Difference between revisions of "EGI-InSPIRE:Amb 2013-10-22"

From EGIWiki
Jump to: navigation, search
(NA1)
(NA1)
Line 10: Line 10:
  
 
* Progress on Milestones & Deliverables
 
* Progress on Milestones & Deliverables
Preparations for the QR14.
+
Preparations for the QR14 - template circulated, metrics being collected
  
 
* Major work done during the past week by task
 
* Major work done during the past week by task
 
   
 
   
 
TNA1.1 Activity management
 
TNA1.1 Activity management
- Changes to activity plan to reflect management changes
+
* Changes to activity plan to reflect management changes, central budget updates
- Change in NA2 and SA1 work package leaders proposed
+
* Change in NA2 and SA1 work package leaders proposed
 +
* PO notified of change to Project Director, LEAR being updated
  
 
TNA1.2 Project and consortium management
 
TNA1.2 Project and consortium management
- Cost statements submitted and accepted for PY3 - Form Cs being sent to EC
+
* Payment schedule for PQ11 and PY3 closing costs prepared
- Budget for 2014 prepared to be voted on at the Council meeting on 24 October
+
* Budget for 2014 revised to be voted on at the Council meeting on 24 October
- Effort allocations adjusted to end of project in consultation with managers - further changes carried out to reflect management changes
+
* Effort allocations to be verified
- Recruitment underway for project roles - 5 roles advertised, interviews scheduled for 2
+
* Proposals for appointments made to the EB for Graphic Designer and Outreach Intern
 +
* Applications open for Business Development Expert, Technical Outreach Expert and Senior Ops Officer
 
   
 
   
 
TNA1.4 Quality assurance
 
TNA1.4 Quality assurance
- QR14 materials and metrics being gathered
+
* QR14 materials and metrics being gathered for 8 November
- Project level metrics to be updated on the website
+
* Project level metrics to be related to the human networks impact
- Project level metrics to be related to the human networks impact
 
  
 
== NA2 ==  
 
== NA2 ==  

Revision as of 08:44, 23 October 2013

Back to the AMB wiki home page

Activity Reports

NA1

  • Progress on Milestones & Deliverables

Preparations for the QR14 - template circulated, metrics being collected

  • Major work done during the past week by task

TNA1.1 Activity management

  • Changes to activity plan to reflect management changes, central budget updates
  • Change in NA2 and SA1 work package leaders proposed
  • PO notified of change to Project Director, LEAR being updated

TNA1.2 Project and consortium management

  • Payment schedule for PQ11 and PY3 closing costs prepared
  • Budget for 2014 revised to be voted on at the Council meeting on 24 October
  • Effort allocations to be verified
  • Proposals for appointments made to the EB for Graphic Designer and Outreach Intern
  • Applications open for Business Development Expert, Technical Outreach Expert and Senior Ops Officer

TNA1.4 Quality assurance

  • QR14 materials and metrics being gathered for 8 November
  • Project level metrics to be related to the human networks impact

NA2

NA2.2

  1. Media mentions
  2. Human Networks
    • Met with CG, GS, RMcL and SC to discuss handover
  3. Deliverables/Milestones
    • MS243, reviewed, edited. With the PMB
  4. Staffing
    • Interviewed 2 candidates for Outreach Officer role, one F2F, other via skype
    • Interviewed 3 candidates for Graphic Designer role, all F2F
  5. Other

NA2.5

  • Review new VT proposal and kick-off VT: Promoting Desktop Grid solutions - https://wiki.egi.eu/wiki/VT_Promoting_Desktop_Grids
  • Teleconference with NILs & Champions about EGI-InSPIRE PY4-5, H2020, CF2012; Discuss survey to be setup this week for NILs and Champs with Tiziana
  • Propose collaboration opportunitites to PRACE (EGI-2013 hydro-meteorology session; science gateways) - meeting to be arranged with Jules Wolfrat
  • Meeting about CF2014 with Richard and Tiziana - event scope, structure, content
  • Discuss human network management with press team and Richard (handover from Richard to Sara)
  • Teleconference with EISCAT_3D study case - next step is to define a 2TB data pilot + planning to H2020 proposal
  • ER-flow review (1 day for Gergely) - the project received a GOOD mark
  • Send out request for QR14 input to TNA2.5 teams
  • Record EGI Introduction lecture for Grid Computing MOOC (mini-project in SA4)
  • Attend review rehearsal of the BioVeL project (webex session)
  • Search for VRE projects (potential EGI customers) on the EC Cordis website - results relevant for ER-flow and EGI-InSPIRE NA2.5

SA1

Report: Inspire_sa1_2013-10-22

SA2

SA4

JRA1

Report: Inspire_jra1_2013-10-22

Participants

Discussion