Alert.png The wiki is deprecated and due to be decommissioned by the end of September 2022.
The content is being migrated to other supports, new updates will be ignored and lost.
If needed you can get in touch with EGI SDIS team using operations @ egi.eu.

Difference between revisions of "DCH-RP:Sprint Planning 20130318"

From EGIWiki
Jump to navigation Jump to search
(Created page with "== Participants == * Michel Drescher (EGI) * Claudio Prandoni (Promoter) * Lajos Balint (NIIFI) * Maciej Brzezniak (PSNC) * Patrizia Martini (ICCU) * Giovanni Ciccaglioni (ICCU)...")
 
 
Line 33: Line 33:
* Provide Easter holidays details to Michel to better plan sprint 3 and 4
* Provide Easter holidays details to Michel to better plan sprint 3 and 4
* Next meetings (second sprint review + third sprint planning) will be called by Michel
* Next meetings (second sprint review + third sprint planning) will be called by Michel
[[Category:Proofs Of Concept]]

Latest revision as of 18:40, 19 March 2013

Participants

  • Michel Drescher (EGI)
  • Claudio Prandoni (Promoter)
  • Lajos Balint (NIIFI)
  • Maciej Brzezniak (PSNC)
  • Patrizia Martini (ICCU)
  • Giovanni Ciccaglioni (ICCU)
  • Rosette Vandenbroucke (BELSPO)

Topics

Agenda

  • Sprint 1 review
  • Sprint 1 retrospective
  • Sprint 2 planning

Meeting infrastructure

Due to audio issues last time with Adobe Connect and as preferred by call members, from now on the call will be held using Skype.

Discussion

  • Review planned tasks for sprint 1 in http://go.egi.eu/DCH-RP-WP5-Backlog (all team members)
  • Move un-finished tasks to sprint 2 (all team members)
  • Add tasks to backlog as required (Product Owners Borje and Rosette + all)
  • Prioritise unprioritised tasks (Product Owners Borje and Rosette + all)
  • Effort estimation for un-estimated tasks (Project team, supported by facilitator & product owners)
  • Team commits to a number of tasks for Sprint 2 (project team)

Main decisions

  • All the issues that have been discussed and the action items for the next two weeks are reported in the backlog file: http://go.egi.eu/DCHRP-WP5-Backlog
  • Decision to keep together sprint review and planning meetings
  • Provide Easter holidays details to Michel to better plan sprint 3 and 4
  • Next meetings (second sprint review + third sprint planning) will be called by Michel