1. Progress on Milestones Deliverables
MS710 - Operational Tools Roadmap
An updated version of the document satisfying reviewers’ comments has been uploaded in the document server: https://documents.egi.eu/secure/ShowDocument?docid=1501
D7.3 - Annual Report on Operational Tool maintenance and development activity
TOC available on the document server: https://documents.egi.eu/secure/ShowDocument?docid=1562.
The first draft will be available by this week.
2. Critical Issues
1) TJRA1.4: the task is still under-reporting after QR11
2) A developer left the Ops Portal team the 1st of December. This could create the following problems: - A final under-reporting on the TJRA1.5 (this task ends at the end of PY3); - The complete release in production of the new portal could be delayed. The release will be probably done step by step - initiated with the new dashboard. The progress on this part will be also dependent from the integration of a new developer.