This page is providing yearly activity plan for WP5 in PY1
Project month
|
Project Tasks
|
Work to be done
|
Goal
(measurable)
|
Owner
(reponsible person)
|
Comments
|
1
|
Task 5.1
|
- Core activities bidding process, including the extension of the service portfolio
- UMD, definition of the processes to improve the service and include new technologies such as the fedcloud software
- Implement an SLA framework with the EGI's stakeholders
- Procedure for the VMI endorsement definition and implementation
|
- Core activities are bid and the new consortia are ready to start delivering the services in May 2016
- UMD releases the JRA2.2 outputs and makes available the releases for the production infrastructure.
- The VMI endorsement procedure is approved by OMB, and it is implemented in the ops tools where necessary
|
Peter Solagna - EGI.eu
|
|
1
|
Task 5.2
|
- Document the security requirements for the EGI Federated Cloud Service and perform a security risk analysis.
- Develop new and revise old security policies to meet the needs of the EGI Federated Cloud Service and the Long Tail of Science Service.
- Technical changes to the trust fabric management will be introduced for new usage scenarios and to support evolving access control mechanisms.
- Develop new operational security procedures for the EGI Federated Cloud Service for incident response and vulnerability handling.
|
- The security requirements and security risk analysis for FedCloud will be produced and agreed/approved by the EGI FedCloud team, the OMB and the security team.
- Policy documents will be produced, consulted on and passed all the way through to formal adoption. This will include at least a revised AUP, a revised VM Endorsement and the new LToS service policy.
- The new trust fabric management will be evaluated on new usage scenarios the evolving access control mechanisms.
- New procedures for FedCloud will be developed, approved and adopted for Incident Response and Vulnerability Handling.
|
David Kelsey - STFC
|
|
2
|
Task 5.3
|
- Enable ESA exploitation platform tasks to run on EGI Fedcloud
- Enable iMarine platform to use EGI resources
- Enable Long tail of science platform
|
- EGI accounting shows resource utilization by the ESA VOs
- EGI accounting shows resource utilization by the iMarine VOs
- EGI accounting shows resource utilization by long tail of science VO (beside testing)
|
Peter Solagna - EGI.eu
|
|