Difference between revisions of "EGI-InSPIRE:Ibergrid-QR6"

From EGIWiki
Jump to navigation Jump to search
(Created page with '__NOTOC__ {| border="1" cellspacing="0" cellpadding="2" |- !scope="col"| Quarterly Report Number !scope="col"| NGI Name !scope="col"| Partner Name !scope="col"| Author |- | | | …')
 
Line 7: Line 7:
!scope="col"| Author  
!scope="col"| Author  
|-
|-
|
|QR5
|
|Ibergrid
|
|LIP & CSIC
|
|Álvaro Simón García, Esteban Freire García (CSIC)
|-
|-
|}
|}
Line 36: Line 36:
!scope="col"|Date||Location||Title||Participants||Outcome (Short report & Indico URL)  
!scope="col"|Date||Location||Title||Participants||Outcome (Short report & Indico URL)  
|-
|-
|
|
|
|
|
|
|-
|-
|}
|}


===1.2. OTHER CONFERENCES/WORKSHOPS ATTENDED===
===1.2. OTHER CONFERENCES/WORKSHOPS ATTENDED===
Line 50: Line 47:
|-
|-
!scope="col"|Date||Location||Title||Participants||Outcome (Short report & Indico URL)  
!scope="col"|Date||Location||Title||Participants||Outcome (Short report & Indico URL)  
|-
|19-23 September||Lyon, France||EGI Technical Forum 2011|| ~ 15||
* Participation from several IBERGRID institutes with contributions in different sessions. Good meeting point to see the status of the middle-ware and to see new developed applications. It was also good to hear about how other NGIs are progressing, the main requirements from their ROD teams, perpectives and difficulties during the "Grid Oversight" session. http://tf2011.egi.eu/
* CESGA: Contribution with the session "EGI Operations Management Board" presenting the EGI-InSPIRE Metrics Portal Demo, https://www.egi.eu/indico/conferenceDisplay.py?confId=434
* IFISC-GRID: Contribution with the session "Science Gateways & Portals" presenting a Web interface for generic grid jobs, Web4Grid, https://www.egi.eu/indico/contributionDisplay.py?contribId=55&confId=452
* PIC: Contribution with the session "Resource Centre Forum" presenting a report about PIC, https://www.egi.eu/indico/contributionDisplay.py?sessionId=52&contribId=382&confId=452
|-
|12-16 September||Lisbon, Portugal||Timbus F2F meeting||5||
* LIP-Lisbon: Presentation of LIP-Lisbon activity in the EGI  framework in the TIMBUS F2F activity. TIMBUS project home page: http://timbusproject.net/
|-
|19-23 September||Santander||XXXIII Bienal de la Real Sociedad Española de Física|| 2||“Aplicaciones de Física utilizando la Infraestructura de e-Ciencia del IFIC” http://indico.ific.uv.es/indico/materialDisplay.py?contribId=0&materialId=paper&confId=418
|-
|26-27 Sep||Amsterdam||LHCOPN-LHCONE joint meeting|| 1||
* IFAE: Reports on the status of LHCOPN and  LHCONE infrastructures. Emphasis on the monitoring tools for LHCOPN such as Perfsonar-PS and also in the deployment of the new infrastructure for Tier2s LHCONE.
http://indico.cern.ch/conferenceOtherViews.py?view=standard&confId=149042
|-
|-
|||||||||
|12 October||Cern, Switzerland||Staged Rollout Process||1||
* LIP-Lisbon: Presentation of the EGI Stage Rollout process at the October GDB aiming to involved WLCG more deeply in the process: http://indico.cern.ch/conferenceDisplay.py?confId=106649
|-
|-
|13-14 October||Barcelona||HPC SysAdmin Meeting'11|| 1||
* IFAE: Presentation on the use of Puppet at PIC as a tool for  services configuration automation and management.
http://hpc.xrqtc.org/index.php/conference-training/anual-meeting
|}
|}


