=== 2.3 TJRA2.3 AppDB  ===
=== 2.3 TJRA2.3 AppDB  ===


*The notification mechanism for the Virtual appliances is ready and has been pushed into production. Documentation [https://wiki.appdb.egi.eu/main:guides:notify_virtual_organization_representatives here]
*The notification mechanism for the Virtual appliances is ready and has been pushed into production. Documentation [https://wiki.appdb.egi.eu/main:guides:notify_virtual_organization_representatives here]  
*A nagios probe has been developed for monitorig the VA distribution workflow supported by AppDB.
*A nagios probe has been developed for monitoring the VA distribution workflow supported by the AppDB.  
*Support for eduGAIN is an on going state. Expected to to have a more solid feedback by the end of the week.
*Support for eduGAIN is an on going state. Expected to to have a more solid feedback by the end of the week.  
*Planning and effort allocation for the PY5 open items is will be ready within the week.
*Planning and effort allocation for the PY5 open items, it will be ready within the week.


=== 2.4 TJRA2.4 e-GRANT  ===
=== 2.4 TJRA2.4 e-GRANT  ===

Revision as of 10:09, 17 June 2014

<< JRA1 weekly reports main page



1. Critical Issues

2. Major work done during the past week by task

2.1 TJRA2.1 SAM

  • Implementation of an API call to return weight factor (i.e. Hepspec) per site (TBD: mid-this-week)
  • Discussion on data store schema for Status results storing (expecting indicative input to decide schema to be implemented)
  • Ongoing migration to the latest version of Lavoisier

2.2 TJRA2.2 Accounting

2.2.1 Accounting Repository

2.2.2 Accounting Portal

2.3 TJRA2.3 AppDB

  • The notification mechanism for the Virtual appliances is ready and has been pushed into production. Documentation here
  • A nagios probe has been developed for monitoring the VA distribution workflow supported by the AppDB.
  • Support for eduGAIN is an on going state. Expected to to have a more solid feedback by the end of the week.
  • Planning and effort allocation for the PY5 open items, it will be ready within the week.

2.4 TJRA2.4 e-GRANT

3. Next Meetings