Difference between revisions of "EGI-InSPIRE:Plan 2013 SA1.3"
Jump to navigation
Jump to search
Milestones not accomplished
Line 35: | Line 35: | ||
== Plans for 2013 == | == Plans for 2013 == | ||
*Providing support to the current UMD-1 and UMD-2 releases. | |||
* Providing support to the current UMD-1 and UMD-2 releases. | *Preparation for the next and final EMI-3 release together with the IGE final releases. | ||
* Preparation for the next and final EMI-3 release together with the IGE final releases. | *Making a final effort to get EA to the missing components list [https://wiki.egi.eu/wiki/EGI_Quality_Criteria_Verification#Verification_engineer_skill_matrix]. | ||
* Making a final effort to get EA to the missing components list [https://wiki.egi.eu/wiki/EGI_Quality_Criteria_Verification#Verification_engineer_skill_matrix]. | *Evaluate and propose changes and improvements in the SW workflow, in order to adapt to the Post-EMI/IGE. In order to fulfill this task, continue a close collaboration between SA1.3 and SA2 in order to accommodate the necessary changes. | ||
* Evaluate and propose changes and improvements in the SW workflow, in order to adapt to the Post-EMI/IGE. In order to fulfill this task, a close collaboration | *Continuing to follow the Virtualization and Cloud Task Force, and access it's implications to the SW provisioning. | ||
* Continuing to follow the Virtualization and Cloud Task Force, and access it's implications to the SW provisioning. | * | ||
* | |||
'''Unicore''' | '''Unicore''' |
Revision as of 19:16, 18 January 2013
Staged rollout
Assessment of progress in 2012
Completed Activities and Milestones
Milestones not accomplished
Plans for 2013
Interoperations
Assessment of progress in 2012
Completed Activities and Milestones
- Finalize integration of UNICORE tests into SAM monitoring framework.
- Definition of tests used for certification of UNICORE and Globus sites. As part of this activity tests will be included in set of operations tests (PROC06)
Milestones not accomplished
- Integration of Desktop Grids sites into EGI operational tools.
- Integration of MAPPER sites running QoSGrid middleware into EGI operational tools.
- Missing Early Adopter teams for some middleware components [1]
Plans for 2013
- Providing support to the current UMD-1 and UMD-2 releases.
- Preparation for the next and final EMI-3 release together with the IGE final releases.
- Making a final effort to get EA to the missing components list [2].
- Evaluate and propose changes and improvements in the SW workflow, in order to adapt to the Post-EMI/IGE. In order to fulfill this task, continue a close collaboration between SA1.3 and SA2 in order to accommodate the necessary changes.
- Continuing to follow the Virtualization and Cloud Task Force, and access it's implications to the SW provisioning.
Unicore
- Accounting and Information System integration.
Mapper/QCG
- Accounting, Support and Information System integration.
- Definition of tests used for certification. As part of this activity tests will be included in set of operations tests (PROC06)
Desktop grid
- Accounting, Support and Information System integration.
- Definition of tests used for certification. As part of this activity tests will be included in set of operations tests (PROC06)
Globus
- Accounting and Information System integration.