Line 67: Line 84:
|-
|-
!scope="col"|Publication title||Journal / Proceedings title||align="left" |Journal references<br> ''Volume number<br> Issue<br><br>Pages from - to''||align="left" |Authors ''<br>1.<br>2.<br>3.<br>Et al?''
!scope="col"|Publication title||Journal / Proceedings title||align="left" |Journal references<br> ''Volume number<br> Issue<br><br>Pages from - to''||align="left" |Authors ''<br>1.<br>2.<br>3.<br>Et al?''
|-
|OCDgLite. An easy way to deploy a customized gLite grid environment
|EGI Technical Forum 2011 (19-23 September). Poster.
|
|Jesús Santisteban, Miguel Angel Díaz, Manuel Enrique Cotallo
|-
|Despliegue auto-adaptativo e inteligente de aplicaciones grid basado en la Búsqueda de Entorno Variable
|VIII Congreso español sobre metaheuristicas, algoritmos evolutivos y bioinspirados - Conference
|
|María Botón-Fernández, Miguel A. Vega-Rodríguez, Francisco Prieto Castrillo
|-
|Modelo de despliegue auto-adaptativo en entornos grid desde las perspectiva de los sistemas complejos
|VIII Congreso español sobre metaheuristicas, algoritmos evolutivos y bioinspirados - Conference
|
|María Botón-Fernández, Francisco Prieto Castrillo, Miguel A. Vega-Rodríguez
|-
|Self-Adaptive and Intelligent Deployment of Grid Applications Based on Several Perspectives from the Artificial Intelligence Field
|Applied Soft Computing (Elsevier) - Journal
|
|María Botón-Fernández, Miguel A. Vega-Rodríguez, Francisco Prieto Castrillo
|-
|-
|}
|}
Line 74: Line 111:


===2.1. Progress Summary===
===2.1. Progress Summary===
# It was produced a report on error messages of LCMAPS which needs to be fixed. The report has been sent to SA1 coordinators, and introduced in the following RT ticket: https://rt.egi.eu/rt/Ticket/Display.html?id=1983
# It was submitted an internal survey to the Ibergrid sites about evaluation of the quality of services and tools at disposal of the site administrators. The NGI IBERGRID Internal survey were analyzed and discussed with the Ibergrid sites in the weekly Ibergrid Operations meeting.
# It was launch a new operations Wiki: http://ibergrid.lip.pt. This new wiki is more flexible than the previous one.
# It was analyzed the 1st EGI review report.
# In order to Ibergrid sites configuring their services to have VOMS redundancy for the Ibegrid VOs, we have created an action in the weekly Ibergrid Operations meeting. The deadline for this action was on the 21st October, and after that date we have started to check what sites are supporting it correctly. We will open a ggus ticket to the sites that are failing.
# For the implementation of the TopBDII HA proposal in NGI_IBERGRID, we have decided to have two primary DNSes to support automatic updates: one in Portugal (operated by LIP in NCG-INGRID-PT site) and one in Spain (hosted by CESGA). It was opened the ggust ticket https://ggus.eu/ws/ticket_info.php?ticket=74883 to carry out this action.
===2.2. Main Achievements===
===2.2. Main Achievements===
 
# Two new sites were joined to the infrastructure:  ARAGRID-CIENCIAS and RC-GISELA-CETA.
# It has been installed a dedicated WMS to support the Ibergrid VOs.


===2.3. Issues and mitigation===
===2.3. Issues and mitigation===
Line 84: Line 129:
!scope="col"| Mitigation Description
!scope="col"| Mitigation Description
|-
|-
|UOGRID site is still suspended.
|This site entering in suspension status after 1 month of downtime during the last QR5.
|-
|There was several issues related with the Ibergrid Regional Nagios:
* There was an external issue related with the connection between RedIris and the Galicia centers), which affected to the Ibergrid Regional Nagios. The incident had place on 08/09/2011, and it took from 01:00 AM CEST to 13:00 PM CEST. GGUS ticket #74146 was open in order to do not take into account that period in the A/R metrics.
* There was an external issue related with the top-bdii configured in the R-Nagios, which affected to the Ibergrid Regional Nagios. The incident had place on 19/09/2011, and it took from 22:00 PM CEST to 12:00 AM CEST (20/09/2011). GGUS ticket #74652 was open in order to do not take into account that period in the A/R metrics.
* It was necessary to reinstall the Ibergrid Regional Nagios, due to an issue related with the Mysql || GGUS ticket #75701 was open in order to do not take into account that period in the A/R metrics.
|
|}
|}
<!--
<!--
  Please, fill the table below. You can add a line copyng the two lines
  Please, fill the table below. You can add a line copyng the two lines

Revision as of 12:14, 31 October 2011

Quarterly Report Number NGI Name Partner Name Author
QR5 Ibergrid LIP & CSIC Álvaro Simón García, Esteban Freire García (CSIC)


1. MEETINGS AND DISSEMINATION

1.1. CONFERENCES/WORKSHOPS ORGANISED

Date Location Title Participants Outcome (Short report & Indico URL)


1.2. OTHER CONFERENCES/WORKSHOPS ATTENDED

Date Location Title Participants Outcome (Short report & Indico URL)
19-23 September Lyon, France EGI Technical Forum 2011 ~ 15
12-16 September Lisbon, Portugal Timbus F2F meeting 5
  • LIP-Lisbon: Presentation of LIP-Lisbon activity in the EGI framework in the TIMBUS F2F activity. TIMBUS project home page: http://timbusproject.net/
19-23 September Santander XXXIII Bienal de la Real Sociedad Española de Física 2 “Aplicaciones de Física utilizando la Infraestructura de e-Ciencia del IFIC” http://indico.ific.uv.es/indico/materialDisplay.py?contribId=0&materialId=paper&confId=418
26-27 Sep Amsterdam LHCOPN-LHCONE joint meeting 1
  • IFAE: Reports on the status of LHCOPN and LHCONE infrastructures. Emphasis on the monitoring tools for LHCOPN such as Perfsonar-PS and also in the deployment of the new infrastructure for Tier2s LHCONE.

