DCH-RP:Sprint Planning 20130909
Jump to navigation
Jump to search
Participants
- Michel Drescher (EGI)
- Claudio Prandoni (Promoter)
- Rosette Vandenbroucke (BELSPO)
- Borje Justrell (RA)
- Eva Toller (RA)
- Giovanni Ciccaglioni (ICCU)
- Patrizia Martini (ICCU)
Topics
Agenda
- Sprint 11 review
- Sprint 11 retrospective
- Next steps
Discussion
- Review planned tasks for sprint 11 in http://go.egi.eu/DCH-RP-WP5-Backlog
- Move un-finished tasks to sprint 12
- Check priorities and effort estimation
- Planning of Sprint 12 and D5.3
Main decisions
- The result of the decisions on Sprint 11 review and Sprint 12 planning can be found in the backlog file: http://go.egi.eu/DCHRP-WP5-Backlog
- e-CSG: some of the tests failed due to some issues reported on the use of the e-CSG in the PoCs, they will be reported in the evaluation document as feedback to WP3
- SCRUM methodology: some concerns arose about the adoption of the SCRUM methodology in the PoC, Michel will take them into account
- D5.3: it will be not a long document, referring to the report to WP3 and including as an Appendix Rosette's document on the technical interpretation of the scenarios; Michel will send a first draft structure ASAP, the first version for internal review will be ready by 15/9, the final version by 30/9
- Michel will circulate the minutes of the Sprint meetings once they are available
- Next appointments will be the EGI Technical Forum in Madrid and the DCH-RP plenary meeting in Malta
- Next meeting will be called by Michel by email + Doodle as usual and will be held using Webex