Staged rollout

Assessment of progress in 2012

Completed Activities and Milestones

  • Number of EAs have increased and committed to staged rollout of EMI 2 products.
  • New EAs committing to new IGE products.
  • SW provisioning workflow has been improved, it has been simplified and made more flexible.
  • Help in the campaign to decommission of glite 3.1 and 3.2 services in favor of EMI 1 and EMI 2 services.
  • Development and implementation at LIP of a web application to record the staged rollout tests [1]. This is used in the quarterly report metrics.

Milestones not accomplished

  • Missing Early Adopter teams for some middleware components [2]

Plans for 2013

  • Providing support to the current UMD-1 and UMD-2 releases.
  • Preparation of UMD-3 to include EMI-3 and IGE final releases.
  • Making a final effort to get EA to the missing components list [3].
  • Evaluate and propose changes and improvements in the SW workflow, in order to adapt to the Post-EMI/IGE. In order to fulfill this task, continue a close collaboration between SA1.3 and SA2 in order to accommodate the necessary changes.
  • Continuing to follow the Virtualization and Cloud Task Force, and access it's implications to the SW provisioning.

Interoperations

Assessment of progress in 2012

Completed Activities and Milestones

  • Finalize integration of UNICORE tests into SAM monitoring framework.
  • Definition of tests used for certification of UNICORE and Globus sites. As part of this activity tests will be included in set of operations tests (PROC06

Milestones not accomplished

  • Integration of Desktop Grids sites into EGI operational tools. 
  • Integration of MAPPER sites running QoSGrid middleware into EGI operational tools. 

Plans for 2013


Unicore

  • Accounting and Information System integration.

Mapper/QCG

  • Accounting, Support and Information System integration.
  • Definition of tests used for certification. As part of this activity tests will be included in set of operations tests (PROC06

Desktop grid

  • Accounting, Support and Information System integration.
  • Definition of tests used for certification. As part of this activity tests will be included in set of operations tests (PROC06)

Globus

  • Accounting and Information System integration.