PDT:MOU advancement
Jump to navigation
Jump to search
MoU Advancement
Late Milestones
- LSCG M1.1: Outline LSGC's areas of expertise (June 2011)
- GISELA M1.1 (A.1) The milestone is achieved by advertising the start of the
- EMI М1.3: Report defining the strategy for managing software releases and repositories
Balazs will provide a report by 10th May 2011
This activity will not be done as there is another milestone to hold this kind of meeting at the TF, therefore, this one cannot be moved to there. StratusLab held a workshop and a training course as well as participated in the UVW in May, but each had a specified milestone marked as "achieved".
- StratusLab M6.1: Establish agreement for delivery of StratusLab software for UMD (May 2011)
- StratusLab M7.1: Establish GGUS support team to support sites running StratusLab (May 2011)
Sep 2011
Expected
Achieved
Aug 2011
Expected
Achieved
Jul 2011
Expected
- LSCG M2.1: List of applications and services needed by LSGC from the EGI community (July 2011)
- gSLM M2.1: Report proposing alignments of EGI terminology as in use within ITSM (July 2011)
- DECIDE M5.1: Both parties announcement agreement on websites (July 2011)
Achieved
Jun 2011
Achieved
- LSCG M6.1: Announce the collaboration agreement on project websites
- gSLM M4.1: Submit a proposal for tutorial at the EGI TF 2011
- SAGA M4.1 The milestone is achieved by advertising the start of the collaboration (April 2011)
- SAGA M1.1: Requires a report listing the inputs to the UMD Roadmap for the EGI-InSPIRE deliverable due in July 2011
May 2011
Achieved
- WeNMR A.5: A.3 Participation in UCB Alexandre Bonvin has attended these meetings and is documented in the UCB Minutes
Planned for next month
MoU Status
- MoU Status (Signed, Negotiation Phase, Planned, DocDB link, Process Owner, etc.)