Milestone
Note well. The detailed description of the computational and storage activity requirements to support DRIHM applications, both the highly parallel and less demanding ones, will be added to the wiki EGI-DRIHM collaboration wiki pages (June 15 - June 30 2013).
Timeline


Detailed description of the computational and storage requirements of the DRIHM applications, both the highly parallel and less demnading ones. (will be added to the wiki EGI-DRIHM collaboration wiki pages).
= DRIHM VO Support =
June 15 - June 30 2013
*Add the support for the DRIHM VO in the resources listed in the EGI testbed, including some Storage Elements to store the input and output data of the models and to test the file transfers to local resources (i.e. storage used by a portal).
 
Add the support for the DRIHM VO in the resources listed in the EGI testbed, including some Storage Elements to store the input and output data of the models and to test the file transfers to local resources (i.e. storage used by a portal).
June 15 - July 31 2013
June 15 - July 31 2013


Enable the DRIHM VO in a couple of  EGI scheduler service (i.e. gLite-WMS/LB), in order to test the facilities offered by these services (jobs bookeeping, rescheduling, resources matchmaking, Input/Output SandBox handling, etc.).
*Enable the DRIHM VO in a couple of  EGI scheduler service (i.e. gLite-WMS/LB), in order to test the facilities offered by these services (jobs bookeeping, rescheduling, resources matchmaking, Input/Output SandBox handling, etc.).
June 15 - July 31 2013
June 15 - July 31 2013


= Services for DRIHM =
Other services needed are: a VOMS server (already available for DRIHM), a file catalogue (i.e. gLite-LFC) and a MyProxy server.
Other services needed are: a VOMS server (already available for DRIHM), a file catalogue (i.e. gLite-LFC) and a MyProxy server.
June 15 - June 30 2013
June 15 - June 30 2013


= Porting =
Porting of the demanding model (i.e. WRF) to the Grid Environment in collaboration with the EGI/NGIs user support teams for some selected "Critical Cases" and preliminary tests of the Grid submission/data management. (using NGI general purpose VO if DRIHM is not deployed yet)
Porting of the demanding model (i.e. WRF) to the Grid Environment in collaboration with the EGI/NGIs user support teams for some selected "Critical Cases" and preliminary tests of the Grid submission/data management. (using NGI general purpose VO if DRIHM is not deployed yet)
15 June - 01 July 2013
15 June - 01 July 2013


= Define sites to support the demanding jobs =
Identification of the testbed members willing to run demanding jobs, as the meteo models, with the indication of the maximum allowable parallelism degree
Identification of the testbed members willing to run demanding jobs, as the meteo models, with the indication of the maximum allowable parallelism degree
01 July - 15 August 2013
01 July - 15 August 2013


Test the job submission (direct to CE and via WMS/LB) and data management from a command line user interface for the most demanding models on the DRIHM testbed - Performance evaluation of the infrastructure resources and services.
= Job submission testing =
*Test the job submission (direct to CE and via WMS/LB) and data management from a command line user interface for the most demanding models on the DRIHM testbed - Performance evaluation of the infrastructure resources and services.
01 July - 31 Aug 2013
01 July - 31 Aug 2013


Porting and preliminary tests for the submission of jobs and data management from a command line user interface of the less demanding applications (hydrologic and hydraulic models) - Performance evaluation of the infrastructure and  investigation of the capabilities offered by the virtualization systems available within EGI that can be suitable to run these applications.
*Porting and preliminary tests for the submission of jobs and data management from a command line user interface of the less demanding applications (hydrologic and hydraulic models) - Performance evaluation of the infrastructure and  investigation of the capabilities offered by the virtualization systems available within EGI that can be suitable to run these applications.
01 July - 31 Aug 2013
01 July - 31 Aug 2013


Preliminary test for the submission of jobs from the DRIHM sci-bus-based portal to the EGI testbed resources
*Preliminary test for the submission of jobs from the DRIHM sci-bus-based portal to the EGI testbed resources
01-30 September 2013
01-30 September 2013


Incremental setup and tests of the complete suite of DRIHM models on the testbed resources
*Incremental setup and tests of the complete suite of DRIHM models on the testbed resources
1 October 2013 - June 2014 ?
1 October 2013 - June 2014 ?


Production phase
= Production phase =
November 2013 ?  - end of the DRIHM project
November 2013 ?  - end of the DRIHM project
*****

Revision as of 16:45, 7 June 2013

Welcome to the page of the EGI-DRIHM collaboration

EGI DRIHAM collaboration menu: Home Members Infrastructure Roadmap


Note well. The detailed description of the computational and storage activity requirements to support DRIHM applications, both the highly parallel and less demanding ones, will be added to the wiki EGI-DRIHM collaboration wiki pages (June 15 - June 30 2013).

DRIHM VO Support

  • Add the support for the DRIHM VO in the resources listed in the EGI testbed, including some Storage Elements to store the input and output data of the models and to test the file transfers to local resources (i.e. storage used by a portal).

June 15 - July 31 2013

  • Enable the DRIHM VO in a couple of EGI scheduler service (i.e. gLite-WMS/LB), in order to test the facilities offered by these services (jobs bookeeping, rescheduling, resources matchmaking, Input/Output SandBox handling, etc.).

June 15 - July 31 2013

Services for DRIHM

Other services needed are: a VOMS server (already available for DRIHM), a file catalogue (i.e. gLite-LFC) and a MyProxy server. June 15 - June 30 2013

Porting

Porting of the demanding model (i.e. WRF) to the Grid Environment in collaboration with the EGI/NGIs user support teams for some selected "Critical Cases" and preliminary tests of the Grid submission/data management. (using NGI general purpose VO if DRIHM is not deployed yet) 15 June - 01 July 2013

Define sites to support the demanding jobs

Identification of the testbed members willing to run demanding jobs, as the meteo models, with the indication of the maximum allowable parallelism degree 01 July - 15 August 2013

Job submission testing

  • Test the job submission (direct to CE and via WMS/LB) and data management from a command line user interface for the most demanding models on the DRIHM testbed - Performance evaluation of the infrastructure resources and services.

01 July - 31 Aug 2013

  • Porting and preliminary tests for the submission of jobs and data management from a command line user interface of the less demanding applications (hydrologic and hydraulic models) - Performance evaluation of the infrastructure and investigation of the capabilities offered by the virtualization systems available within EGI that can be suitable to run these applications.

01 July - 31 Aug 2013

  • Preliminary test for the submission of jobs from the DRIHM sci-bus-based portal to the EGI testbed resources

01-30 September 2013

  • Incremental setup and tests of the complete suite of DRIHM models on the testbed resources

1 October 2013 - June 2014 ?

Production phase

November 2013 ? - end of the DRIHM project