Assessment of progress, 2011

Middleware specific workflows prototyping

This task is done. Specific work flows for DMSU, EMI and the software release process are implemented and operational.

Report generator remodeling

The remodeling of the GGUS Report Generator is still on the roadmap for 2012 as further requirements came up.

Review support units

This task is done. Obsolete support units have been moved to the "Former support units" list in GGUS search engine.

High availability of GGUS

This task is ongoing. Further actions are required in 2012.

NGI integration

Currently 33 NGIs are integrated in GGUS, 10 with automatic interface to local ticketing systems. 4 of them are xGUS instances. This task is ongoing.

Application/Community support

This task is still on the roadmap for 2012.

Plans for 2012

GGUS Report Generator

  • Presentation of first prototype on EGI Community Forum
  • First version available for the EGI Review mid of the year
  • Final version available by end of the year

Integration of further xGUS instances

  • Finish integration of ROC_China
  • New xGUS instance for NGI_Slovenia
  • Maybe some more NGIs

Figure out which NGIs still are missing in GGUS

  • Currently 33 NGIs are integrated in GGUS. Which NGIs are still missing?
  • Russia is still appearing as ROC_Russia

Implementation of specific work flows for CSIRT/Security

  • The CSIRT team is currently evaluating whether they want to use GGUS.
  • If CSIRT will use GGUS the permissions and access rights schema needs to be adapted to their needs.

High availability of GGUS

Q1-Q2.2012

Main purpose: Implement auto-switching between Web Front-end Hosts

  • Auto-switching between Web Front-ends
  • Auto-switching between Logic Servers
  • On call duty service integration
  • Design disaster recovery plan

Q3-Q4.2012

Main purpose: DBMS and other HA questions

  • Intrusion Prevention system configuration for GGUS
  • Improvements into Service Monitoring
  • DBMS on Virtual Environment migration Concept

Application/Community support

  • Evaluating the implementation of web widgets.