Alert.png The wiki is deprecated and due to be decommissioned by the end of September 2022.
The content is being migrated to other supports, new updates will be ignored and lost.
If needed you can get in touch with EGI SDIS team using operations @ egi.eu.

Difference between revisions of "EGI-InSPIRE:Plan 2014 SA1.8"

From EGIWiki
Jump to navigation Jump to search
Line 65: Line 65:
<!-- please make sure that the text here is self explanatory and sufficiently detailed-->
<!-- please make sure that the text here is self explanatory and sufficiently detailed-->


==== VO Services  ====
* Transition to EMI VOMS service for dteam VO completed successfully (September 2013).
** VOMRS interface no longer operational
** VO Database migrated
** Notifications mechanism built up from scratch (with NGI/ROC managers set as contact points)
** Based on EMI-3 VOMS-Admin and VOMS services
* Decomission of NGI legacy groups (i.e. NGI_IE)
==== EGI Catch All CA  ====
* RA changeover in Albania handled
* New RAs in South Africa, Nigeria and Tanzania trained & established.
* CA Changeover
** Policy approval by EUGridPMA
** New CA issues SHA-2 EE certificates.
** Old CA signs CRLs only and will continue to do so.
==== Core Services for Site Certification  ====
* Maintenance and update of certification portal code [https://site-certification.egi.eu/]
** Updated to latest RoR version framework
** Bug fixes
* Replacement of WMS and Top-BDII certification service endpoints with new ones (UMD-3)
=== Operational tools ====
* EGI Middleware Monitoring [[ https://midmon.egi.eu/nagios/ ]]
** Updates and maintenance
** Addition of new probes
* EGI Security Monitoring [[ https://secmon.egi.eu/nagios/ ]]
** Updates and maintenance
** Switchover to new SAM-Update-22 Box
** Addition of several new security probes


===Milestones not accomplished===
===Milestones not accomplished===
<!-- list here milestones that were not completed according to the envisaged schedule, saying why they were not completed, and the new schedule is -->
<!-- list here milestones that were not completed according to the envisaged schedule, saying why they were not completed, and the new schedule is -->


* Decomission of all dteam VO ROC legacy groups has not been completed. This task will go on in 2014.


== Plans for 2014 ==


== Plans for 2014 ==
==== VO Services  ====
 
Decomission of all dteam VO ROC legacy groups.
 
==== EGI Catch All CA  ====
 
Continue the support and operation of the EGI Catch All CA and the expansion of the RA Network as needed.
 
==== Core Services for Site Certification  ====
 
* Code base maintenance and bug fixes
 
==== Operational tools ====
 
* Addition of new probes (as requirements arise)
* Removal of old probes (i.e. removal of security checks running via secmon that should no longer be checked)

Revision as of 19:43, 30 January 2014

Main EGI.eu operations services Support Documentation Tools Activities Performance Technology Catch-all Services Resource Allocation Security


Inspire reports menu: Home SA1 weekly Reports SA1 Task QR Reports NGI QR Reports NGI QR User support Reports


Documentation

Assessment of progress in 2013

  • Creation of end user and site administrator knowledge base on EGI wiki.

OLA documents

  • Finalization of the EGI.eu OLA document
  • Update on RC OLA - changed required to by integration with new middlewares and cloud resources

Completed Activities and Milestones

  • MS425 - Operational Level Agreements (OLAs) within the EGI production infrastructure

Milestones not accomplished

Plans for 2014

QR1

  • creation of EGI.eu SLA between EGI.eu and NGIs
  • creation of EGI.eu OLA between EGI.eu and global tasks providers

QR2

  • Resource Allocation SLA
  • Review of SLAs with technology providers

Availability reporting

Assessment of progress in 2013

Completed Activities and Milestones

Operations tools and availability computations

  • Monthly A/R reporting and handling of re-computation requests [1]
  • Assessment of revision of current suspension policies (A/R thresholds)
  • Automation of A/R reporting investigated (also in the context of A/R mini project)

Milestones not accomplished

Plans for 2014

Availability/Reliability

  • TSA1.8 will continue the handling the validation and distribution of the monthly league tables regarding Resource Center and EGI.eu services and the maintenance of the relevant wiki space:
Availability_and_reliability_monthly_statistics

Catch all services and core grid services

Assessment of progress in 2013

Completed Activities and Milestones

VO Services

  • Transition to EMI VOMS service for dteam VO completed successfully (September 2013).
    • VOMRS interface no longer operational
    • VO Database migrated
    • Notifications mechanism built up from scratch (with NGI/ROC managers set as contact points)
    • Based on EMI-3 VOMS-Admin and VOMS services
  • Decomission of NGI legacy groups (i.e. NGI_IE)

EGI Catch All CA

  • RA changeover in Albania handled
  • New RAs in South Africa, Nigeria and Tanzania trained & established.
  • CA Changeover
    • Policy approval by EUGridPMA
    • New CA issues SHA-2 EE certificates.
    • Old CA signs CRLs only and will continue to do so.

Core Services for Site Certification

  • Maintenance and update of certification portal code [2]
    • Updated to latest RoR version framework
    • Bug fixes
  • Replacement of WMS and Top-BDII certification service endpoints with new ones (UMD-3)

Operational tools =

  • EGI Security Monitoring [[ https://secmon.egi.eu/nagios/ ]]
    • Updates and maintenance
    • Switchover to new SAM-Update-22 Box
    • Addition of several new security probes

Milestones not accomplished

  • Decomission of all dteam VO ROC legacy groups has not been completed. This task will go on in 2014.

Plans for 2014

VO Services

Decomission of all dteam VO ROC legacy groups.

EGI Catch All CA

Continue the support and operation of the EGI Catch All CA and the expansion of the RA Network as needed.

Core Services for Site Certification

  • Code base maintenance and bug fixes

Operational tools

  • Addition of new probes (as requirements arise)
  • Removal of old probes (i.e. removal of security checks running via secmon that should no longer be checked)