targets don't change in case the plan is invoked.

Recovery requirements:

  • Maximum tolerable period of disruption (MTPoD) (the maximum amount of time that a service can be unavailable or undelivered after an event that causes disruption to operations, before its stakeholders perceive unacceptable consequences): 1 day
  • Recovery time objective (RTO) (the acceptable amount of time to restore the service in order to avoid unacceptable consequences associated with a break in continuity (this has to be less than MTPoD)): 4 hours
  • Recovery point objective (RPO) (the acceptable latency of data that will not be recovered): n.a.

Approach for the return to normal working conditions as reported in the risk assessment.

Availability and Continuity test

The proposed A/C test will focus on a recovery scenario: the service is supposed to have been disrupted and needs to be reinstalled from scratch. Typically this covers the risks 1,3, and 8. The last backup of the data will be used for restoring the service, verifying how much information will be lost, and the time spent will be measured.

Performing this test will be useful to spot any issue in the recovery procedures of the service.

Test details and outcome

The overall time needed to recover the service: 4h

The proposed test focused on a recovery scenario:

  1. Restore virtual machines from backups (tapes) (haproxy,apache httpd, mysql)
  2. Restore databases data using the latest dump.
  3. Setup haproxy to proxy services from new machines.
  4. Associate floating IP addresses in OpenStack to haproxy service and open firewall.
  5. Test instance https:/eosc-portal.eu

Revision History

Version Authors Date Comments
Alessandro Paolini 2020-07-02 risk assessment completed
Alessandro Paolini 2020-11-10 plan completed