Wiki page for EGI InSPIRE SA2 activities

WP5-SA2

This activity will coordinate the external provision of software required by EGI to form the production infrastructure. It will:

  • Establish agreements with key software providers
  • Maintain the UMD Roadmap
  • Define general and component specific quality criteria to be applied to software components
  • Verify the software components against these criteria
  • Provide a repository for the software components within UMD and the related support tools
  • Provided a distributed "support unit" within the EGI Helpdesk infrastructure with expertise on the deployed middleware in production use.

Task Leaders

To contact all task leaders (see below), send mail to inspire-sa2-taskleaders@mailman.egi.eu[1].

Task Name Task Leader Deputy
TSA2.1 Activity Management Michel Drescher Steven Newhouse
TSA2.2 Definition of the UMD Quality Criteria Enol Fernandez del Castillo Carlos Fernandez Sanchez (temporary)
TSA2.3 Verification of conformance criteria Carlos Fernandez Sanchez Alvaro Simon
TSA2.4 Provision of a software repository and support tools Kostas Koumantaros Marios Chatziangelou
TSA2.5 Deployed Middleware Support Unit Henrik Thostrup Jensen Michael Gronager

Involved partners

EGI.eu - Netherlands
CESNET - Czech Republic
KIT-G - Germany
CSIC - Spain
GRNET - Greece
INFN - Italy
LIP - Portigal
UCPH - Denmark
VR-SNIC - Sweden
NORDUNET A/S - Denmark


TSA2.1 Activity Management (CTO, EGI.eu)

This task focuses on the management of the activity and the relationship with EGI’s software providers. Prioritised requirements from elsewhere in EGI are collated and distributed to the current software providers and published for the whole community. The functional roadmaps and release dates from individual software providers are assembled into an integrated UMD Roadmap. The projected UMD Roadmap is monitored and the effectiveness of software providers to deliver components to the required schedule and quality will be reported to the TCB. This work will be managed by the Technology Manager who reports to the Project Director and will hold regular meetings of the team to ensure effective coordination of its activities. Additional meetings will be held with the external providers to provide a forum for conflict resolution.

TSA2.2: Definition of the UMD quality criteria (Enol Fernandez, CSIC)

The generic component acceptance criteria will be provided and updated according to evolving needs. Specific criteria will be developed for components on the UMD Roadmap.

TSA2.3: Verification of conformance criteria (Carlos Fernandez, CESGA)

The components contributed to the repository will be validated against the generic and component specific conformance criteria. SA2 will be involved in pre-release component testing. Verification of each component will be summarised in an acceptance report, available with the component in the repository.

TSA2.4: Provision of a software repository and support tools (Kostas Koumantaros, GRNET)

Necessary services to deliver the functionality of the repository and its surrounding process (FTP server, web server, issue tracker, version control system, etc.) will be provided and maintained.

TSA2.5: Deployed Middleware Support Unit (Henrik Thostrup Jensen, NDGF)

Expertise is needed in the production infrastructure to debug problems and then to propose workarounds or solutions with the software used in production. This group will be deployed as a support unit (second line support) as part of the EGI Helpdesk and it will work closely with other EGI operations functions and the external software providers.

Deliverables

The following gives an overview of deliverables scheduled and published by EGI-InSPIRE SA2. For convenience, they are also available in the EGI-InSPIRE SA2 calendar.

Code Title Delivery PM Delivery CM Status Delivery CM
D5.1 UMD Roadmap 3 July 2010
D5.2 UMD Roadmap 9 January 2011
D5.3 Annual Report on the status of Software Provisioning activity and the work of DMSU 11 March 2011
D5.4 UMD Roadmap 15 July 2011
D5.5 UMD Roadmap 21 January 2012
D5.6 Annual Report on the status of Software Provisioning activity and the work of DMSU 23 March 2012
D5.7 UMD Roadmap 27 July 2012
D5.8 UMD Roadmap 33 January 2013
D5.9 Annual Report on the status of Software Provisioning activity and the work of DMSU 35 March 2013
D5.10 UMD Roadmap 39 July 2013
D5.11 UMD Roadmap 45 January 2014
D5.12 UMD Roadmap 47 March 2014

Milestones

The following gives an overview of milestones scheduled and published by EGI-InSPIRE SA2. For convenience, they are also available in the EGI-InSPIRE SA2 calendar.

Milestone Title Lead-Task Delivery PM Calendary Month
MS501 Establishment of the EGI Software Repository and associated support tools TSA2.4 1 May 2010
MS502 Deployed Middleware Support Unit Operations Procedures TSA2.5 2 June 2010
MS503 Software Provisioning Process TSA2.3 2 June 2010
MS504 EGI Software Repository – Architecture and Plans TSA2.4 3 July 2010
MS505 Service Level Agreement with a Software Provider TSA2.2 4 August 2010
MS506 EGI Software Repository – Architecture and Plans TSA2.4 13 May 2011
MS507 Deployed Middleware Support Unit Operations Procedures TSA2.5 14 June 2011
MS508 Software Provisioning Process TSA2.3 14 June 2011
MS509 Service Level Agreement with a Software Provider TSA2.2 16 August 2011
MS510 EGI Software Repository – Architecture and Plans TSA2.4 25 May 2012
MS511 Deployed Middleware Support Unit Operations Procedures TSA2.5 26 June 2012
MS512 Software Provisioning Process TSA2.3 26 June 2012
MS513 Service Level Agreement with a Software Provider TSA2.2 28 August 2012
MS514 EGI Software Repository – Architecture and Plans TSA2.4 37 May 2013
MS515 Deployed Middleware Support Unit Operations Procedures TSA2.5 38 June 2013
MS516 Software Provisioning Process TSA2.3 38 June 2013
MS517 Service Level Agreement with a Software Provider TSA2.2 40 August 2013