== Assessment of progress in 2012  ==
== Assessment of progress in 2012  ==
<!-- this task is about the operational activities around the running of the technical operational tools, it does not include JRA1 activities -->
<!-- this task is about the operational activities around the running of the technical operational tools, it does not include JRA1 activities -->
===Completed Activities and Milestones===
<!-- please make sure that the text here is self explanatory and sufficiently detailed-->


==== DTEAM VO Services  ====
==== DTEAM VO Services  ====
Line 66: Line 71:


* Certification portal maintenance operations [https://site-certification.egi.eu/]
* Certification portal maintenance operations [https://site-certification.egi.eu/]
===Completed Activities and Milestones===
<!-- please make sure that the text here is self explanatory and sufficiently detailed-->


===Milestones not accomplished===
===Milestones not accomplished===

Revision as of 20:01, 16 January 2013


Documentation

Assessment of progress in 2012

OLA documents

  • Finalized EGI.eu RP OLA document (March 2012) [1]
  • Finalized EGI.eu RC OLA document (March 2012) [2]
  • Initial version of EGI.eu OLA document produced (April 2012) [3]
  • Second version of EGI.eu OLA document produced (December 2012 - presented in December OMB) [4]

Completed Activities and Milestones

MSA 418

  • The MS418 milestone "Operational Level Agreements (OLAs) within the EGI production infrastructure" was achieved during 2012
    • MS418 document finalized [5]

Milestones not accomplished

Plans for 2013

Operational Level Agreements (OLAs)

Finalization of the EGI.eu OLA document produced is foreseen early in 2013 (first quarter)

Availability reporting

Assessment of progress in 2012

Completed Activities and Milestones

Milestones not accomplished

Plans for 2013

Catch all services and core grid services

Assessment of progress in 2012

Completed Activities and Milestones

DTEAM VO Services

  • Initialized following dteam VO groups: NGI_UA [6] and EGI
  • Decommissioned following dteam VO legacy group: ROC_UKI [7]

EGI Catch All CA

  • Established new Registration Authority setup for EGI.eu catch all Certification Authority in Senegal
  • New website for EGI.eu catch all Certification Authority developed [8]

Core Services for Site Certification

  • Certification portal maintenance operations [9]

Milestones not accomplished

  • Decomission of all ROC legacy groups has not been completed. This task will go on in 2013.

Plans for 2013

VO Services

Currently the DTEAM VO services are provided through the VOMRS service. Since this service is now unsupported there are ongoing investigations on the missing features of the VOMS service that need to be enabled prior to proceeding to the migration of the service.

Decommission of NGI groups (i.e. NGI_IE) and/or legacy groups is also foreseen in 2013.

EGI Catch All CA

Continue the support and operation of the EGI Catch All CA and the expansion of the RA Network as needed.

Core Services for Site Certification

Continue the support and operation of the Site Certification Core Services. An upgrade of all services is foreseen in the first and second quarter of 2013.