Difference between revisions of "EGI-InSPIRE:Quarterly reports"
Line 1: | Line 1: | ||
== | == EGI-InSPIRE Effort reporting == | ||
{{TOC_right}} | {{TOC_right}} | ||
Revision as of 15:03, 29 March 2011
EGI-InSPIRE Effort reporting
These are formal deliverables for the European Commission, applicable to all members of the EGI-InSPIRE project, beneficiaries and Joint Research Unit members, as well as its collaborating projects.
EGI-InSPIRE Effort reporting
The schedule is described below with reference to days after the end of the month for the submission of the timesheets using PPT:
• M+10 calendar days: Timesheet deadline
• M+15 calendar days: Timesheet Validation
The contributions will be assembled and edited by the PO. Issues requiring clarification will be identified and communicated to the PO:
• PQ+25: PO circulates a final version to the PMB for review
• PQ+30: Submit to EC
Period 1 PQ1: May-July 2010 PQ2: Aug-Oct 2010 PQ3: Nov10- Jan 2011 PQ4: Feb-Apr 2011
Period 2 PQ1: May-July 2011 PQ2: Aug-Oct 2011 PQ3: Nov10- Jan 2012 PQ4: Feb-Apr 2012
Period 3 PQ1: May-July 2012 PQ2: Aug-Oct 2012 PQ3: Nov10- Jan 2013 PQ4: Feb-Apr 2013
Period 4 PQ1: May-July 2013 PQ2: Aug-Oct 2013 PQ3: Nov10- Jan 2014 PQ4: Feb-Apr 2014
Period 1
Q1 May-June-July 2010
EGI-report-Q1-by-Members.pdf [1]
Period 2
Q2 Aug-Oct 2010
EGI-report-Q1&Q2-by-Members.xls [2]
EGI cumulative reports in excel (activity per member Q1, Q2 and cumulated; finance Q1, Q2 and cumulated) [3]