Alert.png The wiki is deprecated and due to be decommissioned by the end of September 2022.
The content is being migrated to other supports, new updates will be ignored and lost.
If needed you can get in touch with EGI SDIS team using operations @ egi.eu.

Difference between revisions of "EGI-InSPIRE:Plan 2012 SA1.7"

From EGIWiki
Jump to navigation Jump to search
Line 4: Line 4:


== Network Support ==
== Network Support ==


MILESTONE-1: Workflow for handling network-related tickets in GGUS implemented and operational, procedures understood and shared, known.
MILESTONE-1: Workflow for handling network-related tickets in GGUS implemented and operational, procedures understood and shared, known.
Line 10: Line 9:


MILESTONE-2: HINTS system up and running, volunteering sites enrolled, pilot phase on-going
MILESTONE-2: HINTS system up and running, volunteering sites enrolled, pilot phase on-going
Fully Achieved : the main server is up and running, pilot sites are using it. ( Achieved 100 %).


MILESTONE-3: HINTS system in production mode, community of sites extended to the whole community of EGI sites willing to join.   
MILESTONE-3: HINTS system in production mode, community of sites extended to the whole community of EGI sites willing to join.   
Partially Achived: some developments are still on going, to consolidate the system and procude ia64 architecture based HINTS probes. ( Achieved 20 % ).


MILESTONE-4:  Live-CD ready and available to the EGI sites for performing measurements and archiving data
MILESTONE-4:  Installation-CD ready and available to the EGI sites for performing measurements and archiving data
Achieved, although currently no further support for this task ( Achieved 100 %).


MILESTONE-5:  Graphical User interface developed and available, complementing the tool provided functionality
MILESTONE-5:  Graphical User interface developed and available, complementing the tool provided functionality
Not Achieved : due to lack of manpower, this development thread has been suspended ( Not Achieved )


MILESTONE-6:  Periodic reports from the GN3 PerfSONAR community to the EGI Network Support written and distributed.  
MILESTONE-6:  Periodic reports from the GN3 PerfSONAR community to the EGI Network Support written and distributed.  
Achieved - although the reports have been mada by means of slides presented at the EGI Net Sup Workshops - and not single DOC or PDF files.  ( Achieved 100 %).


MILESTONE-7:  Improved  NetJobs GUI available
MILESTONE-7:  Improved  NetJobs GUI available
Not Achieved : The GUI of the NetJobs tool did not improve : an upgrade has been made to some components to elimiate  (Not Achieved)


MILESTONE-8:  NetJobs in production mode, new sites enrolled, improved capacity measurements.
MILESTONE-8:  NetJobs in production mode, new sites enrolled, improved capacity measurements.
Not Achieved : no new sites have been enrolled, interest for the tool overall quite low expressed by sites.  (Not Achieved)


MILESTONE-9:  All approved and used Network Support tools documented
MILESTONE-9:  All approved and used Network Support tools documented
Partially Achieved : some documentation has been made available for HINTS, but it is not enough. Documentation for perfSONAR MDM is available ( Achieved 30 %).


MILESTONE-10:  GUIs integrated in the operations portal or at least linked by it
MILESTONE-10:  GUIs integrated in the operations portal or at least linked by it
Not Achieved : This work did not even start mostly due to lack of manpower/resources.  ( Not Achieved)


MILESTONE-11:  Questionnaire produced and circulated to the NRENs, answers gathered, outcome provided to the EGI/EGI-Inspire Operations community.  
MILESTONE-11:  Questionnaire produced and circulated to the NRENs, answers gathered, outcome provided to the EGI/EGI-Inspire Operations community
 
Not Achieved : a general questionare devoted to the NRENs-NGIs interaction was never produced; the emphasis moved to IPv6: a general Survey on it has been organized. (Not Achieved)


=''' Plans for 2012 '''=
=''' Plans for 2012 '''=

Revision as of 13:43, 7 December 2011

Assessment of progress, 2011

Network Support

MILESTONE-1: Workflow for handling network-related tickets in GGUS implemented and operational, procedures understood and shared, known. Fully Achieved. There is a workflow in place for the GGUS Network Support Unit. ( Achieved 100 %).

MILESTONE-2: HINTS system up and running, volunteering sites enrolled, pilot phase on-going Fully Achieved : the main server is up and running, pilot sites are using it. ( Achieved 100 %).

MILESTONE-3: HINTS system in production mode, community of sites extended to the whole community of EGI sites willing to join. Partially Achived: some developments are still on going, to consolidate the system and procude ia64 architecture based HINTS probes. ( Achieved 20 % ).

MILESTONE-4: Installation-CD ready and available to the EGI sites for performing measurements and archiving data Achieved, although currently no further support for this task ( Achieved 100 %).

MILESTONE-5: Graphical User interface developed and available, complementing the tool provided functionality Not Achieved : due to lack of manpower, this development thread has been suspended ( Not Achieved )

MILESTONE-6: Periodic reports from the GN3 PerfSONAR community to the EGI Network Support written and distributed. Achieved - although the reports have been mada by means of slides presented at the EGI Net Sup Workshops - and not single DOC or PDF files. ( Achieved 100 %).

MILESTONE-7: Improved NetJobs GUI available Not Achieved : The GUI of the NetJobs tool did not improve : an upgrade has been made to some components to elimiate (Not Achieved)

MILESTONE-8: NetJobs in production mode, new sites enrolled, improved capacity measurements. Not Achieved : no new sites have been enrolled, interest for the tool overall quite low expressed by sites. (Not Achieved)

MILESTONE-9: All approved and used Network Support tools documented Partially Achieved : some documentation has been made available for HINTS, but it is not enough. Documentation for perfSONAR MDM is available ( Achieved 30 %).

MILESTONE-10: GUIs integrated in the operations portal or at least linked by it Not Achieved : This work did not even start mostly due to lack of manpower/resources. ( Not Achieved)

MILESTONE-11: Questionnaire produced and circulated to the NRENs, answers gathered, outcome provided to the EGI/EGI-Inspire Operations community Not Achieved : a general questionare devoted to the NRENs-NGIs interaction was never produced; the emphasis moved to IPv6: a general Survey on it has been organized. (Not Achieved)

Plans for 2012

MILESTONE 2012-1 MILESTONE 2012-2 MILESTONE 2012-3 MILESTONE 2012-4


Network Support