Difference between revisions of "EGI-InSPIRE:Italy-QR6"
Jump to navigation
Jump to search
Line 63: | Line 63: | ||
| EGI-TF | | EGI-TF | ||
| 10 | | 10 | ||
| Participation in different sessions | | Participation in different sessions(Presentation: “Storage accounting with DGAS and HLRmon"). The poster on the IGI portal has been awarded as the best of the event | ||
|- | |||
| September 19-23, 2011 | |||
| Lyon | |||
| OGF 33 | |||
| 1 | |||
| Presentation and discussion: “Next Generation Usage Records" | |||
|} | |} | ||
Line 84: | Line 90: | ||
== 2. ACTIVITY REPORT == | == 2. ACTIVITY REPORT == | ||
<!--''Note: just report activities relevant to this Quarter.''--> | <!--''Note: just report activities relevant to this Quarter.''--> | ||
==== 2.1.1. GARR ==== | |||
==== 2.1.2. INFN ==== | |||
IGI statutes and legal structure are being finalized, while IGI has started working as INFN Special Project, with expected duration of about 1 year, which will end when IGI will start as an independent legal structure. | |||
*'''Resource centers coordination''' | |||
** good overall results in the league table for this quarter: May (98%/98%), June (97%/97%), July (NA); | |||
** Operation problems are discussed in the regular coordination meeting. The ROD team works well. Grid services are maintained up-to-date, but services have not been migrated to EMI/UMD yet. | |||
** Two new sites (INFN-MIB and GARR-01-DIR) have been certified during this quarter. | |||
*'''Core Services''' | |||
** In the reported period the operation team keeps the Grid core services running smoothly and updated in the region. | |||
*'''Early Adopter activity''' | |||
** Early adopter activity has been carried out for several products: | |||
*** WMS | |||
**** 3.3.2 (started at the end of july and finished in the first part of August) rejected from UMD | |||
**** 3.3.3 (~06.09.2011) rejected from UMD | |||
**** 3.3.4 (20.10.2011) was performed for EMI but rejected (did not reached the Staged Rollout in UMD) | |||
** Early adopter activity for Nagios regarded the updates 10.1, 11 and 11.1. While the 10.1 was a fix for an issue with gLExec profile into update 10, update 11.1 contained a fix for a failure we encountered at yaim config time during update 10. Temporary fix to the problem has been implemented manually removing a column index into metric store database. | |||
===2.2. Main Achievements=== | ===2.2. Main Achievements=== | ||
Revision as of 16:03, 3 November 2011
Quarterly Report Number | NGI Name | Partner Name | Author |
---|---|---|---|
QR6 | IGI | GARR | M. Reale |
QR6 | IGI | INFN | L. Gaido, P. Veronesi |
1. MEETINGS AND DISSEMINATION
1.1. CONFERENCES/WORKSHOPS ORGANISED
Date | Location | Title | Participants | Outcome (Short report & Indico URL) |
---|---|---|---|---|
1.2. OTHER CONFERENCES/WORKSHOPS ATTENDED
Date | Location | Title | Participants | Outcome (Short report & Indico URL) |
---|---|---|---|---|
September 19-23, 2011 | Lyon | EGI-TF | 10 | Participation in different sessions(Presentation: “Storage accounting with DGAS and HLRmon"). The poster on the IGI portal has been awarded as the best of the event |
September 19-23, 2011 | Lyon | OGF 33 | 1 | Presentation and discussion: “Next Generation Usage Records" |
1.3. PUBLICATIONS
Publication title | Journal / Proceedings title | Journal references Volume number Issue Pages from - to |
Authors 1. 2. 3. Et al? |
---|
2. ACTIVITY REPORT
2.1.1. GARR
2.1.2. INFN
IGI statutes and legal structure are being finalized, while IGI has started working as INFN Special Project, with expected duration of about 1 year, which will end when IGI will start as an independent legal structure.
- Resource centers coordination
- good overall results in the league table for this quarter: May (98%/98%), June (97%/97%), July (NA);
- Operation problems are discussed in the regular coordination meeting. The ROD team works well. Grid services are maintained up-to-date, but services have not been migrated to EMI/UMD yet.
- Two new sites (INFN-MIB and GARR-01-DIR) have been certified during this quarter.
- Core Services
- In the reported period the operation team keeps the Grid core services running smoothly and updated in the region.
- Early Adopter activity
- Early adopter activity has been carried out for several products:
- WMS
- 3.3.2 (started at the end of july and finished in the first part of August) rejected from UMD
- 3.3.3 (~06.09.2011) rejected from UMD
- 3.3.4 (20.10.2011) was performed for EMI but rejected (did not reached the Staged Rollout in UMD)
- WMS
- Early adopter activity for Nagios regarded the updates 10.1, 11 and 11.1. While the 10.1 was a fix for an issue with gLExec profile into update 10, update 11.1 contained a fix for a failure we encountered at yaim config time during update 10. Temporary fix to the problem has been implemented manually removing a column index into metric store database.
- Early adopter activity has been carried out for several products:
2.2. Main Achievements
2.3. Issues and mitigation
Issue Description | Mitigation Description |
---|