EGI-InSPIRE:Plan 2013 SA1.6
Revision as of 10:41, 10 January 2013 by Ggrein (talk | contribs) (→Completed Activities and Milestones)
Assessment of progress in 2012
Completed Activities and Milestones
- GGUS Report Generator
The GGUS report generator was re-designed from scratch. Some fine tuning is still to be done.
- xGUS instances
Several new xGUS instances have been introduced: France Grilles, NGI_SI
- High availability of GGUS
- Implemented HA solution for Web Front-ends - Implemented HA solution for Logic Servers - Implemented on call duty service integration Design disaster recovery plan: processes, policies and procedures related to preparing for recovery or continuation of GGUS after a natural or human-induced disaster.