http://indico.cern.ch/conferenceOtherViews.py?view=standard&confId=149042

12 October Cern, Switzerland Staged Rollout Process 1
13-14 October Barcelona HPC SysAdmin Meeting'11 1
  • IFAE: Presentation on the use of Puppet at PIC as a tool for services configuration automation and management.

http://hpc.xrqtc.org/index.php/conference-training/anual-meeting


1.3. PUBLICATIONS

Publication title Journal / Proceedings title Journal references
Volume number
Issue

Pages from - to
Authors
1.
2.
3.
Et al?
OCDgLite. An easy way to deploy a customized gLite grid environment EGI Technical Forum 2011 (19-23 September). Poster. Jesús Santisteban, Miguel Angel Díaz, Manuel Enrique Cotallo
Despliegue auto-adaptativo e inteligente de aplicaciones grid basado en la Búsqueda de Entorno Variable VIII Congreso español sobre metaheuristicas, algoritmos evolutivos y bioinspirados - Conference María Botón-Fernández, Miguel A. Vega-Rodríguez, Francisco Prieto Castrillo
Modelo de despliegue auto-adaptativo en entornos grid desde las perspectiva de los sistemas complejos VIII Congreso español sobre metaheuristicas, algoritmos evolutivos y bioinspirados - Conference María Botón-Fernández, Francisco Prieto Castrillo, Miguel A. Vega-Rodríguez
Self-Adaptive and Intelligent Deployment of Grid Applications Based on Several Perspectives from the Artificial Intelligence Field Applied Soft Computing (Elsevier) - Journal María Botón-Fernández, Miguel A. Vega-Rodríguez, Francisco Prieto Castrillo

2. ACTIVITY REPORT

2.1. Progress Summary

  1. It was produced a report on error messages of LCMAPS which needs to be fixed. The report has been sent to SA1 coordinators, and introduced in the following RT ticket: https://rt.egi.eu/rt/Ticket/Display.html?id=1983
  2. It was submitted an internal survey to the Ibergrid sites about evaluation of the quality of services and tools at disposal of the site administrators. The NGI IBERGRID Internal survey were analyzed and discussed with the Ibergrid sites in the weekly Ibergrid Operations meeting.
  3. It was launch a new operations Wiki: http://ibergrid.lip.pt. This new wiki is more flexible than the previous one.
  4. It was analyzed the 1st EGI review report.
  5. In order to Ibergrid sites configuring their services to have VOMS redundancy for the Ibegrid VOs, we have created an action in the weekly Ibergrid Operations meeting. The deadline for this action was on the 21st October, and after that date we have started to check what sites are supporting it correctly. We will open a ggus ticket to the sites that are failing.
  6. For the implementation of the TopBDII HA proposal in NGI_IBERGRID, we have decided to have two primary DNSes to support automatic updates: one in Portugal (operated by LIP in NCG-INGRID-PT site) and one in Spain (hosted by CESGA). It was opened the ggust ticket https://ggus.eu/ws/ticket_info.php?ticket=74883 to carry out this action.

2.2. Main Achievements

  1. Two new sites were joined to the infrastructure: ARAGRID-CIENCIAS and RC-GISELA-CETA.
  2. It has been installed a dedicated WMS to support the Ibergrid VOs.

2.3. Issues and mitigation

Issue Description Mitigation Description
UOGRID site is still suspended. This site entering in suspension status after 1 month of downtime during the last QR5.
There was several issues related with the Ibergrid Regional Nagios:
  • There was an external issue related with the connection between RedIris and the Galicia centers), which affected to the Ibergrid Regional Nagios. The incident had place on 08/09/2011, and it took from 01:00 AM CEST to 13:00 PM CEST. GGUS ticket #74146 was open in order to do not take into account that period in the A/R metrics.
  • There was an external issue related with the top-bdii configured in the R-Nagios, which affected to the Ibergrid Regional Nagios. The incident had place on 19/09/2011, and it took from 22:00 PM CEST to 12:00 AM CEST (20/09/2011). GGUS ticket #74652 was open in order to do not take into account that period in the A/R metrics.
  • It was necessary to reinstall the Ibergrid Regional Nagios, due to an issue related with the Mysql || GGUS ticket #75701 was open in order to do not take into account that period in the A/R metrics.