Assessment of progress in 2012
Completed Activities and Milestones
- GGUS Report Generator
The GGUS report generator was re-designed from scratch. Some fine tuning is still to be done.
- xGUS instances
Several new xGUS instances have been introduced: France Grilles, NGI_SI
- High availability of GGUS