Difference between revisions of "EGI-InSPIRE:Plan 2013 SA1.4"
Jump to navigation
Jump to search
Line 9: | Line 9: | ||
<!-- please make sure that the text here is self explanatory and sufficiently detailed--> | <!-- please make sure that the text here is self explanatory and sufficiently detailed--> | ||
* | * SAM monitoring of operations tools | ||
** | ** Central OPS-Monitor instance (https://ops-monitor.cern.ch/nagios/) was deployed in November 2012 after SAM Update-19 release. | ||
* MSG: implementation of test message broker network | |||
* | * MSG: staged message broker network upgrades | ||
** Four staged upgrades performed in 2012: January 31st, June 1st, November 7th and November 28th. | |||
* CIC portal | * CIC portal decommissioned | ||
** Decommission of the old CIC portal (cic.egi.eu) was performed on April 25th. | |||
* Deployment of VO operations dashboard | |||
** VO Dashboard was included in Operations Portal 2.9, released on February 15th. | |||
* Site A/R monitoring | |||
** Probe for site A/R monitoring was included in Operations Portal 2.9.6, released on September 27th. | |||
===Milestones not accomplished=== | ===Milestones not accomplished=== |
Revision as of 09:22, 22 January 2013
Assessment of progress in 2012
Completed Activities and Milestones
- SAM monitoring of operations tools
- Central OPS-Monitor instance (https://ops-monitor.cern.ch/nagios/) was deployed in November 2012 after SAM Update-19 release.
- MSG: implementation of test message broker network
- MSG: staged message broker network upgrades
- Four staged upgrades performed in 2012: January 31st, June 1st, November 7th and November 28th.
- CIC portal decommissioned
- Decommission of the old CIC portal (cic.egi.eu) was performed on April 25th.
- Deployment of VO operations dashboard
- VO Dashboard was included in Operations Portal 2.9, released on February 15th.
- Site A/R monitoring
- Probe for site A/R monitoring was included in Operations Portal 2.9.6, released on September 27th.