Difference between revisions of "EGI-InSPIRE:Metrics Portal SA1 how to"
Jump to navigation
Jump to search
Line 10: | Line 10: | ||
#In the new page: in the box "''Tasks by NGI''" choose your NGI and select the "''PQ6''" in the drop down menus. Click on "''Go to NGI tasks''" | #In the new page: in the box "''Tasks by NGI''" choose your NGI and select the "''PQ6''" in the drop down menus. Click on "''Go to NGI tasks''" | ||
#In the new page: select the "''SA1''" activity and then "''PQ6''", then click again on "''go to NGI tasks''" | #In the new page: select the "''SA1''" activity and then "''PQ6''", then click again on "''go to NGI tasks''" | ||
#In the new page click to "Edit" to change the values, or to add values in the empty cells | #In the new page click to "Edit" to change the values, or to add values in the empty cells | ||
#: | #: Some metrics have suggested values, you can modify the suggested values if they are wrong. Please always '''verify''' the suggested values. | ||
#You can | #You '''can''' modify the table once you have submitted the page once. |
Revision as of 16:33, 7 October 2011
How-To fill in the NGI metrics for the quarterly report
This wiki page provide a manual to use the Metrics portal to fill the quarterly metrics for SA1.
It is addressed mainly to the Operations Managers and their staff.
Fill the SA1 NGI metrics
- Go to the metrics portal (metrics.egi.eu)
- On the menu on the left click on "Activity metrics"
- In the new page: in the box "Tasks by NGI" choose your NGI and select the "PQ6" in the drop down menus. Click on "Go to NGI tasks"
- In the new page: select the "SA1" activity and then "PQ6", then click again on "go to NGI tasks"
- In the new page click to "Edit" to change the values, or to add values in the empty cells
- Some metrics have suggested values, you can modify the suggested values if they are wrong. Please always verify the suggested values.
- You can modify the table once you have submitted the page once.